GovChime
Notice ID: 36a908d38eab417f916c8895c2e9553eSolicitation

RPR Sewer & Power Plant Genset & ATS, MULTI

Archived on June 30, 2026. Original response deadline: . Full description on SAM.gov.

Description

The United States Air Force solicits a Request for Technical Proposals for  FA5575-26-B-0002. This project consists in the installation of new permanent emergency generators with automatic transfer switches and related accessories (grounding, underground lines, interior electrical installation, etc.) for continuous electrical supply to various facilities on base to include the Base Power Plant (Bldg #212) and the Water Treatment Sewage Plant (Bldg #1215). All of the emergency generators on those sites have reached their useful life and are identified for replacement under the Morón Generator Replacement Plan.
Also, Bldg #1215 is fed from a pole-mounted transformer that has caused several bird shock hazards causing electrical power outages; remains of HV OH line will also be replaced with UG sections.

This requirement will be procured using RFO 14.211 and RFO 36, Sealed Bidding and Construction Contracts. The two-step sealed bidding method will be used.

The submission of the Technical Proposal is Step One. Only those contractors that have submitted an acceptable Technical Proposal will pass to Step Two and will be requested to submit a priced bid.

Offerors must follow the instructions in Attachment #1 Technical Proposal Instructions.

Offerors shall submit only one technical proposal containing all required evaluation criteria, to include all factors and any significant subfactors, as listed in the attachment Technical Proposal Instructions. The technical proposal shall NOT include prices or pricing information. The Government will review only one technical proposal per offeror.

Offerors shall submit proposals that are acceptable without additional explanation or information.

The Government may make a final determination regarding a proposal’s acceptability solely on the basis of the proposal as submitted.

The Government may proceed with the second step without requesting further information from any offeror; however, the Government may request additional information from offerors of proposals that it considers reasonably susceptible of being made acceptable and may discuss proposals with their offerors.

Technical proposals must be received no later than 15 June 2026 at 1500 hours local time.  Technical proposals not received by the Contracting Construction Team by the exact date and time for receipt of proposals will not be considered.

A notice of unacceptability or acceptability will be forwarded to the offeror upon completion of the proposal evaluation and final determination. Offerors determined to have submitted an acceptable technical proposal will be able to proceed to Step Two, submission of a Sealed Priced Bid.

Offerors will be expected to submit their sealed priced bids within one or two weeks. The exact date and time of submission and bid opening will be notified in the Request for Bids.

No contract will result from this Request for technical Proposal. This is Step One of the Two Step Sealed Bidding.

In accordance with the Agreement of Defense and Cooperation between the Kingdom of Spain and the United States of America, any contract resulting from this notice/solicitation can only be entered into with companies authorized to carry out these activities in Spain under Spanish law. Companies must meet the requirements established by Spanish legislation for execution of Government works. In addition, in accordance with the Agreement of Defense Cooperation between the U.S.A. and the Kingdom of Spain, Annex 6, Article 1 (3) “The contractors must meet the requirements established by Spanish legislation for execution of government works. A breach of contract on the part of a contractor shall have the same consequences for the contractor for purposes of future contracting with the Spanish government as would occur with a breach of a contract with the Spanish public administration.” and (5) " Spanish material, labor, and equipment shall be used whenever feasible and consistent with the requirements".

Notice to Offeror(s)/Supplier(s): Funds are not presently available for this contract. No award will be made under this solicitation until funds are available. The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer. The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs. Bids must be valid through 30 December 2026

Full description on SAM.gov

Overview

Agency:
Department of War
Office:Not specified
Posted:June 10, 2026
NAICS:236220: Commercial and Institutional Building Construction
Last Updated:Aug 21, 2026
PSC:C222: ARCHITECT AND ENGINEERING- GENERAL: ELECTRICAL SYSTEMS
Set-Aside:No Set aside used
Type:Solicitation
Place of Performance:Seville, Sevilla

Award Overview

Possible prior contracts

Sign in to see possible prior contracts for this requirement (matched by agency, NAICS and place of performance; not confirmed).

