Notice ID: 47299126a796440e8812bebe616fd196Award NoticeAwarded
Z--Black Canyon Powerplant Cable Separation
Awarded on September 8, 2023. Full description on SAM.gov.
Awarded tounder 140R1023C0010 (source: SAM.gov award notice)• $287.7K
Overview
- Posted
- September 8, 2023
- Notice type
- Award Notice
- NAICS
- 237130: Power and Communication Line and Related Structures Construction
- Agency
- Department of the Interior
Notice details
- Last updated
- Dec 4, 2025
- Award date
- Sep 8, 2023
- Award amount (SAM.gov award notice)
- $287.7K
Identifiers
- Solicitation number
- 140R1023B0004
- Notice ID
- 47299126a796440e8812bebe616fd196
- Award number (PIID)
- 140R1023C0010
Description
Black Canyon Powerplant Cable Separation
Award Overview
Award Number
140R1023C0010
Award Amount (SAM.gov award notice)
$287.7K
Award Date
Sep 8, 2023
Awardee
Awardee UEI
P5XRJHGMS2Y5
Awardee CAGE Code
0HDU4
Original Solicitation
Notice ID: 47299126a796440e8812bebe616fd196
Posted Date: Sep 8, 2023
Original Response Deadline: Not specified
More From This Vendor
Top 5 most recent
- $702.4KSigned Feb 26, 2026
- $5.5MSigned Jan 9, 2026
- $5.5MSigned Jan 9, 2026
- $702.4KSigned Sep 16, 2025
- $5.4MSigned Dec 19, 2024
Contacts
Documents
No documents available.
Lifecycle
Solicitation:
140R1023B0004- Market Research
- Pre-Solicitation
- Solicitation
- Awarded
This opportunity has been awarded.
- 2×Market ResearchJan 23, 2023
Y--Black Canyon Powerplant Cable Separation
- Pre-SolicitationMay 12, 2023
Y--Black Canyon Powerplant Cable Separation
- 3×SolicitationJul 13, 2023
Z--Black Canyon Powerplant Cable Separation
- AwardedCurrentSep 8, 2023
Z--Black Canyon Powerplant Cable Separation
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
| - | Awarded | Open | |
Folsom Dam Electronic Access Control and Surveillance (EACSS) Fiber Backbone Upgrade | - | Pre-Solicitation | 11/16/2026 |
TRD GSU Transformer Replacements | - | Solicitation | 10/31/2025 |
ACTION: Pre-Solicitation Notice PRE-SOLICITATION NUMBER: 140P2024R0130 CLASSIFICATION CODE: Y1NZ - Construction of other utilities. CONTRACTING OFFICER: Tim Burger CONTRACT SPECIALIST: Brian Baugh DSC-CS Contracting Services Division National Park Service P.O. Box 25287 Denver, CO 80225 POINT OF CONTACT: CONTRACTING OFFICER: tim_burger@nps.gov CONTRACT SPECIALIST: brian_baugh@contractor.nps.gov PLACE OF PERFORMANCE: Voyageurs National Park, Minnesota. PLACE OF PERFORMANCE COUNTRY: USA Title of Project: Replace Power Distribution line. GENERAL: The National Park Service (NPS), Department of Interior (DOI), Denver Service Center (DSC), is soliciting proposals on a full and open basis from all interested businesses having the capability to perform the work described below. The solicitation will be issued electronically on the Federal Business Opportunities website at www.fedbizopps.gov . Proposal documents will be available for download in Microsoft Word, HTML, Microsoft Excel, and Adobe PDF; Specifications will be available in Adobe PDF format; and drawings will be available in PDF format. Please Note: Paper copies of the solicitation will not be made available. Vendors can search for opportunities and award history on www.fbo.gov without registering. The Federal Business Opportunities (www.fbo.gov) website has an Interested Vendors List and a Watchlist where you can add your company¿s interest. Registering provides the opportunity to receive notifications; this is a tool of convenience only and does not serve as a guarantee of notification. Interested vendors and plan holders are required to visit the website periodically to check for amendments and other changes to the synopsis or solicitation documents. Prospective offerors desiring to conduct business with the DOI are required to have an active registration in the Systems for Awards Management (SAM) at www.sam.gov. You are also required to have a DUNS number in order to conduct business with the Federal Government. This pre-solicitation announcement is not a solicitation document, but pre-notice of an upcoming solicitation. Specific instructions on submitting your proposal will be contained in the solicitation documents to be issued on or after the date listed below. Proposed Solicitation Issue Date: Estimated on/about September 3, 2024 This is currently an unfunded requirement with a high expectation that funds will be available. When and if funds become available a contract will be awarded at that time. The NAICS Code for this requirement is 237130 with