GovChime
Notice ID: 0ddf96578ea24f78be4abf3f578175c1PresolicitationArchived

CO NP ROMO 407(1) Holzwarth Culvert

Archived on September 30, 2026. Original response deadline: . Full description on SAM.gov.

Overview

Response deadline
2:00 PM MDT
Posted
August 25, 2026
Notice type
Presolicitation
NAICS
237310: Highway, Street, and Bridge Construction
Agency
Department of TransportationFEDERAL HIGHWAY ADMINISTRATION

Notice details

Office
6982AF CENTRAL FEDERAL LANDS DIVISI
Place of performance
Grand Lake, Colorado, 80447
PSC
Y1LB: CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS
Last updated
Oct 28, 2026
First published
Last updated on SAM.gov

Identifiers

Solicitation number
6982AF26B000012
Notice ID
0ddf96578ea24f78be4abf3f578175c1

Description

THIS IS NOT AN INVITATION FOR BID, PLAN AND SPECIFICATIONS ARE NOT AVAILABLE

PROJECT NUMBER: CO NP ROMO 407(1)

PROJECT NAME: Holzwarth Culvert

PROJECT DESCRIPTION: 

This project will replace the deficient Holzwarth Culvert (Structure No. 1520-029S), a six-barrel corrugated metal arch pipe culvert on the Holzwarth Access Road with a steel girder bridge. Located in Rocky Mountain National Park, approximately nine miles north of Grand Lake, CO, along US HWY 34 at an elevation of 8,900 feet, the culvert conveys flow from the Colorado River and provides access to the Holzwarth Historic Site. The purpose of this project is to prevent future roadway damage and flooding while maintaining access to employee housing, the historic site, and National Park Service and Forest Service recreation opportunities.

SCOPE OF THE WORK:   

The project will consist of removal of the existing six barrel culvert and construction of a new steel girder bridge with a cast in place concrete deck. New bridge abutments and micropiles. Temporary stream diversion and riprap. New aggregate roadway surfacing. Relocation of an existing electrical line. Relocation of existing historic head gates into a new concrete slab. Access to the site is through a gate at the south end of the Holzwarth Historic Site Parking Lot and along the Holzwarth Culvert Access Road. The Holzwarth Culvert Access Road is approximately 13’ wide with tight turns. Temporary widening will be necessary to prevent truck off tracking on to sensitive environmental resources. A temporary truck turnaround will also be necessary as no construction access is allowed more than 100’ west of the bridge.

PRINCIPAL WORK ITEMS:

  • 20304-2000 Removal of Bridge: 1 EACH
  • 30202-2000 Roadway Aggregate, Method 2: 120 TON
  • 55504-0000 Prefabricated Steel Bridge (10’ wide x 48’ long modular steel vehicular bridge): 1 LPSM
  • 56701-0000 Micropile (8.68” dia.): 180 LNFT
  • 62801-0000 Temporary Stream Diversion: 1 LPSM

ANTICIPATED SCHEDULE: 

Advertisement – September 2026

Award – December 2026

NTP – December 2026

Contract Completion – November 2027

ESTIMATED COST RANGE:

 Total estimated cost between $700,000 and $2,000,000.

Full description on SAM.gov

Award Overview

Contacts

Contracting Officer

Primary Contact

Secondary Contact

Ryan D. Phillips

Documents

No documents available.

Lifecycle

  1. 4
    Version 4Sources SoughtArchived

    CO NP ROMO 407(1) Holzwarth Culvert

    Notice e74dc9126c984695af6785f7bb00c6dc on SAM.gov

  2. 7
    Version 7PresolicitationArchivedCurrent

    Type changed from Sources Sought to Presolicitation

    CO NP ROMO 407(1) Holzwarth Culvert

    Notice 0ddf96578ea24f78be4abf3f578175c1 on SAM.gov

  3. 5
    Version 5Solicitation

    Type changed from Presolicitation to Solicitation

    CO NP ROMO 407(1) Holzwarth Culvert

    Notice ca5a8d1d2c63414488418b32e5abf45d on SAM.gov

Similar Opportunities

Additional Details

Solicitation Number

6982AF26B000012

Archive Date

Sep 30, 2026

Office Address

LAKEWOOD, CO, 80228