South Bay International Wastewater Treatment Plant (SBIWTP) Rehabilitation and Expansion Progressive Design-Build (PDB)

Awarded on September 29, 2026. Full description on SAM.gov.

Awarded tounder 191BWC24C0006P00001 (source: SAM.gov award notice)• $552.4M

Overview

Posted
October 13, 2026
Notice type
Award Notice
NAICS
237110: Water and Sewer Line and Related Structures Construction
Agency
International Boundary and Water Commission

Notice details

Office
INTERNAT BOUNDARY AND WATER COMM
Place of performance
San Ysidro, California, 92173
PSC
Y1ND: CONSTRUCTION OF SEWAGE AND WASTE FACILITIES
Last updated
Oct 28, 2026
First published
Last updated on SAM.gov
Award date
Sep 29, 2026
Award amount (SAM.gov award notice)
$552.4M

Identifiers

Solicitation number
191BWC24C0008P00012
Notice ID
fb3dc2bfe38f4cadad0b01ec41e87e68
Award number (PIID)
191BWC24C0006P00001

Description

The purpose of this modification is to incorporate additional construction packages and Phase 1 expansion work into the progressive design-build contract. The modification adds the following construction packages:

Early Work Package (EWP) 1C – Replacement In Kind

Final Construction Price: $13,147,453

Scope includes:

  • Removal and replacement of existing roofs.
  • Replacement of process equipment and piping.
  • Replacement of electrical equipment.
  • Replacement of odor control media.
  • Installation of new window sealants.
  • Replacement of coiling doors.
  • Replacement of emergency showers and eyewashes.
  • Painting and coating of existing facilities. 

Early Work Package (EWP) 3B – Early Procurement

Final Construction Price: $25,693,528

Scope includes procurement of critical long-lead equipment, including:

  • Standby generators and associated switchgear.
  • Medium-voltage switchgear.
  • Positive displacement blowers.
  • Submersible solids-handling pumps.
  • Dewatering centrifuges.
  • Stainless steel slide gates.
  • Stop logs. 

Early Work Package (EWP) 4 – Major Concrete Structures

Final Construction Price: $37,468,188

Scope includes:

  • Construction of major concrete structures for new Headworks facilities.
  • Primary Sedimentation Tanks 6 and 7.
  • Storage Warehouse.
  • New influent and drainage infrastructure.
  • Associated piping, carpentry, architectural, mechanical, electrical, and support features. 

Phase 1 Base Construction Expansion

Final Construction Price: $369,613,306

Scope includes:

  • New Headworks facility with integrated pump station.
  • Screening and grit removal systems.
  • Primary sedimentation expansion.
  • Centralized odor control facilities.
  • Waste activated sludge thickening and storage facilities.
  • Dewatering upgrades.
  • Lime storage/feed and truck loadout facilities.
  • Storage warehouse.
  • Chlorination storage facility.
  • Administrative building expansion.
  • Multiple electrical buildings.
  • New electrical service, generators, utility distribution systems, process piping, and site work.
  • Rehabilitation of existing activated sludge tanks and lime silos.
  • Engineering services during construction and procurement of the effluent meter and bypass piping. 

Construction Allowances

The contract also increases CLIN 008 Construction Allowances by $9,804,886, increasing the allowance amount from $1,783,374 to $11,588,260 to address uncertain construction elements and field conditions associated with EWP-1C and Phase 1 construction activities. [191BWC24C0008 P00012 | PDF]

Period of Performance

The base construction period of performance has been revised to 1,643 calendar days (54 months) from issuance of the Base Construction Notice to Proceed (NTP). Construction closeout requirements remain unchanged and must be completed within 180 calendar days following construction completion. 

Award Value

  • Previous Contract Value: $106,449,546
  • Modification Increase: $445,922,475
  • Revised Total Contract Value: $552,372,021 

Full description on SAM.gov

Award Overview

Award Number

191BWC24C0006P00001

Award Amount (SAM.gov award notice)

$552.4M

Award Date

Sep 29, 2026

Awardee

Awardee Address

Tempe, AZ 85284, UNITED STATES

Original Solicitation

Notice ID: fb3dc2bfe38f4cadad0b01ec41e87e68

Posted Date: Oct 13, 2026

Original Response Deadline: Not specified

Contract Details

Contract data not yet available

Contract details typically appear within 2-4 weeks after award; DoD awards are published about 90 days after signature.

Contacts

Contracting Officer

Primary Contact

Documents

No documents available.

Lifecycle

  1. 1
    Version 1Award NoticeCurrent

    South Bay International Wastewater Treatment Plant (SBIWTP) Rehabilitation and Expansion Progressive Design-Build (PDB)

    Notice fb3dc2bfe38f4cadad0b01ec41e87e68 on SAM.gov