GovChime
Notice ID: 28d5fb2c970b45f6a2ace9384f20f600Combined Synopsis/Solicitation

CRAC Units Replacement for MCE 1211 at GFAFB, ND

Active, responses due . Full description on SAM.gov.

Overview

Response deadline
1:30 PM CST
Posted
October 29, 2026
Notice type
Combined Synopsis/Solicitation
Set-aside
Small Business Set Aside - Total
Agency
Department of WarDepartment of the Air Force

Notice details

Office
AIR COMBAT COMMAND.FA4659 319 CONS PK
Place of performance
Grand Forks AFB, North Dakota, 58205
Last updated
Oct 29, 2026
First published
Last updated on SAM.gov

Identifiers

Solicitation number
FA465927QM001
Notice ID
28d5fb2c970b45f6a2ace9384f20f600

Description

Grand Forks AFB, ND is seeking to replace existing, and procure & install two 8-ton Computer Room Air Conditioner (CRAC) system along with preventative and emergency maintenance & repair services consistent with the PWS attached to this notice. Please review all attachments to this notice for complete details.

Full description on SAM.gov

Award Overview

No prior contract identified

No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.

Contacts

Contracting Officer

Primary Contact

Secondary Contact

Documents

Files (7)

  • Combo FA465927QM001 CRAC Units.pdf

    222 KBAdded in Combined Synopsis/Solicitation version 5Posted
    Download
  • Atch1 Quote Schedule 29Oct26.xlsx

    11 KBAdded in Combined Synopsis/Solicitation version 5Posted
    Download
  • Atch2 PWS CRAC Units for MCE 1211.pdf

    277 KBAdded in Combined Synopsis/Solicitation version 5Posted
    Download
  • Atch3 Provisions and Clauses.pdf

    38 KBAdded in Combined Synopsis/Solicitation version 5Posted
    Download
  • Atch4 SCA WD.pdf

    46 KBAdded in Combined Synopsis/Solicitation version 5Posted
    Download
  • Atch5 DBA WD.pdf

    38 KBAdded in Combined Synopsis/Solicitation version 5Posted
    Download
  • CRAC 1.9 PWS - DRAFT.docx

    36 KBAdded in Sources Sought version 3Posted
    Download

Lifecycle

  1. 3
    Version 3Sources SoughtArchived

    COMPUTER ROOM AIR CONDITIONER (CRAC) REPLACEMENT at GRAND FORKS AFB, ND

    Notice 66fa1abdeefc411588ed607836bd2268 on SAM.gov

  2. 4
    Version 4Combined Synopsis/Solicitation

    Type changed from Sources Sought to Combined Synopsis/Solicitation

    CRAC Units Replacement for MCE 1211 at GFAFB, ND

    Notice d99d7f1660d04762897a2676454439b4 on SAM.gov

  3. 5
    Version 5Combined Synopsis/SolicitationCurrent

    CRAC Units Replacement for MCE 1211 at GFAFB, ND

    Notice 28d5fb2c970b45f6a2ace9384f20f600 on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline
UPDATE 20 AUG 2026 Soliciation Amenmendment added with the government RFI response. Proposal due date: 1 Sep 2026 NLT 2:00PM CST. UPDATE 10 AUG 2026 The site visit sign in sheet has been uploaded. The RFI due date is now 14 August 2026 NLT 2:00PM CST. Please send all RFIs to austin.elm@us.af.mil. This posting is for Tinker AFB – WOSB construction contractors with NAICS 236220. Project Solicitation Number: FA813726R0045 Project Title: 17829397-Decommission & Demo CRAC Units at B3001, Annex G, Tinker AFB Project Location: Tinker Air Force Base 17829397-Decommission & Demo CRAC Units at B3001, Annex G, Tinker AFB- This project is required to safely decommission and remove two (2) obsolete Computer Room Air Conditioning (CRAC) units from a data center facility. The removal of this equipment necessitates the architectural, mechanical, electrical, and structural restoration of the floor, wall, and ceiling systems to return the space to a safe, clean, and fully operational condition. This work ensures the continued integrity, safety, and professional appearance of a critical mission support facility at Tinker AFB. For project specific documents, please email austin.elm@us.af.mil for access. Specific documents cannot be posted on SAM.gov. If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission. In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to. Do not include any Sub-Contractor email addresses. After review of the attached project specific documents, if you are interested to attend the Initial Site Visit, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit. The POC emails are austin.elm@us.af.mil and sharla.flowers_brandon.1@us.af.mil. Your RSVP email must be received by 2:00pm CST on 3 Aug 2026. In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access. If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access. The site visit will be held on 5 Aug 2026. After receipt of your RSVP and EAL if required, an Initial Site Visit will be coordinated. You must attend the Initial Site Visit for the project to be considered eligible to propose.
