WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
Responses closed . Full description on SAM.gov.
Overview
- Response deadline
- 10:00 AM CDT
- Posted
- September 16, 2026
- Notice type
- Combined Synopsis/Solicitation
- Set-aside
- Small Business Set Aside - Total
- NAICS
- 236210: Industrial Building Construction
- Agency
- Department of WarDepartment of the Air Force
Notice details
- Office
- AIR FORCE MATERIEL COMMAND.AIR FORCE SUSTAINMENT CENTER.FA8137 AFSC PZIOC
- Place of performance
- 0, Oklahoma, 73145
- Last updated
- Oct 28, 2026
- First published
- Last updated on SAM.gov
- Additional reporting
- Recovery Act
Identifiers
- Solicitation number
- FA813726R0049
- Notice ID
- 80865a859f084ba2bd23733ef6a71e3b
Description
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Updated 16 September 2026
Attached two pictures pertaining to RFIs 15 and 36.
Proposal Due Date: 18 September 2026
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Updated 14 September 2026
Proposal Due Dates have been extended to 18 September 2026 at 10:00 AM CST.
Attached Government Responses to RFIs, Amendment 0002, and Amendment 0003.
Proposal Due Date: 18 September 2026
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Updated 08 September 2026
Submittal Register has been uploaded in an excel document.
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Updated 14 August 2026
Posted a new accessible Section L document, previous document was unaccessible.
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Updated 14 August 2026
Posted a new accessible Section L document.
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
Updated 13 August 2026
Attached Site Visit Sign in, Section L, Section M and Submittal Register
RFIs are due 19 August 2026.
Proposals are due 14 September 2026.
Only the MAC BOA Holder GCs that attended Site Visit on 12 August 2026 will be able to continue forward toward the award.
This posting is for Tinker AFB - MAC BOA Holders ONLY.
Updated 12 August 2026.
Posted Amendment FA813726R00490001 updating proposal due dates.
New Proposal Due Dates 14 September at 2:00PM CST.
This posting is for Tinker AFB - MAC BOA Holders ONLY.
This posting is for Tinker AFB - MAC BOA Holders ONLY.
Project Solicitation Number: FA813726R0049
Project Title: WWYK21038 – Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
Project Location: Tinker AFB - B3001
Repair by renovation of hallways at project location within B3001 at Tinker Air Force Base (AFB) Oklahoma 73145
The estimated project value is below $25M and is restricted to SB MAC BOA holders only.
Project specific documents are attached to this posting.
If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission. In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to. Do not include any Sub-Contractor email addresses.
This posting is for Tinker AFB - MAC BOA Holders ONLY.
After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit. Your RSVP email must be received within 5 calendar days from the posting of this project. In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access. If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access. ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor.
After receipt of your RSVP and EAL if required, Initial Site Visit is set for Wednesday, August 12th at 2:00 PM CST B3001.
You must attend the Initial Site Visit for the project to be considered eligible to propose.
This posting is for Tinker AFB - MAC BOA Holders ONLY.
