GovChime
AWARDPOSmall business

Po AG4423P080005MIDWAY CONSTRUCTION SERVICE, INC

Overview

Award facts

Period of performance
Dec 15, 2008 to Oct 2, 2008
Ended
Modifications
1
Latest action Dec 15, 2008
Contract type
Po
PIID AG4423P080005

Description of requirement

STREAMBANK STABILIZATION ON SPRINGHILL CHURCH ROAD

Dates and value

Award date
Signed on Mar 4, 2008
Potential end of performance
Oct 16, 2008

Source: Federal Procurement Data System contract actions as published by SAM.gov and USAspending.gov; latest action recorded Dec 15, 2008. View on USAspending · Recipient on SAM.gov

Recipient

LocationROLLING FORK, MS
UEIETKLKK4PWVF9
Business sizeSmall businessSize at award, per the contracting officer

Business types and certifications

Minority-ownedHUBZone firmCorporation (not tax-exempt)

As represented in SAM.gov at the time of the action.

Subcontracting network

The prime, the subcontractors on this award, and their own subcontractors.

Subaward amounts are self-reported by prime contractors to SAM.gov and appear 1 to 2 months after the work. Duplicates are removed on a best-effort basis. Totals are incomplete and not an audit. Source: USAspending.

Agency and place

Awarding and funding

Place of performance

Place of performance
Waynesboro, Wayne County, Mississippi 39367-2616
Congressional district (place of performance)
MS-04As reported at the time of the action

Classification and competition

Classification

Competition

Extent competed
Full and open competitionA
Solicitation procedures
Simplified acquisitionSP1
Set-aside
No set-aside used
Contract pricing
Firm fixed priceJ
Offers received
8

Solicitation and notices

Solicitation ID
AG-4423-S-08-0006
Notices

Contract details

Cost Accounting Standards clause
Not applicable exempt from CASX
Government-furnished property
Transaction does not use GFE/GFPN
Consolidated requirement
No
Undefinitized action (terms not final)
No
Multi-year contract
No
Performance-based service acquisition
No - service where PBA is not used.N

Linked notices

Notice
Notice ID
Type
Link
Posted

Transaction history

Modification history

Base award
Mar 4, 2008Base obligation at award: $48,009
Latest action
Dec 15, 2008 — Funding onlyModification 1; obligation change +$152; funding only: changes obligations, not scope
Latest funding action
Dec 15, 2008 — Funding onlyModification 1; obligation change +$152; funding only: changes obligations, not scope
Actions by type
  • Base award1
  • Funding only1
2 actions recorded, Mar 4, 2008 to Dec 15, 2008; each action counted once.

Similar awards

PIID
Match
Awardee

All contract data

All contract data

Every other field reported for this award, as of its latest reported action

Competition

Evaluation preference
No preference used
Synopsized publicly (SAM.gov / FedBizOpps)
Yes
Simplified procedures for commercial items
No

Pricing and financing

Paid by purchase card
No
Latest action: change in base and exercised options
$152
Latest action: change in base and all options
$152

Socio-economic and policy

Recovered materials and sustainability
No clauses included and no sustainability incluC
EPA-designated product
Not requiredE
National interest action
Hurricane katrina 2005H05K
Construction wage rates (Davis-Bacon)
Yes

Structure

Award or IDV
Award
Award type
PoB
Awarding agency code
1200
Awarding sub-tier code
12C3
Contracting office code
4423
Transactions recorded under this award key
2

Funding

Funding agency code
999