TX FW LGA 10(5) Steve Thompson Wildlife Drive

Archived on October 2, 2026. Original response deadline: . Full description on SAM.gov.

Overview

Response deadline
2:00 PM MDT
Posted
September 1, 2026
Notice type
Presolicitation
Set-aside
Small Business Set Aside - Total
NAICS
237310: Highway, Street, and Bridge Construction
Agency
Department of TransportationFEDERAL HIGHWAY ADMINISTRATION

Notice details

Office
6982AF CENTRAL FEDERAL LANDS DIVISI
Place of performance
Los Fresnos, Texas, 78566
PSC
Y1LB: CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS
Last updated
Oct 28, 2026
First published
Last updated on SAM.gov

Identifiers

Solicitation number
6982AF26B000014
Notice ID
59b8e11f822345fe8c0b03b9292dcab7

Description

THIS IS NOT AN INVITIATION FOR BID, PLAN AND SPECIFICATIONS ARE NOT AVAILBLE

PROJECT NUMBER: TX FW LGA 10(5) 

PROJECT NAME: STEVE THOMPSON WILDLIFE DRIVE

PROJECT DESCRIPTION: 

The proposed project includes full depth reclamation of existing driving surface which includes chip seal material, and existing gravel. After completing full-depth reclamation new aggregate surface course will be added to create a driving surface that has a consistent width. The project also includes installation of aluminum gate and a small concrete pad and safety improvement signs and speed bumps.

The project includes three alternate bid items for Aggregate Surface Course (TON) with one being awarded.

Alternate 1: 2-inches of aggregate surface course added to Bayside Drive and Steve Thompson Wildlife Drive and terminating at Renee’s Overlook Parking Area.

Alternate 2: 2-inches of aggregate surface course added to Bayside Drive and Steve Thompson Wildlife Drive.

Alternate 3: 3-inches of aggregate surface course added to Bayside Drive and Steve Thompson Wildlife Drive and terminating at Renee’s Overlook Parking Area.

PRINCIPAL WORK ITEMS: The project includes the following work items:

Full Depth Reclamation (MILE) – 13 MILE

Aggregate Surface Course (TON) – 11,000 TON

ANTICIPATED SCHEDULE: The anticipated advertisement date is September 2026 with construction beginning in January 2027, and project completion in August 2027.

ORDER OF MAGNITUDE: The proposed project cost ranges between $2,000,000 and $5,000,000.

Full description on SAM.gov

Award Overview

Contacts

Contracting Officer

Primary Contact

Douglas Whitcomb

Secondary Contact

Documents

No documents available.

Lifecycle

  1. 3
    Version 3Sources SoughtArchived

    TX FW LGA 10(5) Steve Thompson Wildlife Drive

    Notice 7752aee91b1b41ffa42b4dec57472cb4 on SAM.gov

  2. 7
    Version 7PresolicitationArchivedCurrent

    Type changed from Sources Sought to Presolicitation

    TX FW LGA 10(5) Steve Thompson Wildlife Drive

    Notice 59b8e11f822345fe8c0b03b9292dcab7 on SAM.gov

  3. 5
    Version 5Solicitation

    Type changed from Presolicitation to Solicitation

    TX FW LGA 10(5) Steve Thompson Wildlife Drive

    Notice c3e08369fdde494b9eee7035768c2845 on SAM.gov

Similar Opportunities

Additional Details

Solicitation Number

6982AF26B000014

Archive Date

Oct 2, 2026

Office Address

LAKEWOOD, CO, 80228