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Contracting Officer
Primary Contact
Secondary Contact
Documents
Files (16)
- Download
RFI 15_36 Picture.jpg
163 KBAdded in Combined Synopsis/Solicitation version 9Posted - Download
RFI 15_36 Picture 2.jpg
206 KBAdded in Combined Synopsis/Solicitation version 9Posted - Download
Solicitation Amendment - FA813726R00490003.pdf
588 KBAdded in Combined Synopsis/Solicitation version 8Posted - Download
Solicitation Amendment - FA813726R00490002.pdf
588 KBAdded in Combined Synopsis/Solicitation version 8Posted - Download
WWYK240052 Renovate Hallway RFIs_COR.pdf
181 KBAdded in Combined Synopsis/Solicitation version 8Posted - Download
ATT8_240052_Submittal Register.xlsx
53 KBAdded in Combined Synopsis/Solicitation version 7Posted - Download
Section L - Instructions to Offerors .pdf.pdf
197 KBAdded in Combined Synopsis/Solicitation version 6Posted - Download
ATT8_240052_Submittal Register.pdf
211 KBAdded in Combined Synopsis/Solicitation version 4Posted - Download
Section M - Evaluation Factors for Award.pdf
186 KBAdded in Combined Synopsis/Solicitation version 4Posted - Download
Site Visit Sign In WWYK240052.pdf
95 KBAdded in Combined Synopsis/Solicitation version 3Posted - Download
Solicitation Amendment - FA813726R00490001.pdf
588 KBAdded in Combined Synopsis/Solicitation version 2Posted - Download
Solicitation - FA813726R0049.pdf
590 KBAdded in Combined Synopsis/Solicitation version 1Posted - Download
EAL List - 240052.xlsx
62 KBAdded in Combined Synopsis/Solicitation version 1Posted - Download
ATT7_240052_MACB SOW.pdf
304 KBAdded in Combined Synopsis/Solicitation version 1Posted - Download
ATT9_240052_Drawings.pdf
954 KBAdded in Combined Synopsis/Solicitation version 1Posted - Download
240052_Specs(1).zip
174 MBAdded in Combined Synopsis/Solicitation version 1Posted
Lifecycle
- 1Version 1Combined Synopsis/Solicitation
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
- 2Version 2Combined Synopsis/Solicitation
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
- 3Version 3Combined Synopsis/Solicitation
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
- 4Version 4Combined Synopsis/Solicitation
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
- 5Version 5Combined Synopsis/Solicitation
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
- 6Version 6Combined Synopsis/Solicitation
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
- 7Version 7Combined Synopsis/Solicitation
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
- 8Version 8Combined Synopsis/Solicitation
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
- 9Version 9Combined Synopsis/SolicitationCurrent
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
This posting is for Tinker AFB - MAC BOA Holders ONLY. UPDATE 08- September 11, 2026 1.Correct Enviromental Report attached and labeled as: Enviromental Report 9-11 2. Amendment attached and labled as: Solicitation Amendment FA813726R00330003 SF 30 3. Due to CORRECT attachment the Proposal date will be extended to: September 16, 2026 at 1200 CST, email them to CS dorothy.inoa@us.af.mil AND sharla.flowers_brandon.1@us.af.mil. This posting is for Tinker AFB - MAC BOA Holders ONLY. UPDATE 07- September 03, 2026 1. Additional RFIs are answered and labeled as: Pre-Bid_RFI_8-28 COR 2. Solicitation Amendment labeled as: Solicitation Amendment FA813726R00330003 SF 30.2 3. Additional information included and labeled as: PW ELMT North LAYOUT - 2.3.26 4. Email Proposals to CS Dorothy Inoa, dorothy.inoa@us.af.mil AND CO Sharla Flowers, sharla.flowers_brandon.1@us.af.mil by September 11, 2026, 2PM CST. This posting is for Tinker AFB - MAC BOA Holders ONLY. UPDATE 06- August 21, 2026 1. Additional RFIs due Wednesday August 26, 2026 2PM CST. Email CS Dorothy Inoa, dorothy.inoa@us.af.mil AND CO Sharla Flowers, sharla.flowers_brandon.1@us.af.mil . 2. RFPs due date September 11, 2026, 2PM CST. This posting is for Tinker AFB - MAC BOA Holders ONLY. UPDATE 05- August 17, 2026 1. Environmental Report Attached as: Environmental Report. 