GovChime
AWARDDEFINITIVE CONTRACTOther than small business

Definitive contract 80HQTR19C0024HONEYBEE ROBOTICS, LTD.

Overview

Award facts

Net obligations
$3.92M
$3,924,956of $3.92M potential value
Outlays (paid to date)
$3.74M
$3.74M paid of $3.92M obligated$3,737,590
Period of performance
Apr 19, 2019 to Oct 18, 2023
Ended
Modifications
22
Latest action Jan 18, 2024
Contract type
Definitive contract
PIID 80HQTR19C0024

Contract value is the most the government could spend; obligations are what it has legally committed; outlays are what it has actually paid.

Description of requirement

REDWATER COMBINES THE TWO TECHNOLOGIES INTO ONE: IT USES THE CT APPROACH TO CREATE A HOLE (FIGURE 1). ONCE THE HOLE IS MADE, THE COILED TUBING IS LEFT IN THE HOLE AND USED AS CONDUIT FOR WATER EXTRACTION. THE BHA CONTAINS A ROTARY-PERCUSSIVE DRILL SUBSYSTEM (SIMILAR TO THE ONE USED IN HONEYBEE ROBOTICS DEEP DRILL3), A DOWNHOLE PUMP, AND HEATERS. THE TUBE HOUSES AN INSULATED AND HEATED HOSE AS WELL AS WIRES FOR DOWNHOLE MOTORS AND HEATERS. DURING DRILLING, COMPRESSED GAS IS SEND DOWNHOLE THROUGH THE HOSE. THE GAS ESCAPES THROUGH THE ANNUAL SPACE BETWEEN THE TUBE AND BOREHOLE WALL AND REMOVES CHIPS THAT CAN BE COLLECTED AND ANALYZED FOR SCIENCE. UPON REACHING AN ICE LAYER, THE DRILL CONTINUES FOR ANOTHER 3 M AND THEN STOPS ADVANCING FORWARD, BUT THE BIT CONTINUOUS SPINNING. HEATERS ARE TURNED ON TO MELT THE SURROUNDING ICE. ONCE ICE STARTS TO MELT, THE PERISTALTIC PUMP STARTS PUMPING A FRACTION OF THE MELTED WATER UP THE SAME HOSE THAT WAS USED FOR THE COMPRESSED GAS, AND INTO A STORAGE TANK ON THE SURFACE VIA A 3-WAY HEATED VALVE (VALVE SWITCHES BETWEEN THE GAS TANK AND WATER TANK). THE REMAINING WATER PASSES THROUGH A DOWNHOLE HEATER AND IS PUMPED INTO THE ROTATING BIT FOR WATER JETTING THIS CONTINUOUS STIRRING OF WATER AND INJECTION OF HOT WATER SPEEDS UP THE MELTING PROCESS. AFTER MELTING A SECTION OF ICE, THE CT IS REACTIVATED TO DRILL FURTHER AND THE MELTING PROCESS CONTINUES. SINCE ATMOSPHERIC PRESSURE AT ARCADIA PLANITIA IS ABOVE THE TRIPLE POINT OF WATER, LIQUID WATER CAN EXIST. HOWEVER, IT IS UNSTABLE AND CAN BOIL OFF VERY QUICKLY. FOR THIS REASON, IT WOULD BE DESIRABLE TO SEAL OFF THE HOLE. THIS CAN BE ACHIEVED VIA ACTIVE MEANS (A PACKER CAN EXPAND IN A HOLE AND SEAL THE ANNULAR SPACE BETWEEN THE TUBE AND THE BOREHOLE) OR PASSIVE MEANS (WATER VAPOR WOULD RE-CONDENSE ON THE COLD BOREHOLE WALL AND SEAL IT THIS IN FACT HAS BEEN OBSERVED). THE TUBE WOULD HAVE TO BE HEATED TO FREE ITSELF UP BEFORE CONTINUING FURTHER DOWN, WHEN NEEDED. OUR PNEUMATIC EXCAVATION TESTS AT 7 TORR SHOWED PENETRATION RATES OF 1 M/MIN IN REGOLITH4. THE MASS RATIO OF GAS USED TO MATERIAL REMOVED OUT OF THE HOLE WAS 1:500. ASSUMING A 5 CM DIAMETER HOLE (CURRENT BASELINE FOR REDWATER), THE REQUIRED MASS OF GAS WOULD BE 10 KG. MOST OF THE SOURCES OF COMPRESSED GAS ARE AT HIGH TRL. GAS CAN BE BROUGHT FROM THE EARTH (MARS2020 MISSION BRINGS A TANK OF COMPRESSED N2 TO BLOW DUST OFF ROCKS), HELIUM PRESSURANT CAN BE USED FROM LANDED SYSTEMS, ROCKET FUEL CAN BE BURNED AND TURNED INTO GAS, AND ISRU GASSES (H2/O2) COULD ALSO BE USED. FINALLY, A COMPRESSOR COULD COMPRESS MARTIAN AIR. MOXI ON MARS2020 HAS A COMPRESSOR THAT WOULD TAKE 100 HOURS TO COMPRESS 10 KG OF CO2 FROM 7 TORR TO 760 TORR. TO EXTRACT THE REQUIRED 16 TONS OF WATER, A POOL OF APPROXIMATELY 3.1 M IN DIAMETER HAS TO BE CREATED, WHICH IS FEASIBLE. THE PROCESS OF WATER EXTRACTION WOULD TAKE SEVERAL WEEKS. OUR THERMAL MODELS USING MATHCAD AS WELL AS CALCULATIONS SHOW THAT REQUIRE HEAT FOR MELTING IS 1.5 KW AND FOR KEEPING THE WATER HOSE WARM ALONG THE 25 M LENGTH IS 1 KW. FIGURE 1 SHOWS REDWATER SYSTEM ON ATHLETE ROVER. IT USES SOLAR PANELS AND MMRTG TO PROVIDE ELECTRICAL POWER AND HEAT. FIGURE 2 SHOWS REDWATER IN ITS STORED CONFIGURATION FOR LAUNCH WHILE FIGURE 3 SHOWS THE UNDERCARRIAGE AND BHA.