Contacts

Contracting Officer

Secondary Contact

Documents

Select documents to download

Showing 6 of 6 items

Document
Source
Agency
Posted Date
File Size
Actions
SolicitationDEPT OF DEFENSEJun 10, 202631.78 KB
SolicitationDEPT OF DEFENSEJun 10, 202614.81 MB
SolicitationDEPT OF DEFENSEJun 10, 2026234.28 KB
SolicitationDEPT OF DEFENSEJun 10, 2026325.09 KB
SolicitationDEPT OF DEFENSEJun 10, 20267.8 MB
25-1008 Part 6.2, Record Drawings.pdf
SolicitationDEPT OF DEFENSEJun 10, 2026210.29 MB

Lifecycle

Solicitation:FA557526B0002
  1. Pre-Solicitation
  2. Solicitation

Award typically follows within 30–90 days after the response deadline. (estimate)

  1. 2×
    Pre-SolicitationApr 17, 2026

    RPR Sewer & Power Plant Genset & ATS, MULTI

    Notice c06c225fdbf44dc3bfe1fb5201bd603b on SAM.gov

  2. 3×
    SolicitationCurrentMay 21, 2026

    RPR Sewer & Power Plant Genset & ATS, MULTI

    Notice 36a908d38eab417f916c8895c2e9553e on SAM.gov

Similar Opportunities

Title
Phase
Agency
NAICS
Set Aside
Posted
Deadline
Location
SUBJECT: — Robins Agile Practices for Infrastructure Development (RAPID) Umbrella Program Notice (10 U.S.C. § 2808a Other Transaction Authority) 1. BOTTOM LINE UP FRONT (BLUF) The Department of the Air Force, specifically the 78th Civil Engineer Group (78 CEG) at Robins Air Force Base (AFB), Georgia, is publishing this Umbrella Program Notice to announce the establishment of the Robins Agile Practices for Infrastructure Development (RAPID) acquisition framework. Operating under the innovative statutory authority of 10 U.S.C. § 2808a, RAPID seeks to completely modernize base infrastructure and execute facility repair and construction projects using flexible, commercial-style Other Transaction Agreements (OTAs). Traditional Federal Acquisition Regulation (FAR) rules do not apply, enabling the Air Force to engage directly with local, regional, and national commercial builders who have limited or no prior federal contracting experience. 2. PROGRAM STRUCTURE & TIMELINE Rather than a single, one-off project solicitation, this Notice establishes the RAPID Umbrella Program, which will remain active for one (1) full year from the date of this posting. During this 12-month period, the Government will periodically publish project-specific solicitations, referred to as Areas of Interest (AOIs), directly under this umbrella. Each independent AOI will outline: The specific facility construction, repair, or modernization project requirements. The exact response date, time, and instructions for submitting Solution Briefs. The collaborative delivery model designated for that project, such as Progressive Design-Build (PDB) utilizing open-book Guaranteed Maximum Price (GMP) pricing, or Build-Only (BO) commercial delivery. Program ParameterDetailsStatutory Authority10 U.S.C. § 2808a (Standalone Facility Construction or Repair Authority)Umbrella Active Period12 Months (Continuous Open Notice)Execution VehicleProject-Specific Areas of Interest (AOIs) & Other Transaction Agreements (OTAs)Key FlexibilitiesNo FAR boilerplate clauses, standard commercial accounting (No CAS), negotiable termsFollow-on AuthorityEligible for non-competitive, sole-source follow-on production construction under § 2808a(c) 3. ELIGIBILITY & PARTICIPATION The RAPID framework actively seeks to lower barriers to entry. Unlike prototype OTAs, 10 U.S.C. § 2808a carries no statutory Nontraditional Defense Contractor (NDC) prerequisites and zero cost-share mandates. Commercial general contractors, specialty trades, design-build firms, and joint ventures are all fully eligible and strongly encouraged to monitor this notice and participate. 4. ACTION REQUIRED FOR INTERESTED VENDORS Interested commercial builders and designers should take the following immediate steps to prepare for upcoming RAPID projects: Monitor This Posting: Bookmark this SAM.gov notice. All project-specific AOIs will be posted as amendments or linked notices here. Register on SAM.gov: Ensure your company has an active, completely free registration and Unique Entity ID (UEI) on SAM.gov. Form Teaming Alliances: Begin networking with regional design firms, general contractors, and trade subcontractors to build integrated design-build consortia capable of executing rapid, commercial-style projects.
Special Notice236220No Set-Aside09/21/202609/16/2027Warner Robins, GA
