Definitive contract NNA13AA05CC. OVERAA & CO./BAYVIEW ENGINEERING & CONSTRUCTION A JOINT VENT

Overview

Award facts

Net obligations
$33.76M
$33,760,235of $33.76M potential value
Period of performance
Aug 8, 2018 to Jul 31, 2018
Ended
Modifications
55
Latest action Aug 8, 2018
Contract type
Definitive contract
PIID NNA13AA05C

Description of requirement

IGF::OT::IGF CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIAL, EQUIPMENT, TRANSPORTATION, SUPERVISION, AND INSPECTION TO REPLACE ARC JET COMPLEX STEAM VACUUM SYSTEM (SVS) BOILER AT NASA AMES RESEARCH CENTER AS PER THE CONTRACT AND SPECIFICATIONS. CONTRACT INCLUDES: (1) THREE LOW EMISSION, HIGH PRESSURE STEAM BOILERS; (2) DEAERATOR HEATER AND FEED WATER STORAGE TANK(S); (3) BOILER NOX REDUCTION SYSTEMS. (4) SUPPORTING AND CONNECTING PIPING; (5) BOILER PLANT CONTROLS; (6) OTHER MAJOR BOILER PLANT MECHANICAL EQUIPMENT, INCLUDING AUXILIARY BOILER, COMBUSTION AIR FAN, BOILER, FEEDWATER AND CHEMICAL FEED PUMPS, BLOWDOWN RECOVERY HEAT EXCHANGER, BOILER MAKEUP WATER SOFTENER PACKAGE, FLOW MEASURING DEVICES, BACKFLOW PREVENTERS, STEAM TRAPS, FLASH TANKS, CONTROL VALVE STATION, PRESSURE REDUCING VALVE STATION, AND SAFETY VALVES; (7) REINFORCED CONCRETE SLAB FOUNDATION; (8) STRUCTURAL STEEL CANOPY COVERING THE FULL FOOTPRINT OF THE NEW BOILER PLANT; (9) PLATFORMS AND STAIRS FOR SERVICING BOILERS AND FEED WATER/DE-AERATOR TANK; (10) DEMOLITION OF N231 SIDEWALK AND PARKING; (11) DEMOLITION OF SITE UTILITIES WITHIN BOUNDARY OF CONSTRUCTION; (12) SELECTED INTERIOR ROOM DEMOLITION AND REMODEL FOR THE NEW CONTROL ROOM IN BUILDING N231; (13) ELECTRIC DISTRIBUTION SERVICE; (14)NEW BOILER CONTROLS AND CONTROL ROOM IN BUILDING N231; (15) CONTROL ROOM LIGHTING, FIRE ALARM, SECURITY, DATA AND COMMUNICATION SYSTEMS; (16) GAS AND WATER UTILITIES; (17) EARTHWORK, INCLUDING GRADING AND DRAINAGE IMPROVEMENTS; (18) ASPHALT PAVEMENT SURROUNDING NEW BOILER PLANT FOUNDATION SLAB; (19) PERIMETER SITE FENCE WITH CONCRETE RAMPS, MANUAL SLIDING GATES AND CARD ACCESS MAN GATE; (20) SITE RESTORATION; (21) TRAFFIC CONTROL FOR STREETS AFFECTED BY CONSTRUCTION OPERATIONS; (22) COMPONENT AND SYSTEM TESTING. OPTIONS INCLUDE: (1) DEMOLITION AND REMOVAL OF NOX SPHERE NO. 6 AND ASSOCIATED BUILDING, PIPING AND TANKS; (2) BOILER AUXILIARY STEAM HEATING SYSTEM; (3) BOILER STACK ACCESS; (4) RENOVATION OF EXISTING TOILET FACILITIES IN BUILDING N231 TO MEET ADA COMPLIANCE, INCLUDING A NEW SHOWER; (5) BOILER CONTROL ROOM HVAC MECHANICAL EQUIPMENT. ACCESSIBLE CONCRETE RAMP, ASPHALT PARKING AND STRIPING IN N231 PARKING LOT; AND (6) N234A BOILER&FWDA DEMOLITION.

