Site Effluent System
Cancelled on SAM.gov (notice posted September 3, 2026). Original response deadline: . Full description on SAM.gov.
Description
This solicitation is reissued due to technical responses that were required in addition to adhering to the FAR Overhaul under Commercial Services. A second site visit is scheduled and listed within the attached Amendment.
BACKGROUND INFORMATION
The Gaithersburg Site Effluent Treatment System is located on the south end of campus at the “E” Gate intersection at Center Drive. Built in the mid-1990’s, the system was designed to comply with Washington Sanitary Sewer Commission (WSSC) effluent discharge requirements. The system is centered around a large concrete tank (wet tank) that provides primary effluent treatment with a stir / chop agitator system PH monitoring and treatment.
Currently, the interior wet tank operational, structural, and life safety systems have rendered this system inoperable. Inspection has found the primary floor support has detached along the south side of the wet tank. This has caused for the aluminum grating to sag, and no longer safe for personnel entry. More, there are areas of the aluminum grate that have literally rotted away.
Further inspection revealed several issues.
Internal blowers to address the confined space ventilation requirements are inoperable and heavily corroded. The system internal heater is inoperable and heavily corroded. The motor and stir mechanism is seized. Additionally, the motor is electrically inoperable. The explosion proof electrical wiring and conduit is in very poor condition.
In general, the entire wet tank and systems needs to be renovated and brought back to operable condition. This requires a complete replacement of all tank components. This includes an entire new floor surface and all support members, safety blowers and heaters, new stir / agitation motor and shaft system, PH monitoring probes and data signaling, epoxy lining of the wet tank, lighting, electrical outlets, and demolition and replacement of all the explosion proof electrical wiring and conduit. Other work as required to conform to current regulatory requirements, as required.
PURPOSE
The Site Effluent Treatment System requires a complete rebuilding of all internal components to fulfill operational, regulatory, and life safety requirements.
PLACE OF PERFORMANCE
NIST Campus in Gaithersburg, Maryland.
NOTICE TO OFFERORS
Proposals are being requested in accordance to the submission requirements for Technical Approach, Schedule, and Price. Award will be made on the basis of the best value to the government
PERIOD OF PERFORMANCE
The period of performance for this project is estimated at 200 days from Notice to Proceed.
Overview
Award Overview
Possible prior contracts
Sign in to see possible prior contracts for this requirement (matched by agency, NAICS and place of performance; not confirmed).
Contacts
Contracting Officer
Primary Contact
Documents
Files (6)
- Download
A003 SF30.pdf
211 KBAdded in Combined Synopsis/Solicitation version 9Posted - Download
Public Notice_1333ND26RNB190022 Site Effluent.pdf
103 KBAdded in Combined Synopsis/Solicitation version 7Posted - Download
A002_1333ND26RNB190022 Site Effluent.pdf
341 KBAdded in Combined Synopsis/Solicitation version 6Posted - Download
A001_1333ND26RNB190022 Site Effluent.pdf
1.1 MBAdded in Combined Synopsis/Solicitation version 5Posted - Download
Attachment 5 Question and Answer Template - Site Effluent System 1333ND26RNB190022.xlsx
11 KBAdded in Combined Synopsis/Solicitation version 4Posted - Requires SAM.gov sign-in
1333ND26RNB190022 Site Effluent.pdf
6.7 MBAdded in Combined Synopsis/Solicitation version 4Posted
Lifecycle
- 3Version 3Combined Synopsis/SolicitationArchived
Site Effluent System
- 4Version 4Combined Synopsis/SolicitationArchived
Site Effluent System
- 5Version 5Combined Synopsis/SolicitationArchived
Site Effluent System
- 6Version 6Combined Synopsis/SolicitationArchived
Site Effluent System
- 7Version 7Combined Synopsis/SolicitationArchived
Site Effluent System
- 9Version 9Combined Synopsis/SolicitationArchived
Site Effluent System
- 10Version 10Combined Synopsis/SolicitationArchived
Site Effluent System
- 11Version 11Combined Synopsis/SolicitationCancelledArchivedCurrent
Site Effluent System
Similar Opportunities
Title | Phase | Agency | NAICS | Set Aside | Posted | Deadline | Location |
|---|---|---|---|---|---|---|---|
Additional Details
Solicitation Number
1333ND26RNB190022
Archive Date
Sep 4, 2026
Office Address
GAITHERSBURG, MD, 20899