SUBJECT: — Robins Agile Practices for Infrastructure Development (RAPID) Umbrella Program Notice (10 U.S.C. § 2808a Other Transaction Authority) 1. BOTTOM LINE UP FRONT (BLUF) The Department of the Air Force, specifically the 78th Civil Engineer Group (78 CEG) at Robins Air Force Base (AFB), Georgia, is publishing this Umbrella Program Notice to announce the establishment of the Robins Agile Practices for Infrastructure Development (RAPID) acquisition framework. Operating under the innovative statutory authority of 10 U.S.C. § 2808a, RAPID seeks to completely modernize base infrastructure and execute facility repair and construction projects using flexible, commercial-style Other Transaction Agreements (OTAs). Traditional Federal Acquisition Regulation (FAR) rules do not apply, enabling the Air Force to engage directly with local, regional, and national commercial builders who have limited or no prior federal contracting experience. 2. PROGRAM STRUCTURE & TIMELINE Rather than a single, one-off project solicitation, this Notice establishes the RAPID Umbrella Program, which will remain active for one (1) full year from the date of this posting. During this 12-month period, the Government will periodically publish project-specific solicitations, referred to as Areas of Interest (AOIs), directly under this umbrella. Each independent AOI will outline: The specific facility construction, repair, or modernization project requirements. The exact response date, time, and instructions for submitting Solution Briefs. The collaborative delivery model designated for that project, such as Progressive Design-Build (PDB) utilizing open-book Guaranteed Maximum Price (GMP) pricing, or Build-Only (BO) commercial delivery. Program ParameterDetailsStatutory Authority10 U.S.C. § 2808a (Standalone Facility Construction or Repair Authority)Umbrella Active Period12 Months (Continuous Open Notice)Execution VehicleProject-Specific Areas of Interest (AOIs) & Other Transaction Agreements (OTAs)Key FlexibilitiesNo FAR boilerplate clauses, standard commercial accounting (No CAS), negotiable termsFollow-on AuthorityEligible for non-competitive, sole-source follow-on production construction under § 2808a(c) 3. ELIGIBILITY & PARTICIPATION The RAPID framework actively seeks to lower barriers to entry. Unlike prototype OTAs, 10 U.S.C. § 2808a carries no statutory Nontraditional Defense Contractor (NDC) prerequisites and zero cost-share mandates. Commercial general contractors, specialty trades, design-build firms, and joint ventures are all fully eligible and strongly encouraged to monitor this notice and participate. 4. ACTION REQUIRED FOR INTERESTED VENDORS Interested commercial builders and designers should take the following immediate steps to prepare for upcoming RAPID projects: Monitor This Posting: Bookmark this SAM.gov notice. All project-specific AOIs will be posted as amendments or linked notices here. Register on SAM.gov: Ensure your company has an active, completely free registration and Unique Entity ID (UEI) on SAM.gov. Form Teaming Alliances: Begin networking with regional design firms, general contractors, and trade subcontractors to build integrated design-build consortia capable of executing rapid, commercial-style projects.
Special Notice236220No Set-Aside09/21/202609/16/2027Warner Robins, GA
Amendment 0002- The purpose of this Amendment is to: -Extend the proposal due date from 11 September 2026 to 16 September 2026 at 0000GMT / 0900JST -Update Requirement Description text -Remove requirement for Bond/Guarantee -Update RFI responses with further clarifications (2 clarified responses. Highlighted Yellow) -Add or Replace Updated Section J Attachments: -Replace previous SOW (Rev5) with updated revision 8 -Add updated Drawings (Drawing labeled "########" on SF30 is labeled "Transfer Surface Drawing" on SAM. Original Document name is "米軍工事転移表面") All other terms and conditions remain the same. Amendment 0001- The purpose of this amendment is to provide the responses to all RFIs submitted by the August 21st deadline. Additional questions will only be accepted if they relate directly to one of the government responses. Follow-up questions must be submitted by August 28th, at 1200 JST. As of now, there will not be an extension in the proposal submission deadline. If an updated SOW and drawings are not provided before the deadline, the answers in the RFIs will take precedence over any conflicting information within the documents. All other terms and conditions remain the same. Amendment 0: Due to internal system issues, this amendment will be considered "Amendment 0" for acknowledgement of amendments on block 19 of the SF 1442. We apologize for the inconvenience. Amendment details - Correction in response to RFI. "Block 13.b of the SF 1442" requires a bid