Dca DTFAGL08C00347DSM EXTERIORS INC
Overview
Award facts
- Period of performance
- Sep 18, 2008 to Oct 31, 2008
- Ended
- Modifications
- 0
- Latest action Sep 18, 2008
- Contract type
- Dca
- PIID DTFAGL08C00347
Description of requirement
REMOVAL AND REPLACEMENT OF THE DUPAGE (DPA) VOR METAL ROOF WITH A NEW SINGLE PLY MEMBRANE ROOF SYSTEM. *** TECHNICAL QUESTIONS MAY BE REFERRED TO DAVE WEBER AT 847.508.5814. ALL OTHER QUESTIONS SHALL BE REFERRED TO LOIS FLICK AT 847.608.5743. *** SCOPE OF WORK: THE CONTRACTOR SHALL ACT ASA GENERAL CONTRACTOR AND SHALL FURNISH ALL LABOR, MATERIALS, SERVICES, INSURANCE, EQUIPMENT, ETC. TO REPLACE THE STAINLESS STEEL TERNE-PLATED METAL ROOF WITH A NEW SINGLE PLY ROOF MEMBRANE SYSTEM AT THE DUPAGE VOR, WEST CHICAGO, ILLINOIS. THIS WORK CONSISTS OF, BUT IS NOT LIMITED TO, THE FOLLOWING PRINCIPLE ITEMS: A. REMOVAL AND DISPOSAL OF THE EXISTING STAINLESS STEEL TERNE-PLATED METAL ROOF, INCLUDING ROSIN PAPER AND BASE FELT DOWN TO THE PLYWOOD DECKING. B. REMOVAL AND REPLACEMENT OF APPROXIMATELY 500 BOARD FEET OF 2X6 ROTTED WOOD DECKING. C. REMOVAL AND REINSTALLATION OF EIGHT (8) LADDER ANCHOR PLATES AROUND THE FIBERGLASS ANTENNA CONE IN LOCATIONS SHOWN ON THE PLANS. D. FURNISH AND INSTALL NEW 2"X8" PRESSURE TREATED WOOD NAILERS AROUND THE PERIMETER OF THE COUNTERPOISE ROOF. E. FURNISH AND INSTALL NEW GRACE & COMPANY ICE AND WATER SHIELD OR APPROVED EQUAL SELF-ADHERED WATER PROTECTION MEMBRANE, INCLUDING ALL RELATED MATERIALS REQUIRED FOR A COMPLETE INSTALLATION. F. FURNISH AND INSTALL NEW GALVANIZED 1/2" X 1/2", 16GA. STEEL MESH ON THE EXISTING WOOD DECK. G. FURNISH AND INSTALL NEW 1 1/2" OF POLYISOCYANURATE INSULATION TO THE ROOF SURFACE, EXCLUDING THE AREA WITHIN THE FIBERGLASS SHELTER. H. FURNISH AND INSTALL NEW SINGLE PLY FULLY ADHERED, PVC ROOF MEMBRANE OVER THE ENTIRE ROOF SURFACE AND INTERIOR OF THE FIBERGLASS ANTENNA SHELTER, INCLUDING FABRICATION AND INSTALLATION OF NEW SINGLE-PLY MEMBRANE, COPPER FLASHING, AND INSTALLATION OF NEW GROUND CONDUCTOR. I. FURNISH AND INSTALL NEW SINGLE-PLY WALKWAY TREADS FROM LADDER SUPPORTS AT ROOF EDGE TO THE ANTENNA SHELTER AND AROUND THE SHELTER, INCLUDING THE INSTALLATION OF NON-SLIP GRANULARS EMBEDDED IN ADHESIVE OVER THE NEW WALKWAY TREADS. J. FURNISH ANDSETUP ONE 56 FEET DIAMETER TARPAULIN TO COVER THE ROOF DURING INCLEMENT WEATHER DURING CONSTRUCTION. K. REPAINTING OF THE FIBERGLASS ANTENNA SHELTER INCLUDING REMOVAL OF THE DME ANTENNA, REMOVAL AND REINSTALLTION OF THE FIBERGLASS ANTENNA FABRICATION AND INSTALLATION OF NEW COPPER GROUND SEGMENTS ON THE ANTENNA SHELTER BASE. L. INSTALLATION OF A NEW 120V GFI OUTLET LOCATED IN THE ANTENNA SHELTER. M. ALL RELATED FABRICATION, INSTALLATION, ELECTRICAL AND GROUNDING WORK REQUIRED FOR A COMPLETE INSTALLATION. *** LETTER TO AIR TRAFFIC OFFICE/LETTER TO AIRPORT DISTRICT OFFICE/NOTICE OF PROPOSED CONSTRUCTION OR ALTERATION/NS STUDY: N/A SHUTDOWN SCHEDULE: THIS FACILITY WILL BE SHUT DOWN FOR 14 CALENDAR DAYS TO COMPLETE THIS PROJECT. THE SHUTDOWN WILL BE COORDINATED BY THE ELGIN TSOC ONCE A CONTRACT HAS BEEN AWARDED. FLIGHT CHECK: FLIGHT CHECK WILL BE REQUIRED WHEN ALL WORK HAS BEEN COMPLETED AND WILL BE COORDINATED BY THE ELGIN TSOC. PERFORMANCE TIME: ALL WORK IS TO BE ACCOMPLISHED DURING THE 14 CALENDAR DAY SHUTDOWN. THE CONTRACTOR SHALL ADJUST HIS/HER WORK SCHEDULE ACCORDINGLY TO ACCOMPLISH THIS WORK DURING THE FACILITY SHUTDOWN AT NO ADDITIONAL COST TO THE