Process Vacuum Pump
Archived on February 10, 2026. Original response deadline: . Full description on SAM.gov.
Description
76 CMXG is requesting the purchase of the following item(s).
1. The addition of an oil-lubricated rotary screw vacuum pump to the existing system, along with an integrated control panel to enable fully redundant operation between the two pumps.
2. The contractor shall provide a complete turnkey solution, including all materials, labor, site preparation, delivery, installation, and commissioning of a fully operable process vacuum system.
3. The requested equipment item descriptions/specifications are outlined below
1. Vacuum Pump Specifications:
a. Equipment:
o Provide a new Quincy QSV-530 rotary screw vacuum pump or equivalent oil-seal screw pump that meets the following requirements as a minimum.
o Nominal capacity: 510 CFM.
o Vacuum range: 18" HgV to 29.9" HgV.
o Electrical requirements: 480V, 3-phase, 60 Hz.
o Maximum dimensions: 51" length × 38" width × 44" height (to fit in designated space)
o Drive system: Electric motor with Variable Speed technology, allowing automatic adjustment of motor speed based on process demand
o Operating modes (minimum): Medium PI control loop, Slow PI control, Forced Maximum Speed, and Fixed Speed Control, or equivalent
o Air/oil separation: Oil-separator tank with oil filter; airflow must be cleaned through the air/oil separator filter before discharge
o Cooling system: Oil cooler
o Condensate system: Designed to prevent condensate accumulation in the oil separator, extending oil life
o Inlet valve: Located between the pump and tank; must automatically close during startup when the pump is not yet warmed up, or incorporate an equivalent design to prevent reverse operation
o Cooling and enclosure: Air-cooled, enclosed in sound-insulated bodywork
o Monitoring: Real-time trending of pump metrics over a customizable time period, including (at minimum) inlet pressure, motor speed, power consumption, and oil temperature, displayed in graphical format
o Restart capability: Automatic restart when voltage is restored after a power failure
o Noise level: Maximum 76 dB
b. Warranty:
o Include a comprehensive 2-year warranty covering all parts and labor from the successful start-up date.
o If contractor-performed periodic PM is required to maintain the warranty, all
o associated service costs must be included in the turnkey package.
2.. Integrated Control System Requirements
c. Control Features:
o System must regulate vacuum supply based on real-time demand for optimal energy
efficiency.
o Implement lead/lag sequencing: primary pump operates under standard
demand; secondary pump engages during scheduled downtime or when additional
capacity is needed.
d. PLC Controller:
o Must support OPC UA (preferred) or BACnet protocol for transmitting
performance metrics, diagnostics, and alarms to Tinker AFB’s network.
o Security protocols must comply with ISO 62443
o Controller must support DHCP for IP address assignment or allow IP
reconfiguration via remote access or on-machine HMI
o Enable secure wired remote access via Tinker’s intranet; requires RJ45 port into
control system
e. Automation Capabilities:
• Include full building automation functionalities such as:
o Scheduling
o Alarm notifications
o Historical data logging
o Energy management
o Custom control routines
o Tagging, templating, and hierarchical navigation
f. User Interface:
• Equip with an HTML-based touchscreen interface display:
o Vacuum levels
o Pump temperature
o Operational status, power status, fault codes, last shutdown data
o Elapsed and run hours
o Audio/visual alarms for exceeding operating thresholds
• All operational health data available on the HMI should be included as data tags
g. Panel Construction:
• All components and wiring must be clearly labeled for ease of maintenance.
• Access to system settings must be secured with user profiles, login credentials, and password
protection.
• Incorporate a protected Emergency Stop push button to prevent accidental
engagement.
3. Project Execution Requirements
h. Installation & Commissioning:
o Contractor to furnish all labor, equipment (pump, auxiliary components, piping,etc.), materials, and tools.
o Conduct start-up procedures and full capacity testing to verify operational
readiness.
i. Documentation Deliverables:
• Provide information for PLC Controller:
o Control System Type
o Model, Make, Manufacturer
o Protocol, and Communication port
o MAC Address
o OS/iOS/FW Version (if applicable)
o Host Name
• Provide data tag documentation
o The name or identifier for each data tag
o A description of what each data tag represents. (A brief explanation of what the data measures)
o The data type of each tag. (e.g., Integer, Float, Boolean, String)
o The units of measurement, if applicable. (e.g., RPM, degrees Celsius, mm
o The communication protocol (e.g., OPC UA, Modbus TCP, MTConnect,
o proprietary API)
Admin: Username/password
Customer: Username/password (if required)
o The update frequency or polling rate of each tag (if known)
o Read-only or read-write status
o Any supporting documentation or links describing tag usage.
