USCGC Gasconade SSDG Control Panel replacement
Archived on January 21, 2026. Original response deadline: . Full description on SAM.gov.
Overview
- Response deadline
- 8:00 AM PST
- Posted
- December 23, 2025
- Notice type
- Combined Synopsis/Solicitation
- Set-aside
- Total Small Business Set-Aside (FAR 19.5)
- NAICS
- 336611: Ship Building and Repairing
- Agency
- Department of Homeland SecurityUS COAST GUARD
Notice details
- Office
- SFLC PROCUREMENT BRANCH 2(00085)
- Place of performance
- Saint Louis, Missouri, 63118
- PSC
- J020: MAINT/REPAIR/REBUILD OF EQUIPMENT- SHIP AND MARINE EQUIPMENT
- Last updated
- Nov 4, 2026
- First published
- Last updated on SAM.gov
Identifiers
- Solicitation number
- 70Z08526Q0002157
- Notice ID
- d108f1bfd85e4538991fa9ae9204626e
Description
Statement of Work (SOW)
Project Title: Replacement, Installation, and Calibration of CAT 10R-9661 - Kit ELEK GP Controller on both SSDG’s aboard CGC GASCONADE
- Background
The purpose of this project is to replace both existing controllers on the cutters SSDG’s with the CAT 10R-9661 - Kit ELEK GP, ensuring proper installation and calibration in accordance with the manufacturer's instructions. This work is critical to maintaining the operational efficiency and reliability of the equipment.
- Contractor Furnished Equipment
Qty 2 – CAT Kit ELEK GP – 10R-6991
3. Scope of Work
The contractor shall provide all necessary labor, tools, equipment, and expertise to perform the following tasks:
- Removal of Old Controller:
- Safely disconnect and remove the existing controllers from the equipment.
- Ensure no damage is caused to surrounding components during removal.
- Installation of New Controller:
- Install the CAT 10R-9661 - Kit ELEK GP controllers in accordance with the manufacturer's specifications.
- Verify that all connections are secure and properly aligned.
- Calibration of Controller:
- Calibrate the newly installed controllers per the manufacturer's instructions.
- Ensure the controllers are functioning optimally and meets operational requirements.
4. Deliverables
The contractor shall provide the following:
- Two fully installed and calibrated CAT 10R-9661 - Kit ELEK GP controllers.
- Documentation of calibration settings and procedures performed.
- A brief report confirming the successful completion of the work and equipment functionality.
5. Period of Performance
The work shall be completed within 5 business days from the start date agreed upon by the contractor and the project manager.
6. Location of Work
The work will be performed at CGC GASCONADE, 100 Arsenal Street, ST. Louis MO, 63118
7. Contractor Responsibilities
The contractor shall:
- Comply with all safety regulations and standards during the execution of work.
- Provide qualified personnel to perform the tasks outlined in this SOW.
- Ensure all tools and equipment used are in good working condition.
8. Government Furnished Equipment (GFE)
None
9. Acceptance Criteria
The work will be considered complete when:
- The old controllers have been removed without damage to the equipment.
- The new controllers have been installed and calibrated per the manufacturer's instructions.
- The equipment is fully operational and meets performance standards.
10. Points of Contact
Questions related to anything listed within this statement of work, or access to the ship should be directed to: MKCS Matt Morin, 571-607-9267, matthew.j.morin@uscg.mil
Award Overview
Contacts
Contracting Officer
Primary Contact
Secondary Contact
Documents
Files (1)
- Download
Statement of Work Gasonade.pdf
111 KBAdded in Combined Synopsis/Solicitation version 3Posted
Lifecycle
- 3Version 3Combined Synopsis/SolicitationArchivedCurrent
USCGC Gasconade SSDG Control Panel replacement
Similar Opportunities
Additional Details
Solicitation Number
70Z08526Q0002157
Archive Date
Jan 21, 2026
Office Address
ALAMEDA, CA, 94501