57%
Solicitation09/01/2026
Amendment 0003 (04 in SAM) -Solicitation has been extended one final time to allow adequate time for responses to RFI Responses (03) -SOW has been updated to reflect responses to RFIs and site visit remarks. -PSC has been updated. -RFI Responses (03) has been uploaded. The United States Government (USG) has a requirement for design-build services set forth under this contract at Mountain Home Air Force Base (MHAFB) to replace the antiquated fire alarm system at the Sagebrush Inn, building 2320, with a new addressable fire alarm system, as required by the Fire Prevention Engineer. The design-build services shall develop a complete design with supporting specifications, analysis (without hazardous material survey for asbestos and lead-based paints, as per the MHAFB environmental office.), and proposed construction project schedule; followed by construction services to include demolition; new installation, and commissioning fire alarm systems in accordance with Unified Facility Criteria (UFC); design drawings and specifications; and other design standards and guidance. Building 2320 has an outdated fire alarm panel and devices which violate the Fire Code requirements. There are no replacement parts available for what is currently installed, which is driving the requirement for a replacement and upgraded system. It is anticipated that the period of performance will be 407 calendar days from the Notice to Proceed. Design phase being limited to 212 days and construction phase to 180 with the remaining days being used for De-mobilization and Close-out. Building 2320 will be occupied with Airmen and the everyday mission of those airmen should be minimally disrupted as much as possible. This project will be broken up into 3 phases. Phase 1 will be dedicated to the design of the project and result in the 65% design package being submitted to USG. At the same time the 65% design is delivered Phase 2, which is dedicated to construction, will kick off. Phase 3 will involve tasks finishing up construction, testing, demobilizing, etc. See attachments below for all relevant documents. For the proposal, all "if applicable" items shall be priced as if they are all applicable. Any proposals with these items not priced will be deemed unacceptable. Site Visit: A site visit for any interested parties will be held on January 6th, 2026 at 2:00 PM MST to walk through the facility and have any questions related to the design-build or technical aspects answered. This site visit is not mandatory, and all relevant questions will be recorded and posted to the solicitation after. All interested parties will need to meet at the visitor's center at 1:30 PM local (MST) to acquire day passes if you do not have base access already. The visitor's center is located just north of the main gate, on the west side of the highway. If you stay to the right as you approach the base, you can turn into the visitor center's parking lot about 100ft before the manned gate. Attempting to enter the base without a pass will result in a lengthy delay. We will be leaving the visitor's center at 2:00 PM local time (MST). Per the evaluation factors, Questions must be submitted no later than 3:00 PM local (Mountain), Jan 12th, 2026 Proposals must be submitted no later than 12:00 PM local (Mountain), Jan 28th, 2026 Questions shall be directed to both POCs.
47%
Solicitation01/28/2026
FA8501-27-RAPID-CIRCUIT F1-170129-OTA Under the RAPID Umbrella Framework: RAPID Progressive Design-Build to Replace Circuit F-01 from Fowler Substation UHHZ170129 Description The Department of the Air Force, 78th Civil Engineer Group, Robins Air Force Base, Georgia, is issuing this Special Notice under the Robins Agile Practices for Infrastructure Development (RAPID) umbrella framework and pursuant to 10 U.S.C. § 2808a. The Government seeks industry Solution Briefs for an anticipated Other Transaction Agreement (OTA) to Replace Circuit F-01 from Fowler Substation at Robins AFB, GA. The requirement includes replacement of all 15kV, 500MCM cable throughout circuit F-01. This will include replacement and removal all broken breakers or bad cable racks, install new bell ends on conduits, and pump water/dirt from manholes. This Special Notice is not an invitation for bids, a request for proposals under the Federal Acquisition Regulation, nor a commitment by the Government to make an award. Any resulting instrument