Definitive contract NNG09FA40CLOCKHEED MARTIN CORPORATION
Overview
Award facts
- Net obligations
- $194.51M
- $194,514,277of $198.77M potential value
- Period of performance
- Oct 1, 2009 to Sep 30, 2027
- Ends in 10 months
- Modifications
- 120
- Latest action Nov 10, 2026
- Contract type
- Definitive contract
- PIID NNG09FA40C
Description of requirement
INTERFACE REGION IMAGING SPECTROGRAPH (IRIS). THE CONTRACTOR SHALL REFINE AND EVOLVE THE CONTRACTOR'S COST ESTIMATE FOR PHASES B-F FOR THE INTERFACE REGION IMAGING SPECTROGRAPH (IRIS) MISSION SUBMITTED IN RESPONSE TO NASA ANNOUNCEMENT OF OPPORTUNITY #NNH07ZDA003O FOR THE EXPLORERS PROJECTS DIVISION. THE PRIMARY TASKS IN PHASE B WILL INCLUDE THE GENERATION AND PRESENTATION OF THE SYSTEMS REQUIREMENTS REVIEW (SRR) AND THE PRELIMINARY DESIGN REVIEW (PDR). IN ORDER TO SUPPORT THESE REVIEWS, THE CONCEPT DEFINITION EFFORTS SHALL ENCOMPASS THE WORK REQUIRED TO UPDATE AND REFINE THE PROPOSAL'S SCIENCE INVESTIGATION OBJECTIVES AND PLANS (IF NECESSARY), INSTRUMENT AND SPACECRAFT CONCEPTS AND PERFORMANCE CHARACTERISTICS, AND SCIENCE OPERATIONS AND FLIGHT OPERATIONS PLANS AND CONCEPTS. THESE EFFORTS SHALL IDENTIFY THE CONDITIONS AND CONSTRAINTS NECESSARY FOR THE DEVELOPMENT OF AN INTEGRATED IRIS MISSION APPROACH. THE CONTRACTOR'S MISSION INTEGRATION EFFORTS SHALL INCLUDE CONSIDERATIONS FOR THE ACCOMMODATION OF THE IRIS OBSERVATORY ONTO THE LAUNCH VEHICLE. THE CONTRACTOR'S PHASE B PRELIMINARY DESIGN EFFORTS SHALL DEVELOP THE CSR AND SITE VISIT CONCEPTS INTO A PRELIMINARY DESIGN AND DEFINITION OF THE IRIS MISSION, INCLUDING ITS MISSION OPERATIONS CENTER (MOC) AND SCIENCE OPERATIONS CENTER (SOC). THE PRELIMINARY DESIGN REVIEW (PDR) SHALL BE HELD IN ACCORDANCE WITH NPR 7120.5D, NPR 7123.1A, AND GSFC STD 1001B. THE CONTRACTOR'S EFFORTS IN PHASE B SHALL FORM THE BASIS FOR FINAL ATION OF THE REMAINDER OF THE IRIS DEVELOPMENT AND OPERATIONAL PHASES (C, D, E AND F). DETAILED COST AND SCHEDULE ESTIMATES SHALL BE PREPARED AND SUBMITTED DURING PHASE B, WHICH DEFINES THE CONTRACTOR'S UPDATED BUDGET FOR PHASE B AND THE PLANNED BUDGETS FOR PHASE C, D, E AND F WORK. PERIODIC TECHNICAL AND PROGRAMMATIC INTERCHANGE MEETINGS AT BOTH THE CONTRACTOR'S FACILITY AND AT GSFC SHALL BE REQUIRED TO COORDINATE EFFORTS BETWEEN THE CONTRACTOR AND THE EXPLORERS PROJECTS OFFICE. THESE MAY BE CONDUCTED AS FACE-TO-FACE MEETINGS OR TELECONFERENCES, AS REQUIRED.