bond/guarantee. Disregard this, as a bid bond/guarantee is not required for this requirement. The 356th Expeditionary Theater Support Group (356 ETSG/CONS) Contracting Office is posting this solicitation for a design-build construction project to deliver a membrane shelter at Matsushima Japan Air Self-Defense Force (JASDF) Base, Japan. Complete project requirements, technical specifications, and performance parameters are detailed in the attached draft Statement of Work (SOW) and corresponding project drawings. Project Magnitude / ROM (Rough Order of Magnitude): Between $1,000,000 and $5,000,000 USD. ⚠️ SPECIAL NOTICE: MANDATORY JAPANESE LICENSING REQUIREMENT In accordance with Japanese Construction Industry Law (Law No. 100 of 1949), the Prime Contractor (or the lead entity of a joint venture) MUST hold a valid Japanese Construction License at the time of proposal submission. No Subcontracting of License: To ensure direct performance accountability and robust contract administration, the offering Prime Contractor itself (or the lead entity of a Joint Venture) must hold this license. Relying on a subcontractor's Japanese Construction License to satisfy this requirement is prohibited. Compliance: Offerors must submit proof of the Prime Contractor's license with their technical proposal. Sub-contracting a company with the license will not be permitted. Evaluation: This is a strict pass/fail threshold requirement. Proposals from prime vendors who do not hold this license or cannot demonstrate legal compliance with Japanese construction licensing laws will be determined non-compliant and excluded from evaluation. 1. Critical Acquisition Milestones & Deadlines Please review the timeline below carefully. Late submissions or questions will not be entertained unless explicitly authorized by the Contracting Officer. All times are in Japan Standard Time (JST). Site Visit (Completed): An organized pre-solicitation site visit was held on 05 August 2026. No secondary or additional site visits will be hosted. Additional RFI Deadline: 21 August 2026 @ 09:00 AM JST. Additional RFIs must be sent via email to both designated POCs (see below) by this deadline to be answered. RFI Responses Posted: The government's RFI responses will be posted as an amendment to this notice no later than 24 August 2026. Proposal Submission Due Date: 11 September 2026 @ 09:00 AM JST. 2. Important Submission & Evaluation Instructions Request for Information (RFI) Ground Rules: Resulting from the August 5th site visit, RFIs were submitted and are currently in the process of being answered. Once the formal RFI responses are posted on August 24th, additional questions will only be accepted if they relate directly to one of the published government responses. This process may result in an extended proposal submission window, but does not guarantee additional response time. Proposal Due Date Clarification: Please ignore any system-generated defaults on SAM.gov or within the SF 1447 block that state "00:00 local time" as the submission deadline. The official, legally binding deadline for proposal receipt is September 11th, 2026, at 09:00 AM JST. Evaluation Guidelines: The full SF 1447 solicitation document contains all guidelines for proposal submission (Section L) and the evaluation factors for award (Section M). These instructions and evaluation factors will only be amended to correct clerical errors or clear up misunderstandings. 3. Contact Instructions Please direct all questions, RFIs, and final proposal submissions* via email to both of the following Points of Contact: SSgt Cameron Smith: cameron.smith.16@us.af.mil SSgt Daniel Callahan: daniel.callahan.7@us.af.mil * For submissions over 10mb, they will not be accepted by our internal e-mail security measures. Offerors must submit a request for a DoDSAFE link to submit their proposals no later than 48hrs before submission deadline.
Solicitation236220No Set-Aside08/27/202609/16/2026Higashimatsushima, JP-04