will be an OTA for facility construction and repair under 10 U.S.C. § 2808a. Purpose The purpose of this Area of Interest is to obtain commercially viable, safe, and schedule-credible solutions to design plans for and to perform the replacement of expired high-risk Circuit F01 cabling in order to prevent operational risk, mission delays, and compounding economic costs due to infrastructure failure at Robins Air Force Base, Georgia. The Government requires an integrated approach to address the design, removal of deteriorated cables and replacement with new cable in The Fowler Substation. The selected approach must provide a practical path to execute the work while minimizing disruption to aircraft operations and controlling construction, safety, environmental, and schedule risks. Project Background and Existing Conditions Circuit F-01 has surpassed its operational lifecycle, creating a high-probability risk for catastrophic failure. If the remaining aged portion is not replaced, the installation faces risk of emergency repair premiums and disruption to sustaining airfield infrastructure, supporting safe aircraft movement, installation readiness, and continued mission operations. The work area is slightly congested and impacted by various airfield operations. The Fowler Substation Circuit F-01 will remain in full operation during the entire duration of the project by back feeding with circuit ties. Project Areas Phase 1 (Preconstruction & Collaborative Design): Collaborative design development stakeholders to achieve 65%, site surveys, risk mitigation planning, schedule and establishment of an open-book Guaranteed Maximum Price (GMP) IAW with all other aspects of the SOO. Phase 2 (Final Design & Construction Execution) Completion of final design and full construction execution (exercised upon agreement). Safely construct the facility/project within the agreed GMP and schedule. Assume hazardous materials exist. Address requirements for worker notification, abatement, and disposal. Employ a safety and health professional to provide a HASP per DoDI 6055.01. Comply with Robins Environmental Requirements (Section 01560) submitting Waste Management Report/Landfill Waste Tickets, Solid Waste Disposal Plan, and Qualified Recycling Program (QRP). Appropriately coordinate Stormwater & Erosion Control. Structure execution to allow for payable milestones payments, as well as all other aspects outlined in the SOO. Project-Specific Objectives and Phasing Replace all 15kV, 500MCM cable throughout the distribution of circuit F-01 in its entirety of multiple different installation facilities, while remaining in full operation besides outages and removing and replacing all broken breakers or bad cable racks, install new bell ends on conduits, and pump water/dirt from manholes. Address specific phasing to accommodate congested areas. OTA & RAPID Framework Approach This project is being executed as an Area of Interest (AOI) under the overarching RAPID (Robins Agile Practices for Infrastructure Development) Umbrella Program Notice. In accordance with the RAPID framework, this project utilizes a Progressive Design-Build approach under the standalone statutory authority of 10 U.S.C. § 2808a. The Government will be expecting a 100% completed design package and/or specific phasing and repair requirements followed by the completion of the construction or performance of the designed actions. Competitive Selection Process Phase 1 Solution Brief Requirements The Government reserves the right, at its sole discretion, to determine that a response which does not conform to the requirements or instructions contained in this announcement is ineligible for further consideration. Interested respondents shall submit a Phase 1 Solution Brief in a clear, concise, and organized manner in accordance with this announcement. To facilitate an efficient review, responses shall be prepared in accordance with the instructions and formatting requirements contained in this announcement. Failure to comply with these requirements may increase the risk that the response will not be considered for further evaluation. The Government will evaluate them to identify the most highly qualified parties. Submission Requirement should be submitted by 3:00 PM Eastern Standard Time on or before 20 November 2026. Interested respondents shall submit a Phase 1 Solution Brief consisting of no more than five written pages (5), excluding the cover page. Email is the official form of submission for responses. Surety letters may be attached without counting