REQUEST FOR INFORMATION (RFI) DDG 1000 Class Modernization: USS Michael Monsoor (DDG 1001) Conventional Prompt Strike (CPS) Depot Modernization Period (DMP); Large Missile Vertical Launch System (LMVLS) Heavy Lift and Industrial Installation

Active, responses due . Full description on SAM.gov.

Overview

Response deadline
12:00 PM EST
Posted
November 17, 2026
Notice type
Special Notice
Set-aside
No Set aside used
NAICS
336611: Ship Building and Repairing
Agency
Department of WarDepartment of the Navy

Notice details

Office
NAVSEA.NAVSEA HQ.NAVSEA HQ
Last updated
Nov 17, 2026
First published
Last updated on SAM.gov

Identifiers

Solicitation number
N00024-27-R-4444
Notice ID
c96fb8d16b2a4fa59ada92cbde9a02c8

Description

1.0 PURPOSE & OBJECTIVE

PAE Maritime, on behalf of the dPAE Combatants/ DDG 1000 Class Program Office (PMS 500), is conducting market research to assess industry capabilities, engineering rigor, and shipyard infrastructure necessary to accomplish the industrial integration and installation of the Large Missile Vertical Launch System (LMVLS) aboard the USS Michael Monsoor (DDG 1001).

The primary objective of this RFI is to evaluate prospective offerors' specific technical expertise, dry dock/pier-side heavy-lift capabilities, dimensional control methodologies, and integrated production scheduling to execute the installation of a pre-manufactured ~600-ton LMVLS module and associated Conventional Prompt Strike (CPS) warfare alterations.

The questions contained in Section 3.0 are specifically structured to allow industry respondents to demonstrate their understanding of the unique structural, spatial, lifting, and combat systems complexities associated with this depot modernization period.

2.0 TECHNICAL BASELINE & REQUIREMENT SUMMARY

Key technical parameters within the DDG 1001 CPS DMP include:

2.1 Ship Particulars

  • Vessel: USS Michael Monsoor (DDG 1001)
  • Length Overall (LOA) / LBP: 186 m (610 ft) / 182.9 m (600 ft)
  • Beam (Maximum): 24.6 m (80.7 ft)
  • Draft (Navigational / DWL): 8.4 m (27.6 ft) / 7.0 m (23.0 ft)
  • Hull Form & Superstructure: Wave-piercing tumblehome hull; steel hull structure with composite deckhouse; integrated power system (IPS).

2.2 LMVLS Pre-Manufactured Assembly Profile (GFM)

  1. The Government plans to deliver the LMVLS as Government-Furnished Material (GFM) as a fully out-fitted, pre-manufactured modular block. The industrial effort will require rigging, lifting, transferring, lowering, and setting the ~600-ton LMVLS module into the hull pocket within tight spatial and angular tolerances. Additional specifications include:
  • Envelope Dimensions: Approximately 44’ 7” Length × 20’ 8” Width × 41’ 1” Height.
  • Total Lift Weight: Approximately 600 Long Tons (LT).
  • Component Integration: Four (4) launch tubes housing Advanced Payload Modules (APMs) and All-Up Round Canisters (AUR-C), integral shock-isolation foundation assemblies, multi-level bulkheads (down through L5), decks, pre-installed outfitting, and weather deck / 01-level hatch structures.
  • Installation Location: Forward Stack 1400 (reclaimed forward space following MT 61 AGS complete removal).

3.0 TECHNICAL CAPABILITY QUESTIONNAIRE

Interested sources are requested to provide detailed technical narrative responses, supported by engineering calculations, facility specifications, past performance references, and risk mitigation methodologies, addressing each section below.

