USCGC Alder Cargo Hatch Welding

Archived on May 26, 2026. Original response deadline: . Full description on SAM.gov.

Overview

Response deadline
8:00 AM PDT
Posted
April 30, 2026
Notice type
Combined Synopsis/Solicitation
Set-aside
Total Small Business Set-Aside (FAR 19.5)
NAICS
336611: Ship Building and Repairing
Agency
Department of Homeland SecurityUS COAST GUARD

Notice details

Office
SFLC PROCUREMENT BRANCH 2(00085)
Place of performance
San Francisco, California, 94130
PSC
J020: MAINT/REPAIR/REBUILD OF EQUIPMENT- SHIP AND MARINE EQUIPMENT
Last updated
Oct 30, 2026
First published
Last updated on SAM.gov

Identifiers

Solicitation number
70z08526Q0024676
Notice ID
6b6676b2d9c540c19a86465f50635c2e

Description

Statement of Work
USCGC ALDER (WLB 216)
Cargo Hold Hatch Cofferdam Drain Piping Crop & Renew
1. Purpose and Scope
. KTR shall renew necessary portions of the cargo hold hatch cofferdam drain piping
located in compartment 2-30-0-AA, Cargo Hold.
2. Deliverables and Performance Requirements
. Protective measures: The KTR must furnish and install all protective measures IAW
SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment
protection).
. Interferences: The KTR must handle all interferences IAW SFLC Std Spec0000,
(Interferences).
. Contamination prevention: The KTR must take all precautions to prevent
contamination of personnel and spaces IAW all applicable Federal, state, and local
regulations.
. Fluid handling: The KTR must remove and dispose of removed fluids from the
affected piping system, IAW all applicable Federal, state, and local regulations. Do not
drain any fluids into any spaced, bilge, or exterior location.
. Piping renewal particulars: The KTR must accomplish the following tasks, using
Coast Guard Drawing 225–WLB–528–001, REV K as guidance:
o Crop out necessary length of piping (3” & 2” diameter), to include all necessary
funnel pieces of the cofferdam system.
o Fabricate necessary piping arrangement previously cropped IAW CG Drawing.
o Install all fabricated piping to include all required gaskets/seals IAW CG
Drawing.
o KTR must provide a means of sealing any open piping while any portion of the
system is open (i.e.: upstream valve blind flange).
. Pipe hangers: Furnish, fit, and install new pipe hangers, as necessary.
. Pipe labeling: The KTR must label affected piping as follows:
o Name of the piping system service.
o Destination, where feasible.
o Direction of flow, indicated by an arrow three inches long pointing away from
the lettering.
. Leak Test: After completing all authorized mechanical (i.e. threaded, bolted, etc.)
joint repairs, the Contractor must test the affected piping system's operation using the
system fluid at normal operating pressure. Ensure zero visible leakage from or
deformation of mechanical parts by repairing all leaks and discrepancies.
. Touch-up preservation: The KTR must prepare and coat all new and disturbed
surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310,
(Touch-ups and minor coating repairs.)
. Piping insulation installation: The KTR must install new insulation materials over
the exposed pipe surfaces at thicknesses appropriate to the application and temperature
ranges specified in ASTM F683 Tables.

Full description on SAM.gov

Award Overview

Contacts

Contracting Officer

Primary Contact

Secondary Contact

Documents

Files (1)

  • ALDER_SOW_CargoHoldHatchCofferdamDrainPiping_CropRenew.pdf

    1.5 MBAdded in Combined Synopsis/Solicitation version 3Posted
    Download

Lifecycle

  1. 3
    Version 3Combined Synopsis/SolicitationArchivedCurrent

    USCGC Alder Cargo Hatch Welding

    Notice 6b6676b2d9c540c19a86465f50635c2e on SAM.gov

Similar Opportunities

Additional Details

Solicitation Number

70z08526Q0024676

Archive Date

May 26, 2026

Office Address

ALAMEDA, CA, 94501