Dates and value

Award date
Signed on Aug 28, 2013
Potential end of performance
Sep 29, 2018
Current value
$33,760,235Base and exercised options
Potential value (if all options are exercised)
$33,760,235

Obligations by fiscal year of action

  • FY2018: $895,524
  • FY2017: $3,019,165
  • FY2016: $5,873,143
  • FY2015: $879,159
  • FY2014: $118,772
  • FY2013: $22,974,472

Total across 6 fiscal years: $33,760,235

Source: Federal Procurement Data System contract actions as published by SAM.gov and USAspending.gov; latest action recorded Aug 8, 2018. View on USAspending · Recipient on SAM.gov

Recipient

LocationRICHMOND, CA
UEIV9J2BWC3HWN8
CAGE code6X4V1
Business sizeOther than small businessSize at award, per the contracting officer
Organization typeCorporate not tax exempt

Business types and certifications

Self-certified small disadvantaged businessFor-profit organizationCorporation (not tax-exempt)

As represented in SAM.gov at the time of the action.

Subcontracting network

The prime, the subcontractors on this award, and their own subcontractors.

Subaward amounts are self-reported by prime contractors to SAM.gov and appear 1 to 2 months after the work. Duplicates are removed on a best-effort basis. Totals are incomplete and not an audit. Source: USAspending.

Agency and place

Awarding and funding

Awarded by
  1. National Aeronautics and Space Administration
  2. NASA AMES RESEARCH CENTER
Funded by
  1. National Aeronautics and Space Administration
  2. NASA AMES RESEARCH CENTER
Funded from
Construction and environmental compliance and restoration (DIRECT)Program activities080-0130Federal accounts (agency financial reports)

Place of performance

Place of performance
Moffett Field, Santa Clara County, California 94035-0001
Congressional district (place of performance)
CA-18As reported at the time of the action

Classification and competition

Classification

Competition

Extent competed
Full and open competitionA
Solicitation procedures
Negotiated proposal/quoteNP
Set-aside
No set-aside used
Contract pricing
Firm fixed priceJ
Offers received
3

Contract details

Subcontracting plan
Plan required - incentive not includedC
Major program
Replace arc jet complex steam vacuum system (SVS) boiler
Cost Accounting Standards clause
Not applicable exempt from CASX
Certified cost or pricing data
No
Service Contract Act labor standards
No
Commercial procedures
Commercial item procedures not usedD
Government-furnished property
Transaction does not use GFE/GFPN
Bundled requirement
Not a bundled requirementD
Consolidated requirement
No
Undefinitized action (terms not final)
No
Multi-year contract
No
Performance-based service acquisition
No - service where PBA is not used.N

Linked notices

Notice
Notice ID
Type
Link
Posted

Transaction history

Modification history

Base award
Aug 28, 2013Base obligation at award: $22,974,472
Latest action
Aug 8, 2018 — Change orderModification 55; obligation change +$173,139
Latest substantive action
Aug 8, 2018 — Change orderModification 55; obligation change +$173,139
Latest funding action
Aug 5, 2016 — Funding onlyModification 28; obligation change +$20,522; funding only: changes obligations, not scope
Actions by type
  • Base award1
  • Change order32
  • Other administrative action17
  • Funding only4
  • Supplemental agreement (within scope)2
56 actions recorded, Aug 28, 2013 to Aug 8, 2018; each action counted once.

Similar awards

PIID
Match
Awardee

All contract data

All contract data

Every other field reported for this award, as of its latest reported action

Competition

Evaluation preference
No preference used
Local area set-aside
No
Synopsized publicly (SAM.gov / FedBizOpps)
Yes
Simplified procedures for commercial items
No
A-76 (FAIR Act) action
No

Pricing and financing

Paid by purchase card
No
Latest action: change in base and exercised options
$173,139
Latest action: change in base and all options
$173,139

Socio-economic and policy

Inherently governmental functions
Other functionsOT
Recovered materials and sustainability
No clauses included and no sustainability includedC
EPA-designated product
Not requiredE
Clinger-Cohen Act planning (IT)
No
Walsh-Healey Act (materials and supplies)
Yes
Construction wage rates (Davis-Bacon)
Yes

Place and origin

Domestic or foreign entity
U.S. owned businessA
Country of product or service origin
United statesUSA
Place of manufacture
Not a manufactured end productC

Structure

Award or IDV
Award
Award type
Definitive contractD
Awarding agency code
8000
Awarding sub-tier code
8000
Contracting office code
80ARC0
Transactions recorded under this award key
56

Funding

Funding agency code
8000
Funding sub-tier code
8000
Funding office code
80ARC0
Treasury accounts
  • 080-2013/2018-0130-000
  • 080-2014/2019-0130-000
  • 080-2015/2020-0130-000
  • 080-2016/2021-0130-000
Object classes
  • 32.0: Land and structures