2.Proposal Due Date: September 11, 2026, 2PM CST. 3. Send all questions to CS Dorothy Inoa, dorothy.inoa@us.af.mil AND CO Sharla Flowers, sharla.flowers_brandon.1@us.af.mil This posting is for Tinker AFB - MAC BOA Holders ONLY. UPDATE 04- August 11, 2026 1) Soliciation will be extended for 30 days. 2) New due date for proposals: September 11, 2026, 2PM CST. 3) Soliciation amendment attached as: Solicitation Amendment FA813726R00330002 SF 30 4) Send proposals to SrA Dorothy Inoa: dorothy.inoa@us.af.mil and CC Sharla Flowers Brandon: sharla.flowers_brandon.1@us.af.mil . This posting is for Tinker AFB - MAC BOA Holders ONLY. UPDATE 03-July 7, 2026 1) Soliciation amendment attached as document: Solicitation-FA8137326R0033-amendment 2) New due date for proposals will be provided when the new information is recieved and provided to all contractors. 3) Reach out to SrA Dorothy Inoa: dorothy.inoa@us.af.mil and CC Sharla Flowers Brandon: sharla.flowers_brandon.1@us.af.mil with any questions. This posting is for Tinker AFB - MAC BOA Holders ONLY. UPDATE 02- June 24, 2026 1) RFI's and their responses have been posted in the attached document labeled: RFI Questions 6-24-2026 2) Proposal Response Date: 08 July 2026 at 2PM CST. 3) Send proposals to SrA Dorothy Inoa: dorothy.inoa@us.af.mil and CC Sharla Flowers Brandon: sharla.flowers_brandon.1@us.af.mil This posting is for Tinker AFB - MAC BOA Holders ONLY. UPDATE 01 - May 28, 2026 1) Site Visit was held and concluded on May 28, 2026. 2) RFIs are due on Thursday June 04, 2026 COB. All RFIs will be sent to CE on Friday June 05, 2026. 3) Sign in sheet has been added to the attachments. This posting is for Tinker AFB - MAC BOA Holders ONLY. After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit. Your RSVP email must be received within 5 calendar days from the posting of this project. In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access. If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access. ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor. After receipt of your RSVP by May 21, 2026 COB CST and EAL if required, an Initial Site Visit is set for May 28, 2026 –– B3001. RSVP required for TIME of the inital site visit. A calendar invite will be sent out to those who RSVP. You must attend the Initial Site Visit for the project to be considered eligible to propose. This posting is for Tinker AFB - MAC BOA Holders ONLY. | 72% | Solicitation | 09/16/2026 |
Update 28 October 2026 An Amended Solicitation has been created to cancel the project due to funding. The amended solicitation has been attached. ======================================================== Update 01: June 12, 2026 Solicitaiton was amended to extend the offer due date from June 15, 2025, to June 22, 2026 Amended Drawings were attached below as well as additional clasuses RFO 52.240-93 and R-DFARS 252.240-7997, In relation to RFI Answer 30 and 31. Pre Bid RFI Q&A has been posted below as well. Only the MAC BOA Holder GCs that attended Site Visit on 19 MAY 2026 will be able to continue forward toward the award. Updated 19 MAY 2026 Initial Site Visit Sign In Sheet has been attached. RFIs due 27 MAY 2026 Proposals due 15 June 2026 Only the MAC BOA Holder GCs that attended Site Visit on 19 MAY 2026 will be able to continue forward toward the award. This posting is for Tinker AFB - MAC BOA Holders ONLY. UPDATE 01 1) The Site Visit for this project is Scheduled for 19 May 2026 at 0900 (9:00 am) UPDATE 02 5/14/2026 1) Solicitation Amendment FA813726R00240001 Created to add section L-Instructions to Offerors and M- Evaluation Factors for Award This posting is for Tinker AFB - MAC BOA Holders ONLY. Project Solicitation Number: FA813726R0024 Project Title: WWYK210116 – REPLACE HVAC, B285 Project Location: Tinker AFB -B285 Repair the HVAC system at project location within B285 at Tinker Air Force Base (AFB) Oklahoma 73145 The estimated project value is between $1,000,000 and $5,000,000 and is restricted to SB MAC BOA holders only. Project specific documents are attached to this posting. If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission. In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to. Do not include any Sub-Contractor email addresses. This posting is for Tinker AFB - MAC BOA Holders ONLY. After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit. Your RSVP email must be received within 3 calendar days from the posting of this project. In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access. If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access. ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor. Only sevein individuals will be allowed per prime contractor. Site visit date will be (19 May 2026) and RSVPs are due 15 May 2026. Calendar invite will be sent to only those who have RSVPd. You must attend the Initial Site Visit for the project to be considered eligible to propose. This posting is for Tinker AFB - MAC BOA Holders ONLY. | 63% | Solicitation | 06/22/2026 |