towards 5 page limit. Page format should be 8.5 x 11. The Solution Brief shall include: Cover Page Company name UEI Mailing address Primary point of contact Email address and telephone number Identification of this RAPID AOI Executive Summary, Team Composition, and Organization Summary of the respondent’s qualifications and anticipated delivery capability Explanation of why the team is qualified for the anticipated requirement The team’s understanding of the Robins Air Force Base operational environment The team’s experience working in occupied facilities, congested site logistics, complex mechanical/electrical system integrations, and adherence to stringent environmental and safety standards. (e.g., hazardous material abatement, and experience with Department of War/Air Force Standards). The team’s proposed approach to Phase 1 collaboration and risk reduction Identification of any material capability, staffing, access, bonding, or teaming assumptions. Past Relevant Construction Capability and Experience Minimum Requirement: The Company must demonstrate a minimum of five (5) years of experience successfully executing construction projects of comparable size, scope, and complexity. Focus: Historical performance in occupied facilities, managing congested site logistics, complex mechanical/electrical system integrations, adhering to environmental and safety standards.(e.g., hazardous material abatement, and experience with Department of Defense/Air Force Standards). Note that while DoD experience is considered, it will not be a deciding factor in determining a firm more qualified. Financial Capacity and Bonding A statement of financial capacity to perform the anticipated work Current single-project and aggregate bonding capacity, if bonds are anticipated; Name of surety Any other information necessary to demonstrate capacity to perform the anticipated project. Construction Execution and Phasing Approach Methodology for physical work execution Utility outage coordination Evaluation & Selection Criteria The Government will utilize a two-step, Qualifications-Based Selection (QBS) process mapped to the RAPID framework to select the Design-Builder. In accordance with PDB methodology, price will not be evaluated during the initial selection process. Selection is based on qualifications, experience, and collaborative capabilities. Step 1: RAPID Phase 1 Equivalent Evaluation of written Solution Brief to establish a short-list of the most highly qualified firms. Price is not evaluated in Step 1. Step 2: RAPID Phases 2 Equivalent Interactive Pitch Presentations/Interviews and evaluation of the Phase 1 PDB Price Proposal (short-listed teams only) to determine the final best-value selection. Step 1: Statement of Qualifications Evaluation Factors Factor 1: Past Relevant Experience Minimum Requirement: The Design-Builder (and/or key teaming partner) must demonstrate a minimum of five (5) years of experience successfully executing construction projects of comparable size, scope, and complexity. Focus: Historical performance in occupied facilities, managing congested site logistics, complex mechanical/electrical system integrations, and adherence to stringent environmental and safety standards (e.g., hazardous materials abatement, and experience with Department of War/Air Force Standards). Note: while DoW experience is considered, it will not be a deciding factor in determining a firm more qualified. Factor 2: Team Composition and Organization Focus: The government will evaluate the proposed organization structure, the integration of design and construction personnel from project inception, and the qualifications of Key Personnel. This includes assessing the proposed site superintendent/project managers ability to oversee operations and coordinate with the Government daily. Factor 3: Project Approach and Understanding Focus: The Government will assess the firm’s understanding of the PDB OTA process and their proposed approach to executing Phase 1 (Design and Preconstruction) and Phase 2 (Final Design & Construction). This includes the firm’s strategy for open-book estimating, schedule development, and manage site-specific constraints at Robins AFB (e.g. restricted area access, flightline requirements, and utility outage coordination). Step 2: Pitch Presentation and Price Evaluation (Final Down-Select) The Government may invite selected respondents to participate in an oral presentation or pitch. Phase 2 may assess the respondent’s technical approach, constructability, airfield-operational