GovChime
Notice ID: fdc5590ebeab4fcfab76ff3c55c4d95dPresolicitation

CO BR UCPO Blue Mesa Road(1) Blue Mesa Road

Active, no response deadline listed. Full description on SAM.gov.

Overview

Posted
October 27, 2026
Notice type
Presolicitation
Set-aside
Small Business Set Aside - Total
NAICS
237310: Highway, Street, and Bridge Construction
Agency
Department of TransportationFEDERAL HIGHWAY ADMINISTRATION

Notice details

Office
6982AF CENTRAL FEDERAL LANDS DIVISI
Place of performance
Gunnison, Colorado, 81231
PSC
Y1LB: CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS
Last updated
Oct 28, 2026
First published
Last updated on SAM.gov

Identifiers

Solicitation number
6982AF27B000009
Notice ID
fdc5590ebeab4fcfab76ff3c55c4d95d

Description

THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.

PROJECT NAME: CO BR UCPO Blue Mesa Road(1) Blue Mesa Road


Blue Mesa Road is a 1.44-mile corridor located in Gunnison County, CO and provides access to the Bureau of Reclamation (BOR) Power Plant and Pine Creek Trailhead recreational activities on the Curecanti National Recreational Area.

SCOPE OF THE WORK

 Schedule A: Proposed rehabilitation of 0.86 miles to replace existing gravel roadway with asphalt concrete pavement. Reconstruction/Rehabilitation, as needed, for 0.24 miles of existing asphalt to incorporate raising roadway profile at US 50 intersection, drainage improvements including replacement and/or lining of damaged culverts, relocation of traffic counters, formalize parking area with ADA stalls, signing and striping, ditch reconditioning, rockfall mitigation.


Option X: Proposed rehabilitation of 0.34 miles to replace existing gravel roadway with asphalt concrete pavement from BOR gate to Blue Mesa Power Plant, drainage improvements to include replacement of damaged culverts, signing and striping, ditch reconditioning, installation of 6” electrical conduit for purposes of future automatic gate installation.


Option Y: Proposed 6-inch electric conduit installation and 2 ft x 2 ft max trenching for 2,215 LF miles from the electric security gate to The Blue Mesa Power Plant. Conduit will provide future access for BOR to provide electric connection to security gate.
 

PRINCIPAL WORK ITEMS:
Schedule A:

  • 15225-0000 Slope, Reference, and Clearing and Grubbing Control: 1.051 MILE
  • 20301-1900 Removal of Pipe Culvert: 5 EACH
  • 20401-0000 Roadway Excavation: 1,500 CU YD
  • 30201-2000 Roadway Aggregate, Method 2: 2,500 CU YD
  • 30302-1000 Ditch Reconditioning: 3,280 LN FT
  • 40301-0100 Asphalt Concrete Pavement, Type 1: 2,500 TON
  • 60103-0140 Concrete, Headwall for 24-Inch Pipe Culvert (L-Shaped): 3 EACH
  • 60103-0160 Concrete, Headwall for 30-Inch Pipe Culvert: 1 EACH
  • 60103-0280 Concrete, Headwall for 66-Inch Pipe Culvert (Includes Wingwalls): 1 EACH
  • 60201-0800 24-Inch Pipe Culvert: 255 LN FT
  • 60201-0900 30-Inch Pipe Culvert: 45 LN FT
  • 60707-1200 Lining 66-Inch Pipe Culvert (HDPE Slipline): 110 LN FT
  • 60707-1300 Lining 72-Inch Pipe Culvert (HDPE Slipline): 190 LN FT
  • 63401-0300 Pavement Markings, Type B, Solid: 46,000 LN FT

Option X:

  • 15225-0000 Slope, Reference, and Clearing and Grubbing Control: 0.38 MILE
  • 20420-0000 Embankment Construction: 200 CU YD
  • 30201-2000 Roadway Aggregate, Method 2: 700 CU YD
  • 40301-0100 Asphalt Concrete Pavement, Type 1: 650 TON
  • 56603-0000 Reinforced Shotcrete: 180 SQ YD
  • 60704-0000 Cleaning Culvert in Place: 7 EA
  • 63401-0300 Pavement Markings, Type B, Solid: 8,500 LN FT

Option Y:

  • 63610-3410 Conduit, 6-Inch, HDPE (Schedule 40): 2,215 LN FT
  • 63621-1000 Utility Box, Pullbox: 6 EA
  • 63622-0000 Utility Trench: 2,215 LN FT

ANTICIPATED SCHEDULE
Advertisement: November 2026
Award: January 2027
NTP: April 2027
Construction: May 2027- October 2027

ESTIMATED COST RANGE: Between $2,000,000 and $5,000,000

 A NON-MANDATORY PRE-BID SITE VISIT WILL BE HELD NOVEMBER 4TH, 2026 AT 10:00AM. PLEASE SEE ATTACHEMENTS FOR ADDITIONAL INFORMATION 

Full description on SAM.gov

Award Overview

Contacts

Contracting Officer

Primary Contact

Stephanie Navarro

Secondary Contact

Documents

Files (4)

  • DRAFT 01.100 SCR (Final).pdf

    1.2 MBAdded in Presolicitation version 5Posted
    Download
  • DRAFT.02.100 XSS (Final).pdf

    10 MBAdded in Presolicitation version 5Posted
    Download
  • DRAFT. 01.100 Plans (Final).pdf

    19 MBAdded in Presolicitation version 5Posted
    Download
  • PreBid Contractor Site Investigation - NOTICE TO BIDDERS (1) (1).pdf

    90 KBAdded in Presolicitation version 4Posted
    Download

Lifecycle

  1. 3
    Version 3Sources SoughtArchived

    CO BR UCPO Blue Mesa Road(1) Blue Mesa Road

    Notice 0168b3f2fe3c4fa1bfcac893b91d7859 on SAM.gov

  2. 4
    Version 4Presolicitation

    Type changed from Sources Sought to Presolicitation

    CO BR UCPO Blue Mesa Road(1) Blue Mesa Road

    Notice a161f76c94394a8393d040fef7cc67ea on SAM.gov

  3. 5
    Version 5PresolicitationCurrent

    CO BR UCPO Blue Mesa Road(1) Blue Mesa Road

    Notice fdc5590ebeab4fcfab76ff3c55c4d95d on SAM.gov

Similar Opportunities

Additional Details

Solicitation Number

6982AF27B000009

Archive Date

Dec 1, 2026

Office Address

LAKEWOOD, CO, 80228