a size standard of $45 million. Description: This project will replace the main underwater high voltage cable and multiple transformer boxes that run from the mainland to the Kettle Falls district. Pad-mounted switchgear, sectionalizing enclosures, elbow terminations, as well as individual and other associated components will be replaced as needed. An improved level of emergency backup generation for critical loads at Kettle Falls Area will be installed. Due to the compromised neutral wire, this poses a serious safety risk to visitors as well as employees. The neutral serves as a ground for the cable, and as more lightning strikes occur the chances of someone being struck increase. Secondly when power goes out facilities are forced to be closed such as restrooms, showers, and the restaurant. There is also a food safety factor at the restaurant due to the freezers and coolers loss of power. This has potential for food to develop bacteria that could lead to sickness of visitors. The Fire suppression system pumps are run by electricity; therefore, if there is no power then there is no fire protection for the Historic hotel. This jeopardizes the visitor's safety as well as the historic building. The new backup generator would allow the concession to continue to stay operational in the event of a power outage. Estimated Price Range: Over $10,000,000 Estimated Period of Performance: 730 calendar days Proposal receipt date is not known at this time. The actual date will be established in the solicitation documents A pre-proposal meeting may be posted and date/location will be noted in the solicitation or a forthcoming amendment. This procurement will be competed via full and open. All responsible sources may submit an offer which, if submitted in a timely manner, will be considered. It is the policy of the government to provide maximum practicable opportunities in its acquisitions to small business, veteran-owned small business, small disadvantaged business, and women-owned small business concerns. Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency, consistent with efficient contract performance. All offerors are strongly encouraged to contact their local Small Business Administration Office, to post their need for qualified subcontractors at http://www.sba.gov . | - | Pre-Solicitation | 10/03/2024 |
November 5, 2026- Amendment 1 issued to clarify timne and location of the Pre-Proposal Meeting. This scope of work is to rebuild and renovate the Kautz Road Substation (KRS), which is UIP subproject SP-2. The KRS supplies electricity to various lab buildings and systems. These systems serve both conventional facility needs, as well as process utility requirements. It is vital to Fermilab’s mission that KRS be revitalized and expanded, ensuring the ability to serve existing and future loads. The General contractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings, technical specification and the detailed description contained herein. The critical schedule constraint for construction of this project is Fermilab’s accelerator shutdown, with an anticipated scheduled start on January 1, 2028, and anticipated end date of January 1, 2030- these dates may change depending on the needs of the Lab. The General Contractor must start their on-site efforts, and complete the construction scope under this contract, within the shutdown window. This project includes the following milestones: Milestone 1 – 60 Calendar Days after issuance of Notice to Proceed (NTP). This milestone is intended for completion of necessary submittals and RFIs, approval of shop drawings for fabrication and procurement. Milestone 2 – 4th January 2028; This milestone marks the point where access is permitted inside Kautz Road Substation yard and construction work may begin. Milestone 3 – 31st of March 2028; This milestone marks the completion of building foundation and ready for placement of the new prefabricated control house building (provided by FermiForward). Milestone 4 – 2nd July 2029; This milestone marks the formal issuance of an Authorization for Use and Possession (AUP) of the KRS Substation facility, including all remedial work following removal of site trailers, but not including seasonal work and all final punch list items addressed.. Milestone 5 – 30th September 2029; This milestone marks the completion of the project. | - | Solicitation | 12/18/2026 |
Additional Details
Solicitation Number
140R1023B0004
Archive Date
Sep 23, 2023
Office Address