Updated: June 17th, 2026 Solicitation Amended to extend Offer Due date from 2:00pm (CDT) June 17, 2026, to 2:00pm (CDT) June 24, 2026, Design narrative has also been attached to Section J- List of attachments. The Following Clauses have been added: 52.223-23 Sustainable Products and Services. (DEVIATION 2025-O0004), 52.240-93 Basic Safeguarding of Covered Contractor Information Systems. (Deviation 2026-O0038, 252.204-7012), 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. (DEVIATION 2024-O0013 REVISION 1) 252.240-7997 NIST SP 800-171 DoD Assessment Requirements. (DEVIATION 2026-O0025). Updated: June 16th, 2026 Design Narrative, attachment 4 has been attached below in regards to SOW 4.0. Updated: June 12, 2026 Pre Bid RFI Anwers have been submitted below Updated: June 09 2026 As-Built Info has been attached below Updated: June 08 2026 Amendment 001 (June 08 2026) Solicitation Amended to Extend the Offer Due Date from June 08th 2026 to June 17th 2026 Only the MAC BOA Holder GCs that attended Site Visit on 20 MAY 2026 will be able to continue forward toward the award. Updated 20 MAY 2026 Initial Site Visit Sign In Sheet has been attached. RFIs due 28 MAY 2026 Proposals due 08 June 2026 Only the MAC BOA Holder GCs that attended Site Visit on 20 MAY 2026 will be able to continue forward toward the award. This posting is for Tinker AFB - MAC BOA Holders ONLY. Project Solicitation Number: FA813726R0028 Project Title: WWYK260003, REPAIR ROOF, ELECT, HVAC & RESTROOMS, B4019 Project Location: Tinker AFB - B4019 Renovation of B4019 for office use at Tinker Air Force Base (AFB) Oklahoma 73145 The estimated project value is below $25M and is restricted to SB MAC BOA holders only. Project specific documents are attached to this posting. If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission. In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to. Do not include any Sub-Contractor email addresses. Currently, the Solicitation – Request for Proposal (RFP) is in the draft stage and will be posted once available. This posting is for Tinker AFB - MAC BOA Holders ONLY. After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit. Your RSVP email must be received within 3 calendar days from the posting of this project. In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access. If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access. ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor. Initial Site Visit is set for May 20th, 2026, 10:00 AM, At Building 4019 north side parking lot. *Only 7 attendees per Prime Contractor allowed to attend Site Visit.* You must attend the Initial Site Visit for the project to be considered eligible to propose. This posting is for Tinker AFB - MAC BOA Holders ONLY. | 63% | Combined Synopsis | 06/24/2026 |
November 13, 2026 1. Extended proposal due date to 30 November 2026 at 1PM 2. Incorporate the following updated documents: Attachment 3 Section M Evaluation Criteria_10 Nov 26 Attachement 2 Section L Instructions to Offerors_10 Nov 26 Attachment_2d_Appendix_D_MACC_FOSelf_Scoring_Matrix_10 Nov 26 Attachment_2f_Appendix_F_MACC_FOCross_Reference_Matrix_05 Nov 26 Attachment_2e_Appendix_E_MACC_SBCross_Reference_Matrix_05 Nov 26 01 25 26_25 Oct 26 01 45-00_25 Oct 26 Attachement 1 Statement of Work 5_Nov_26 Attachment_2c_Appendix_C_MACC_SBSelf_Scoring_Matrix_05 Nov 26 3. Provide for reference use only the following documents intended to assist prospective contractors in identifying changes. The documents listed in paragraph 2 have been substantially edited. Although the government attempted to identify every change, prospective offerors are required to review them in their entirety as the documents provided in paragraph 3 are for reference only and may not have captured every change. MACC Summary of Changes October 2026 (Reference Only) Attachment_2c_Appendix_C_MACC_SBSelf_Scoring_Matrix_25 Oct 26 (Reference Only) Attachment_2d_Appendix_D_MACC_FOSelf_Scoring_Matrix_25 Oct 26 (Reference Only) Attachment_2e_Appendix_E_MACC_SBCross_Reference_Matrix_25 Oct 26 (Reference Only) Attachement 1 Statement of Work r4_25 Oct 26 (Reference Only) Attachement_2f_Appendix_F_MACC_FOCross_Reference_Matrix_25 Oct 26 (Reference Only) Attachment 2 Section L Instructions to Offerors_25 Oct 26 (Reference Only) Attachment 3 Section M Evaluation Criteria_25 Oct 26 Follow up Questions and Answers 3 Nov 2026 October 22, 2026 Please see amendment 0006 attached. Complete RFI responses and documents will be posted at a later date. October 7, 2026 The government is still working through RFI followup responses and the subsequent amendment. This amendment adjusts the proposal due date to 28 October, 2026, while the government finalizes documents. September 23, 2026 The government is sitll working through RFI followup responses and the subsequent amendment. This amendment adjusts the proposal due date to 13 October, 2026, while the government finalizes documents. September 16, 2026 Complete RFI responses posted. Followup questions related to these RFIs can be submitted by September 21 at noon CST. The government is not accepting new questions. Any question submitted must be tied to an answer provided in the attachment. The proposal due date will remain unchanged but the government will continue to monitor the need to extend. September 10, 2026 It was brought to the government's attention that previous solicitation amendments cannot be accessed. They now have been activated and are accessible. September 3, 2026 Amendment posted with updated Proposal due date, please see attachment. The government is still working to answer all RFIs. August 25, 2026: See attachment for a complete list of RFIs received to date. Some have already been answered, and the government is working to answer the rest. The government will continue to evaluate the need to extend the proposal deadline based on the time required to answer all questions and supply those answers to industry. August 19 2026: Please see amendment 0002 attached and an updated Section L. August 11 2026: 1. Please see amendment 0001 attached and an updated Section L dated 5 August 2026. 2. The government is accepting RFIs until 21 August at 3PM EDT. If you have already sent your RFIs to the POCs you do not have to resubmit them. 4 August 2026: Please see the attached RFP (FA8137-26-R-0040) and all attachments. --------------------------------------------------------------------------------------------------------------- THIS POSTING WILL SATISFY THE REQUIREMENT OF RFO 5.101, Presolicitation Multiple Award Construction Contract (MACC) for General Construction Services will accomplish a broad range of sustainment, maintenance, repair, alteration/renovation, and minor construction projects affecting real property facilities at Tinker Air Force Base, Oklahoma. The work performed will be complex in nature, require multiple construction trades, and may require engineering design performed by credentialed professionals. Project execution methods will fall into one of the following classifications. The execution method will be defined in the project documents for each Task Order (TO) under this Indefinite Delivery Indefinite Quanity (IDIQ) contract. Design Build will include the Contractor providing both the design and construction services for a project; during the Design-Build process, final design solutions are provided by the Contractor, not the Government. The Government will provide a Statement of Work (SOW), drawings, and other preliminary documents to establish requirements from the work to be completed. These documents will be equivalent to a schematic 15% or greater design. When awarded the TO for the project, the Contractor will complete the design to the 100% level to include drawings, specifications, design analysis/narrative, and other documentation as required by the Government. Construction with Limited Design method will include the Government providing the design and the Contractor will further develop portions as required and will provide construction services for the project. This method will be used for non-complex or repetitive work types of projects where design cost and effort is not warranted. The Government will provide the SOW, drawings, and other documents as necessary to establish requirements to complete the project. These documents will be equivalent to a design submittal 35% to 65%. When awarded the TO the Contractor will complete any additional design efforts required by the project and produce a set of working documents for use during construction. Construction only method will include the Government providing 100% design package, including the SOW, drawings, specification, and any other documents as