Notice ID: 5a6ce1bb867b43ecb2af896a113b70cfCombined Synopsis/Solicitation
Sole Source - DFC Elec Infrastructure - Y-Side Substation Transformer Replacement
Archived on January 15, 2023. Original response deadline: . Full description on SAM.gov.
Overview
- Response deadline
- 10:00 AM UTC−07:00
- Posted
- December 14, 2022
- Notice type
- Combined Synopsis/Solicitation
- Agency
- General Services AdministrationPUBLIC BUILDINGS SERVICE
Notice details
- Office
- PBS R8 ACQUISITION MANAGEMENT DIVISION
- Place of performance
- Lakewood, CO, 80225
- Last updated
- Dec 4, 2025
Identifiers
- Solicitation number
- 47PJ0022R0102
- Notice ID
- 5a6ce1bb867b43ecb2af896a113b70cf
Description
Construction activity at the Denver Federal Center to repair/replace the Y-Side Substation transformer, one of two existing primary substation transformers at the DFC. Project would include Project would include the engineer and design a set of construction documents and specifications for the civil, structural, and electrical work for the replacement of the Y side Substation. The design shall incorporate the transformer and switchgear. Including the manufacturer engineering, purchase, and deliver a new Y side Substation transformer to match the performance characteristics of the existing X side Substation transformer. Project would include engineering, purchase, and deliver a new 15kv Y side switchgear. New switchgear sections shall match the existing sections purpose with new circuit breakers, protective relays, and metering cabinets. Design a new foundation sized and engineered to meet the geotechnical conditions and weight of the new transformer and equipment to be installed. Construct an oil retention pit or curb, with tank. Remove and install a new concrete duct bank from the transformer to the existing switchgear pad. Coordinate demolition of existing equipment as well as installation dependent on timing of equipment delivery.
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Documents
No documents available.
Lifecycle
Solicitation:
47PJ0022R0102- Combined Synopsis
- Combined SynopsisCurrentDec 14, 2022
Sole Source - DFC Elec Infrastructure - Y-Side Substation Transformer Replacement
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
Additional Details
Solicitation Number
47PJ0022R0102
Archive Date
Jan 15, 2023
Office Address
LAKEWOOD, CO, 80225