Amendment 0002 Correction- RFI reponses were not included with Amendment 0002. Added to attachments, [RFIs-FA502526RB006 (27 Aug Updates)] Amendment 0002- The purpose of this Amendment is to: -Extend the proposal due date from 11 September 2026 to 16 September 2026 at 0000GMT / 0900JST -Update Requirement Description text -Remove requirement for Bond/Guarantee -Update RFI responses with further clarifications (2 clarified responses. Highlighted Yellow) -Add or Replace Updated Section J Attachments: -Replace previous SOW (Rev5) with updated revision 8 -Add updated Drawings (Drawing labeled "########" on SF30 is labeled "Transfer Surface Drawing" on SAM. Original Document name is "米軍工事転移表面") All other terms and conditions remain the same. Amendment 0001- The purpose of this amendment is to provide the responses to all RFIs submitted by the August 21st deadline. Additional questions will only be accepted if they relate directly to one of the government responses. Follow-up questions must be submitted by August 28th, at 1200 JST. As of now, there will not be an extension in the proposal submission deadline. If an updated SOW and drawings are not provided before the deadline, the answers in the RFIs will take precedence over any conflicting information within the documents. All other terms and conditions remain the same. Amendment 0: Due to internal system issues, this amendment will be considered "Amendment 0" for acknowledgement of amendments on block 19 of the SF 1442. We apologize for the inconvenience. Amendment details - Correction in response to RFI. "Block 13.b of the SF 1442" requires a bid bond/guarantee. Disregard this, as a bid bond/guarantee is not required for this requirement. The 356th Expeditionary Theater Support Group (356 ETSG/CONS) Contracting Office is posting this solicitation for a design-build construction project to deliver a membrane shelter at Matsushima Japan Air Self-Defense Force (JASDF) Base, Japan. Complete project requirements, technical specifications, and performance parameters are detailed in the attached draft Statement of Work (SOW) and corresponding project drawings. Project Magnitude / ROM (Rough Order of Magnitude): Between $1,000,000 and $5,000,000 USD. ⚠️ SPECIAL NOTICE: MANDATORY JAPANESE LICENSING REQUIREMENT In accordance with Japanese Construction Industry Law (Law No. 100 of 1949), the Prime Contractor (or the lead entity of a joint venture) MUST hold a valid Japanese Construction License at the time of proposal submission. No Subcontracting of License: To ensure direct performance accountability and robust contract administration, the offering Prime Contractor itself (or the lead entity of a Joint Venture) must hold this license. Relying on a subcontractor's Japanese Construction License to satisfy this requirement is prohibited. Compliance: Offerors must submit proof of the Prime Contractor's license with their technical proposal. Sub-contracting a company with the license will not be permitted. Evaluation: This is a strict pass/fail threshold requirement. Proposals from prime vendors who do not hold this license or cannot demonstrate legal compliance with Japanese construction licensing laws will be determined non-compliant and excluded from evaluation. 1. Critical Acquisition Milestones & Deadlines Please review the timeline below carefully. Late submissions or questions will not be entertained unless explicitly authorized by the Contracting Officer. All times are in Japan Standard Time (JST). Site Visit (Completed): An organized pre-solicitation site visit was held on 05 August 2026. No secondary or additional site visits will be hosted. Additional RFI Deadline: 21 August 2026 @ 09:00 AM JST. Additional RFIs must be sent via email to both designated POCs (see below) by this deadline to be answered. RFI Responses Posted: The government's RFI responses will be posted as an amendment to this notice no later than 24 August 2026. Proposal Submission Due Date: 11 September 2026 @ 09:00 AM JST. 2. Important Submission & Evaluation Instructions Request for Information (RFI) Ground Rules: Resulting from the August 5th site visit, RFIs were submitted and are currently in the process of being answered. Once the formal RFI responses are posted on August 24th, additional questions will only be accepted if they relate directly to one of the published government responses. This process may result in an extended proposal submission window, but does not guarantee additional response time. Proposal Due Date Clarification: Please ignore any system-generated defaults on SAM.gov or within the SF 1447 block that state "00:00 local time" as the submission deadline. The official, legally binding deadline for proposal receipt is September 11th, 2026, at 09:00 AM JST. Evaluation Guidelines: The full SF 1447 solicitation document contains all guidelines for proposal submission (Section L) and the evaluation factors for award (Section M). These instructions and evaluation factors will only be amended to correct clerical errors or clear up misunderstandings. 3. Contact Instructions Please direct all questions, RFIs, and final proposal submissions* via email to both of the following Points of Contact: SSgt Cameron Smith: cameron.smith.16@us.af.mil SSgt Daniel Callahan: daniel.callahan.7@us.af.mil * For submissions over 10mb, they will not be accepted by our internal e-mail security measures. Offerors must submit a request for a DoDSAFE link to submit their proposals no later than 48hrs before submission deadline.