necessary to establish requirements for the work to be accomplished. When awarded the TO the Contractor shall commence with construction in accordance with the design and contract requirements. The Contractor is required to furnish all materials, labor, plant, tools, transportation, equipment, testing services, quality control, and incidentals necessary to provide a complete useable end product as specified in the TO/project documents. The North American Industry Classification System (NAICS) Code is 236210, Industrial Building Construction with a small business size standard of $45 million. The MACC will be executed for one base period of five (5) years with one option period of five (5) years. The Government will negotiate equitable adjustments resulting from change orders in the shortest practicable time. Approximately 120 days are required to definitize equitable adjustments associated with change orders for construction. The definitization of an equitable adjustment begins when the contracting officer receives an adequate change order definitization proposal and ends when the contracting officer executes a contractual action to definitize the change order. IMPORTANT NOTICE: Offerors are required to complete their registration in the System for Award Management (SAM) database via the website https://www.sam.gov. Offerors are strongly encouraged to review their informaiton in SAM to validate that it is current and up to date. Failure to do so could result in the offeror being ineligible for award of Department of War contracts IAW RFO 4.203-1 registered in SAM database. DISCLAIMER: The information being requested does not constitute a commitment on the part of the Government to award a contract, nor to pay for any costs incurred as a result of replying to this notice. This notice should not be construed as a commitment by the Government for any purpose. | 60% | Solicitation | 11/30/2026 |
Only the MAC BOA Holder GCs that attended Site Visit on 26 May 2026 will be able to continue forward toward the award. Updated 12 June 2026 Government response to RFIs are attached Proposals due 25 June 2026 Only the MAC BOA Holder GCs that attended Site Visit on 26 May 2026 will be able to continue forward toward the award. Only the MAC BOA Holder GCs that attended Site Visit on 26 May 2026 will be able to continue forward toward the award. Updated 27 May 2026 Solicitation is attached. RFIs due 02 June 2026 Proposals due 25 June 2026 Only the MAC BOA Holder GCs that attended Site Visit on 26 May 2026 will be able to continue forward toward the award. Only the MAC BOA Holder GCs that attended Site Visit on 26 May 2026 will be able to continue forward toward the award. Updated 26 May 2026 Initial Site Visit Sign In Sheet has been attached. RFIs due 02 June 2026 Proposals due 25 June 2026 Only the MAC BOA Holder GCs that attended Site Visit on 26 May 2026 will be able to continue forward toward the award. This posting is for Tinker AFB - MAC BOA Holders ONLY. Project Solicitation Number: FA813726R0034 Project Title: WWYK190021 - Repair Overhead Doors, Fire Station, B989 Project Location: Tinker AFB - B989 Repair by replacement of overhead doors at project location within B989 at Tinker Air Force Base (AFB) Oklahoma 73145 The estimated project value is below $25M and is restricted to SB MAC BOA holders only. Project specific documents are attached to this posting. If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission. In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to. Do not include any Sub-Contractor email addresses. The Solicitation – Request for Proposal (RFP) is attached. This posting is for Tinker AFB - MAC BOA Holders ONLY. After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit. Your RSVP email must be received within 3 calendar days from the posting of this project. In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access. If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access. ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor. After receipt of your RSVP and EAL an Initial Site Visit is set for Tuesday, May 26th at 0900 CST at Building 989. You must attend the Initial Site Visit for the project to be considered eligible to propose. This posting is for Tinker AFB - MAC BOA Holders ONLY. | 59% | Solicitation | 06/25/2026 |
Additional Details
Solicitation Number
FA813726R0049
Archive Date
Dec 31, 2026
Office Address
TINKER AFB, OK, 73145-9125