• Provide comprehensive as-built documentation using industry standards:
o Equipment drawings
o Factory specifications
o Catalog cut sheets for all ancillary items
o Wiring schematics, logic diagrams, interconnect detailsComplete BOM (Bill of Materials)
o O&M manuals, troubleshooting resources, PM schedules
• Submit both printed and digital formats. All drawings must be provided in .dxf or.dwg format.
Training:
o Deliver on-site training for operators and maintenance staff.
o Training must cover system operation and diagnostic interpretation for
preventive maintenance.
Overview
Award Overview
Possible prior contracts
Sign in to see possible prior contracts for this requirement (matched by agency, NAICS and place of performance; not confirmed).
Contacts
Contracting Officer
Primary Contact
Secondary Contact
Documents
No documents available.
Lifecycle
C26-021- Pre-Solicitation
Formal solicitation typically follows within 30–60 days. (estimate)
- Pre-SolicitationCurrentJan 23, 2026
Process Vacuum Pump
Similar Opportunities
Title | Phase | Agency | NAICS | Set Aside | Posted | Deadline | Location |
|---|---|---|---|---|---|---|---|
Amendment 02 (13 Oct): Questions and Answers posted. Due date remains at October 16, 2026. Amendment 01 (08 Oct): The due date for quotes has been extended to October 16, 2026. Bauer Rebuild Kit in accordance with the Equipment List. Important Note: All amendments must be acknowledged via signature in order for the quote to be complete. | Combined Synopsis | 333912 | Total Small Business Set-Aside | 10/14/2026 | 10/16/2026 | 0, OK | |
Amendment 01 (08 Oct): The due date for quotes has been extended to October 16, 2026. Bauer Rebuild Kit in accordance with the Equipment List. Important Note: All amendments must be acknowledged via signature in order for the quote to be complete. | Combined Synopsis | 333912 | Total Small Business Set-Aside | 10/08/2026 | 10/16/2026 | 0, OK | |
Bauer Rebuild Kit in accordance with the Equipment List. | Combined Synopsis | 333912 | Total Small Business Set-Aside | 09/25/2026 | 10/09/2026 | 0, OK | |
**THIS IS THE PRE-SOLICITATION NOTICE** The Air Force intends to solicit the following supply: The AMXG group is requesting utilization of funds for the purchase of Portable Electrostatic paint cart systems & Spray Guns. The requested equipment item descriptions/specifications are outlined below: PURCHASE DESCRIPTION FOR PORTABLE ELECTROSTATIC PAINT CART SYSTEMS & STANDALONE SPRAY GUNS. SCOPE & IDIQ ORDERING LIMITATIONS The Government requires the procurement of two distinct items: oCLIN 0001 -Fully Integrated Mobile Cart Assemblies oCLIN 0002 -Standalone Electrostatic Spray Guns Brand Restriction: Graco Brand Name ONLY (Genuine Graco components/integrated assemblies). Contract Type: 5-Year IDIQ •Maximum Annual Ceiling: 24 Complete Carts AND 24 Standalone Spray Guns per Ordering Period. •Minimum Order Size: Twelve (12) of CLIN 0001 A Firm Fixed Price type contract is contemplated. Estimated Period of Performance: Five (5) one-year ordering periods. This is a small business set-aside System for Award Management (SAM) is required to receive any award. Contractors can register electronically at https://www.sam.gov/portal/public/SAM/. The NAICS code for this requirement is 333912 with a size standard of 1000 EMP. Interested persons may identify their interest and capability to respond to the requirement by submitting a proposal. Electronic procedures will be used for this solicitation through Beta.sam.gov at https://sam.gov/content/home. No telephone requests. See Note 22. Authority is 10 USC 2304 (c)(1). Foreign Participation: No For further information contact: Sheridan Robison Contracting Officer | Pre-Solicitation | 333912 | Total Small Business Set-Aside | 10/02/2026 | 10/09/2026 | 0, OK | |
Ball Screw and Components | Awarded | 333994 | No Set-Aside | 10/14/2026 | Open | - |
Additional Details
Solicitation Number
C26-021
Archive Date
Feb 10, 2026
Office Address
TINKER AFB, OK, 73145-3303