Dates and value

Award date
Signed on Apr 19, 2019
Potential end of performance
Oct 17, 2023
Current value
$3,924,956Base and exercised options
Potential value (if all options are exercised)
$3,924,956

Obligations by fiscal year of action

  • FY2021: $1,499,047
  • FY2020: $1,133,849
  • FY2019: $1,292,060

Total across 3 fiscal years: $3,924,956

Source: Federal Procurement Data System contract actions as published by SAM.gov and USAspending.gov; latest action recorded Jan 18, 2024. View on USAspending · Recipient on SAM.gov

Recipient

LocationBROOKLYN, NY
UEIF7UHKQTEYHW8
CAGE code0LTS6
Business sizeOther than small businessSize at award, per the contracting officer
Organization typeCorporate not tax exempt
Parent companyENSIGN-BICKFORD INDUSTRIES, INC.

Business types and certifications

For-profit organizationSubchapter S corporationCorporation (not tax-exempt)

As represented in SAM.gov at the time of the action.

Subcontracting network

The prime, the subcontractors on this award, and their own subcontractors.

Subaward amounts are self-reported by prime contractors to SAM.gov and appear 1 to 2 months after the work. Duplicates are removed on a best-effort basis. Totals are incomplete and not an audit. Source: USAspending.

Agency and place

Awarding and funding

Awarded by
  1. National Aeronautics and Space Administration
  2. NASA KENNEDY SPACE CENTER
Funded by
  1. National Aeronautics and Space Administration
  2. NASA KENNEDY SPACE CENTER
Funded from
Space technology (DIRECT)Program activities080-0131Federal accounts (agency financial reports)

Place of performance

Place of performance
Pasadena, Los Angeles County, California 91103-1003
Congressional district (place of performance)
CA-28As reported at the time of the action

Classification and competition

Classification

Competition

Extent competed
Full and open competitionA
Solicitation procedures
Negotiated proposal/quoteNP
Set-aside
No set-aside used
Contract pricing
Firm fixed priceJ
Offers received
44

Solicitation and notices

Solicitation ID
NNH16ZCQ001K-ISRU
Notices

Contract details

Subcontracting plan
Plan not included - no subcontracting possibilitiesA
Cost Accounting Standards clause
Not applicable exempt from CASX
Certified cost or pricing data
Yes
Commercial procedures
Commercial products/services procedures not usedD
Government-furnished property
Transaction does not use GFE/GFPN
Bundled requirement
Not bundledH
Consolidated requirement
Not consolidatedD
Undefinitized action (terms not final)
No
Multi-year contract
No
Performance-based service acquisition
No - service where PBA is not used.N

Linked notices

Notice
Notice ID
Type
Link
Posted

Transaction history

Modification history

Base award
Apr 19, 2019
Latest action
Jan 18, 2024 — Supplemental agreement (within scope)Modification P00022
Latest substantive action
Jan 18, 2024 — Supplemental agreement (within scope)Modification P00022
Latest funding action
Jul 28, 2021 — Funding onlyModification P00015; obligation change +$250,000; funding only: changes obligations, not scope
Actions by type
  • Base award1
  • Supplemental agreement (within scope)10
  • Funding only5
  • Other administrative action5
  • Option exercised1
  • Change order definitized1
23 actions recorded, Apr 19, 2019 to Jan 18, 2024; each action counted once.

Similar awards

PIID
Match
Awardee

All contract data

All contract data

Every other field reported for this award, as of its latest reported action

Competition

Evaluation preference
No preference used
Local area set-aside
No
Synopsized publicly (SAM.gov / FedBizOpps)
Yes
Simplified procedures for commercial items
No
A-76 (FAIR Act) action
No

Pricing and financing

Paid by purchase card
No

Socio-economic and policy

Inherently governmental functions
Other functionsOT
Recovered materials and sustainability
Environmentally preferableF
EPA-designated product
Not requiredE
Clinger-Cohen Act planning (IT)
No

Place and origin

Domestic or foreign entity
U.S. owned businessA
Country of product or service origin
United statesUSA
Place of manufacture
Not a manufactured end productC

Structure

Award or IDV
Award
Award type
Definitive contractD
Awarding agency code
8000
Awarding sub-tier code
8000
Contracting office code
80KSC0
Transactions recorded under this award key
23

Funding

Funding agency code
8000
Funding sub-tier code
8000
Funding office code
80KSC0
Treasury accounts
  • 080-2019/2020-0131-000
  • 080-2020/2021-0131-000
  • 080-2021/2022-0131-000
Object classes
  • 25.2: Other services from non-Federal sources
  • 25.5: Research and development contracts
Disaster or emergency funding (DEFC)
  • Q: Not Designated Nonemergency/Emergency/Disaster/Wildfire Suppression