integration, phasing, site logistics, safety, environmental approach, risk management, collaboration capability, and preliminary schedule approach. Specific instructions will be provided with invitation to the pitch day. Factor 1: Collaborative Capability and Cultural Fit Focus: Ability to work in a transparent, “open-book” partnership with the 78 CEG Project Delivery Team (PDT) and Base stakeholders. Factor 2: Real-Time Problem-Solving and Risk Management Focus: Capacity to identify, analyze, and mitigate complex project risks. Evaluated based on response to real-time scenarios presented during the Q&A. Factor 3: Innovative Design-Build Solutions Focus: Creative, value-driven, and cost effective courses of action (COAs) proposed to meet the Government’s mission objectives. Factor 4: Financial Capacity and Bonding Focus: Demonstrated financial capacity to support the anticipated project magnitude and, if required by the final OTA, sufficient bonding capacity. Focus: The estimated magnitude of construction associated with this Area of Interest (AOI) is $5M to $10M. This range is provided for planning purposes only and does not constitute an explicit funding guarantee or disclose the Independent Government Estimate. This range is provided to assist interested offerors in determining the necessary single-project and aggregate bonding capacity required to support the subsequent construction agreement. Final Selection and Award Upon concluding presentations, the evaluation team will select the single most highly qualified Design-Builder. The Government will invite the selection firm to negotiate terms, Scope of Services, and a design/preconstruction fee for the Phase 1 OTA Agreement. The Government will address the applicability of Davis-Bacon, prevailing-wage, and other labor requirements during the Pitch phase or before award; any requirements determined applicable will be incorporated into the resulting OTA. Government Reservations The Government reserves the right to: Invite, not invite, or limit respondents advancing to later phases; Conduct technical exchanges; Request clarifications or supplemental information; Negotiate with one or more respondents; Modify, suspend, or cancel this Special Notice; Issue additional notices or requests; and Make no award. Attachments UHHZ170129 - 01005 - SOO - PDB with OTHER TRANSACTIONAL AUTHORITY F1 Binder UHHZ170129 REV 22-02 base power grid F1 REV 22-02 base power grid 0111 REV 22-02 base power grid-Model F1 compact Send all submissions to: angela.whitley@us.af.mil and kristen.denlinger@us.af.mil Notice of Expanded Opportunity, Follow-On Awards, and Multi-Base Utilization; While the immediate requirement under this AOI is to Replace Circuit F-01 from Fowler Substation at Robins AFB, GA, offerors are advised that participation and successful evaluations under this AOI may provide significant strategic opportunities beyond the initial project.
45%
Special Notice11/20/2026
The Design Build Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to design and construct a log cabin kit to be ordered from Conestoga Log Cabins. Existing site already has 2 new Conestoga Log Cabins and continuity is recommended. The Design Build Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to design and construct an asphalt paved parking lot for the Wateree Recreation users and employee use. All work shall be done in strict accordance with this Statement of Work and subject to the terms and conditions of the contract and in accordance with Unified Facilities Criteria (UFC), Unified Facilities Guide Specifications(UFGS), International Building Code (IBC), National Electrical Code (NEC), National Electrical Safety Code (NESC), National Fire Protection Association (NFPA), EPA 402-K-01-001 (2008), South Carolina Department of Transportation (SCDOT), and Shaw Air Force Base Design Standards.
42%
Market Research11/20/2026
This solicitation has been extended to 4:30 PM ET, 16 November 2026 due to the worldwide Microsoft issues. Acknowledgement of this extension is not required on the SF1442. All proposals with acknowledgement of Amendment 1 will be deemed fully responsive. AMENDMENT 01: The purpose of this amendment is to: A. Extend the proposal due date to 12:00 PM ET 13 November 2026. B. Incorporate Questions and Answers, and revised/additional solicitation documents to the solicitation. C. All other terms and conditions remain unchanged.
42%
Solicitation11/16/2026

Additional Details

Solicitation Number

FA465927QM001

Archive Date

Dec 25, 2026

Office Address

GRAND FORKS AFB, ND, 58205