Dates and value
- Award date
- Signed on Sep 30, 2009
- Current value
- $198,769,611Base and exercised options
- Potential value (if all options are exercised)
- $198,769,611
Obligations by fiscal year of action
- FY2027: $449,000
- FY2026: $3,927,943
- FY2025: $6,841,983
- FY2024: $5,009,000
- FY2023: $5,044,800
- FY2022: $5,673,387
- FY2021: $5,086,519
- FY2020: $5,602,311
Show all 19 yearsEarlier years (FY2009–FY2019)
- FY2019: $5,591,914
- FY2018: $5,648,206
- FY2017: $6,167,000
- FY2016: $6,096,000
- FY2015: $5,735,000
- FY2014: $6,493,789
- FY2013: $10,956,534
- FY2012: $22,445,750
- FY2011: $44,930,000
- FY2010: $28,738,379
- FY2009: $14,076,763
Total across 19 fiscal years: $194,514,277
Source: Federal Procurement Data System contract actions as published by SAM.gov and USAspending.gov; latest action recorded Nov 10, 2026. View on USAspending · Recipient on SAM.gov
Recipient
Business types and certifications
As represented in SAM.gov at the time of the action.
Subcontracting network
The prime, the subcontractors on this award, and their own subcontractors.
Agency and place
Awarding and funding
- Awarded by
- National Aeronautics and Space Administration
- NASA GODDARD SPACE FLIGHT CENTER
- Funded by
- National Aeronautics and Space Administration
- NASA GODDARD SPACE FLIGHT CENTER
Place of performance
- Place of performance
- Palo Alto, Santa Clara County, California 94304-1121
- Congressional district (place of performance)
- CA-16As reported at the time of the action
Classification and competition
Classification
- Product or service (PSC)
- 1820SPACE VEHICLE COMPONENTS (product)
Competition
- Extent competed
- Full and open competitionA
- Solicitation procedures
- Negotiated proposal/quoteNP
- Set-aside
- No set-aside used
- Contract pricing
- Cost plus fixed feeU
- Offers received
- 32
Solicitation and notices
- Solicitation ID
- NNH07ZDA003O
- Notices
- Presolicitation posted Dec 5, 2007
- Presolicitation posted Nov 27, 2007
- Presolicitation posted Oct 22, 2007
Contract details
- Subcontracting plan
- Individual subcontract planF
- Major program
- Iris
- Cost Accounting Standards clause
- Yes - CAS clause includedY
- Commercial procedures
- Commercial products/services procedures not usedD
- Government-furnished property
- Transaction does not use GFE/GFPN
- Bundled requirement
- Not a bundled requirementD
- Consolidated requirement
- No
- Undefinitized action (terms not final)
- No
- Multi-year contract
- No
Linked notices
Notice | Notice ID | Type | Link | Posted |
|---|---|---|---|---|
Transaction history
Modification history
- Base award
- Sep 30, 2009Base obligation at award: $14,076,763
- Latest action
- Nov 10, 2026 — Funding onlyModification 120; obligation change +$449,000; funding only: changes obligations, not scope
- Latest substantive action
- Oct 20, 2026 — Supplemental agreement (within scope)Modification 119
- Latest funding action
- Nov 10, 2026 — Funding onlyModification 120; obligation change +$449,000; funding only: changes obligations, not scope
- Actions by type
- Base award1
- Funding only76
- Supplemental agreement (within scope)27
- Other administrative action14
- Change order2
- Terminated for convenience1
Similar awards
PIID | Match | Awardee |
|---|---|---|
All contract data
All contract data
Every other field reported for this award, as of its latest reported action
Competition
- Evaluation preference
- No preference used
- Local area set-aside
- No
- Synopsized publicly (SAM.gov / FedBizOpps)
- Yes
- Simplified procedures for commercial items
- No
- A-76 (FAIR Act) action
- No
Pricing and financing
- Paid by purchase card
- No
Socio-economic and policy
- Recovered materials and sustainability
- No clauses included and no sustainability includedC
- EPA-designated product
- Not requiredE
- Clinger-Cohen Act planning (IT)
- No
Place and origin
- Domestic or foreign entity
- U.S. owned businessA
- Country of product or service origin
- United statesUSA
- Place of manufacture
- Mfg in U.S.D
Structure
- Award or IDV
- Award
- Award type
- Definitive contractD
- Awarding agency code
- 8000
- Awarding sub-tier code
- 8000
- Contracting office code
- 80GSFC
- Transactions recorded under this award key
- 121
Funding
- Funding agency code
- 8000
- Funding sub-tier code
- 8000
- Funding office code
- 80GSFC