Solicitation236220No Set-Aside08/27/202609/16/2026Higashimatsushima, JP-04
Amendment 0001- The purpose of this amendment is to provide the responses to all RFIs submitted by the August 24th deadline. Additional questions will only be accepted if they relate directly to one of the government responses. Follow-up questions must be submitted by August 28th, at 1200 JST. As of now, there will not be an extension in the proposal submission deadline. If an updated SOW and drawings are not provided before the deadline, the answers in the RFIs will take precedence over any conflicting information within the documents. All other terms and conditions remain the same. The 356th Expeditionary Theater Support Group (356 ETSG/CONS) Contracting Office is posting this solicitation for two (2) design-build construction projects to deliver storage shelters at Misawa Air Base, Japan. Complete project requirements, technical specifications, and performance parameters are detailed in the corresponding attached draft Statement of Work (SOW) and project drawings. The following are the ROMs for each site: Project Magnitude / ROM (Rough Order of Magnitude): Site 1 (C-1) Applicable Proposal ROM: $1,000,000 to $5,000,000 Site 2 (A-1) Applicable Proposal ROM: $3,000,000 to $7,000,000 1. Critical Acquisition Milestones & Deadlines Please review the timeline below carefully. Late submissions or questions will not be entertained unless explicitly authorized by the Contracting Officer. All times are in Japan Standard Time (JST). Site Visit (Completed): An organized pre-solicitation site visit was held on 03 August 2026. No secondary or additional site visits will be hosted. Additional RFI Deadline: 21 August 2026 @ 09:00 AM JST. Additional RFIs must be sent via email to both designated POCs (see below) by this deadline to be answered. RFI Responses Posted: The government's RFI responses will be posted as an amendment to this notice no later than 24 August 2026. With the RFIs, the final SOW, drawings and related updates will be provided as well. Proposal Submission Due Date: 11 September 2026 @ 12:00PM JST. Multiple or Single Award: At this time, the Government intends to make two separate awards (one contract for each site) to the responsible Offeror(s) whose proposal(s) provide the best value to the Government. There is a possibility of one single award, but it is not guaranteed. The Government will conduct two distinct evaluations- one for Site 1 and one for Site 2. Offerors may win one site, both sites, or neither site. 2. Important Submission & Evaluation Instructions Request for Information (RFI) Ground Rules: Resulting from the August 3rd site visit, RFIs were submitted and are currently in the process of being answered. Once the formal RFI responses are posted by August 24th, additional questions will only be accepted if they relate directly to one of the published government responses. This process may result in an extended proposal submission window, but does not guarantee additional response time. Proposal Due Date Clarification: Please ignore any system-generated defaults on SAM.gov or within the SF 1447 block that state "03:00 GMT" as the submission deadline. The official, legally binding deadline for proposal receipt is September 11th, 2026, at 12:00 PM JST. Evaluation Guidelines: The full SF 1447 solicitation document contains all guidelines for proposal submission (Section L) and the evaluation factors for award (Section M). These instructions and evaluation factors will only be amended to correct clerical errors or clear up misunderstandings. 3. Contact Instructions Please direct all questions, RFIs, and final proposal submissions* via email to both of the following Points of Contact: SSgt Cameron Smith: cameron.smith.16@us.af.mil SSgt Daniel Callahan: daniel.callahan.7@us.af.mil * For submissions over 10mb, they will not be accepted by our internal e-mail security measures. Offerors must submit a request for a DoDSAFE link to submit their proposals no later than 48hrs before submission deadline.
Solicitation236220No Set-Aside08/24/202609/11/2026Misawa Air Base, JP-02

Additional Details

Solicitation Number

FA557526B0002

Archive Date

Jun 30, 2026

Place of Performance Country

SPAIN

Office Address

APO, AE, 09643-6585