GOVERNMENT. PROJECT SCHEDULE: THIS WORK SHALL TAKE PLACE ONLY WHEN OUTDOOR TEMPERATURES ARE ABOVE 50 DEGREES FARENHEIGHT OR AS REQUIRED BY THE ROOF SYSTEM MANUFACTURER. MATERIALS: FURNISH AND DELIVER ALL MATERIALS AS DESCRIBED IN THE DRAWINGS AND SPECIFICATIONS (PROJECT FAA-C90-207) DATED 3/1/08. GOVERNMENT FURNISHED MATERIALS: THE GOVERNMENT SHALL FURNISH NEW ANTENNA SHELTER GASKET(S) AND ANTENNA SHELTER LIFTING SLING TO THE CONTRACTOR FOR USE AS PART OF THIS PROJECT. INSPECTION: RESIDENT ENGINEER ON THIS PROJECT WILL BE DAVE WEBER, TECHNICAL SUPPORT GROUP, ELGIN, IL. HIS TELEPHONE NUMBER IS 487.608.5814. MR. WEBER HAS COMPLETED COTR TRAINING. PROJECT FUNDING: APPROVED FY-08 UIS OPS FU
Dates and value
- Award date
- Signed on Sep 18, 2008
- Potential end of performance
- Oct 30, 2008
Source: Federal Procurement Data System contract actions as published by SAM.gov and USAspending.gov; latest action recorded Sep 18, 2008. View on USAspending · Recipient on SAM.gov
Recipient
Business types and certifications
As represented in SAM.gov at the time of the action.
Subcontracting network
The prime, the subcontractors on this award, and their own subcontractors.
Agency and place
Awarding and funding
- Awarded by
- Department of Transportation
- Federal Aviation Administration
- DEPT OF TRANS/FEDERAL AVIATION ADMIN
Place of performance
- Place of performance
- Saint Charles, Kane County, Illinois 60175-8101
- Congressional district (place of performance)
- IL-11As reported at the time of the action
Classification and competition
Classification
- Product or service (PSC)
- Z123MAINT-REP-ALT/RADAR & NAV FAC (service)
Competition
- Extent competed
- Not competedC
- Solicitation procedures
- Simplified acquisitionSP1
- Set-aside
- No set-aside used
- Contract pricing
- Firm fixed priceJ
- Offers received
- 1
Contract details
- Subcontracting plan
- Plan not requiredB
- Cost Accounting Standards clause
- Not applicable exempt from CASX
- Government-furnished property
- Transaction does not use GFE/GFPN
- Bundled requirement
- Not a bundled requirementD
- Consolidated requirement
- No
- Undefinitized action (terms not final)
- No
- Multi-year contract
- No
- Performance-based service acquisition
- No - service where PBA is not used.N
Linked notices
Notice | Notice ID | Type | Link | Posted |
|---|---|---|---|---|
Transaction history
Modification history
- Base award
- Sep 18, 2008Base obligation at award: $68,155
- Latest action
- Sep 18, 2008 — Base awardModification 0; obligation change +$68,155
- Actions by type
- Base award1
Similar awards
PIID | Match | Awardee |
|---|---|---|
All contract data
All contract data
Every other field reported for this award, as of its latest reported action
Competition
- Evaluation preference
- No preference used
- Simplified procedures for commercial items
- No
Pricing and financing
- Paid by purchase card
- No
- Latest action: change in base and exercised options
- $68,155
- Latest action: change in base and all options
- $68,155
Socio-economic and policy
- Recovered materials and sustainability
- No clauses included and no sustainability incluC
- EPA-designated product
- Not requiredE
- Construction wage rates (Davis-Bacon)
- No
Structure
- Award or IDV
- Award
- Award type
- DcaD
- Awarding agency code
- 6900
- Awarding sub-tier code
- 6920
- Contracting office code
- 00014
- Transactions recorded under this award key
- 1
Funding
- Funding agency code
- 999