Archived on April 4, 2026. Original response deadline: . Full description on SAM.gov.
Overview
- Response deadline
- 5:00 PM PDT
- Posted
- March 10, 2026
- Notice type
- Sources Sought
- NAICS
- 115310: Support Activities for Forestry
- Agency
- Department of AgricultureFOREST SERVICE
Notice details
- Office
- USDA-FS, STEWARDSHIP CONTRACTING BRANCH
- Place of performance
- Downieville, California
- Last updated
- Nov 2, 2026
- First published
- Last updated on SAM.gov
Identifiers
- Solicitation number
- 12363N26Q4069
- Notice ID
- 163d25bc58ed416182f1a2889c30faf5
Description
UPDATE: 3/10/2026 - Replaced Attachment 1: Galloway G-Z_RFI_Letter.pdf.
The U.S. Forest Service is issuing this formal Request for Information (RFI) in connection with the Tahoe National Forest, Galloway G-Z Stewardship IRSC. The objectives of this initiative are to improve and restore forest health and resilience, reduce the risk of high-severity wildfire threats to communities and wildlife habitat from large, severe wildfires and protect and secure water supplies by restoring, and maintaining the watershed. While providing a steady supply of wood products to local facilities to bolster the wood utilization capacity of the region.
Project Overview and Scope:
- Approximately 5,127 gross acres are available for treatment across the Galloway G-Z Stewardship IRSC; approximately 1,500 acres prepared for timber harvest (Keystone Roadside Fuelbreak), and 3,627 acres available for preparation and timber harvest (Hungry Slug). The contract term is anticipated to be up to 5 years. The net acres for treatment are expected to be less after unit layout.
- Approximately 15+ MMBF of commercial timber and 8,000+ CCF of biomass is anticipated to be offered over the contract life.
- Types of Service Work may include:
-
- Timber sale preparation activities which may include harvest unit layout, GPS traversing, unit boundary marking, verifying silvicultural prescription accuracy, interior marking in select units, and timber volume determination.
- Road reconditioning, and curve widening. Please note that detailed road design activities such as geometric alignment, engineering drawings, and technical specifications will be included in the final contract.
- Timber removal that will include logging operations conducted by tractor, skyline, and/or tethered systems and transportation.
- Temporary road construction and obliteration.
- Low value stand treatment including precommercial thinning (PCT), mastication, etc. with a volume removal option.
- Biomass removal that may include thinning non-merchantable material, chipping, transportation and other related activities.
Anticipated Terms:
- Minimum timber value estimates will be based on base rates and/or appraised rates if appropriate as determined from the Forest Service’s Timber appraisal system.
- Payment terms for service work items are anticipated to be by the acre, ton or linear foot for most treatments. Reconstruction activities may be priced by the mile or contract quantity.
- The project will include both mandatory and optional service items; product value at awarded rates will be used to offset the cost-of-service work items.
- Davis-Bacon wages and certified payrolls will be required for all Road Construction requirements. Service Contract Act wages will apply towards all non-construction service work requirements.
- Road construction requirements will be subject to bonding at applicable regulatory thresholds.
By March 20th, 2026 at 5:00 P.M. Pacific, interested parties are asked to submit written responses to questions included in this RFI letter via email to evan.fellrath@usda.gov and Kasandra.meyer@usda.gov.
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Contracting Officer
Primary Contact
Secondary Contact
Documents
Files (4)
- Download
1. REVISED_Galloway G-Z_RFI_Letter_3.10.2026.pdf
224 KBAdded in Sources Sought version 3Posted - Download
2. Galloway G-Z_Project Area Map.pdf
7.1 MBAdded in Sources Sought version 1Posted - Download
3. Keystone_Project Area Map.pdf
7.1 MBAdded in Sources Sought version 1Posted - Download
4. HungrySlug_Project Area Map.pdf
3.7 MBAdded in Sources Sought version 1Posted
Lifecycle
- 1Version 1Sources SoughtArchived
Galloway G-Z Stewardship IRSC
- 3Version 3Sources SoughtArchivedCurrent
Galloway G-Z Stewardship IRSC
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
Additional Details
Solicitation Number
12363N26Q4069
Archive Date
Apr 4, 2026
Office Address
Washington, DC, 202501138