Section A: Heavy Lift, Rigging & Facility Engineering Capabilities

  1. Lifting Infrastructure & Capacities:
  • Detail your primary crane assets (gantry, floating, portal, or crawler) capable of hoisting and swinging a 600-ton (approx. 1,344,000 lbs) rigid modular assembly.
  • Provide the specific crane load charts demonstrating rated capacity at the required operating radius and minimum hook height necessary to clear DDG 1001’s deck edge, bulwarks, and adjacent deckhouse structures (taking into account the 41’ 1” module height plus lifting beam/spreader bar rigging height).
  • If utilizing a floating crane for the LMVLS, confirm that the selected crane has the clearance to transit under any bridges necessary to arrive at your shipyard.
  • Specify whether the 600-ton lift will be executed in dry dock or pier-side, and detail the structural load-bearing capacity (pounds per square foot / ground bearing pressure) of the quay wall, pier apron, or dry dock wing walls supporting the crane footprint during maximum outrigger or track loadings.
  1. Rigging, Stability & Tandem Operations:
  • Describe your concept for the lift rigging assembly (spreader frames, equalizing grommets, dynamic load monitoring systems) to eliminate torsional deflection, racking, and localized stress concentrations on the pre-assembled LMVLS module during the pick.
  • If a tandem or multi-crane lift is planned, provide your operational methodology for synchronous motion, hook travel rate synchronization, and emergency load re-distribution mitigation.
  • Address environmental limits: What are your maximum allowable wind speed, wave/surge motion (if using floating derrick/crane barges), and tidal envelopes for executing this precision lift?
  1. Ship Mooring, Ballast & Hull Stability During Module Placement:
  • DDG 1001 possesses a unique wave-piercing tumblehome form with strict naval architectural stability limitations. Describe your approach to calculate, model, and monitor ship list, trim, draft changes, and metacentric height during the removal of the forward AGS weight and subsequent setting of the 600-ton LMVLS module (whether afloat at a pier or during block contact in dry dock).

Section B: Precision Alignment, Metrology & Structural Integration

  1. Dimensional Control & Metrology Framework:
  • The LMVLS module must interface with existing ship structure, pre-established shock-attenuation foundations, and tight topside radar cross-section (RCS) deck tolerances. Describe your advanced metrology procedures (e.g., 3D laser scanning, photogrammetry, laser tracking) from initial ship condition surveying through pre-lift verification and final post-weld alignment.

Section C: Industrial Coordination, Schedule Phasing & AIT Co-Existence

  1. Integration of Alteration Installation Teams (AIT) & System OEMs:
  • Installation of the CPS LMVLS requires extensive concurrent work by Government labs and weapon system prime contractors (e.g., Raytheon, Lockheed Martin, NAVWAR).
  • Detail your approach for managing space conflicts, shared lifting/crane services, security access controls for classified weapon compartments, and jurisdictional hand-offs between shipyard trades and specialized weapon installers.
  1. Subcontracting, Teaming & Industrial Workshare:
  • If teaming or significant subcontracting (>20%) is required to satisfy heavy crane, precision metrology, or specialized welding capabilities, outline your proposed organizational hierarchy, prime contractor oversight model, and quality assurance audit procedures.
  • If responding as a Small Business prime under FAR 52.219-14, explicitly demonstrate how your organization will perform at least 50% of the cost of manufacturing and direct industrial labor.

Section D: Risk Assessment, Lessons Learned & Resource Management

  1. Critical Technical & Industrial Risks:
  • Identify what your organization views as the top three (3) critical technical failure modes or schedule risks during the LMVLS module installation (e.g., crane unavailability, structural distortion exceeding cell launch tolerances, GFM delivery mismatches, dry dock schedule creep).
  • For each identified risk, provide specific, mitigation strategies and fallback procedures.

4.0 RESPONSE INSTRUCTIONS & SUBMISSION GUIDELINES

4.1 Content & Page Limitations

  • Cover Sheet: CAGE Code, SAM UEI, MSRA/ABR status, business size under NAICS 336611 (Ship Building and Repairing), primary technical and contracts POCs.
  • Volume I (Technical Capability Narrative): Not to exceed five (5) pages, addressing all questions in Section 3.0.
  • Volume II (Facilities, Equipment & Crane Load Charts): Not to exceed five (5) pages, containing facility schematics, dry dock certified dimensions, dock loading curves, and relevant crane radius/load capacity charts.

4.2 Marking of Proprietary Information

Respondents must clearly mark and isolate any proprietary data, trade secrets, or commercial pricing/cost methodologies. The Government will handle properly marked data in accordance with applicable statutory regulations and protect it as Business Sensitive.

4.3 Inquiries & Submission Points of Contact

Submissions shall be delivered electronically via DoD SAFE or secure email no later than the time and date specified in the official SAM.gov synopsis:

  • Procuring Contracting Officer: Brian Romano, PAE M 025 (brian.c.romano.civ@us.navy.mil)
  • Contract Specialist: James Thomas, PAE M 025 (james.c.thomas118.civ@us.navy.mil)
  • Reference: Sources Sought N00024-26-R-4443 (DDG 1001 CPS DMP LMVLS RFI)

Full description on SAM.gov

Award Overview

No prior contract identified

No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.

Contacts

Contracting Officer

Secondary Contact

Documents

Files (1)

  • Enclosure 1.pdf

    212 KBAdded in Sources Sought version 3Posted
    Download

Lifecycle

  1. 3
    Version 3Sources SoughtArchived

    Sources Sought Notice for USS MICHAEL MONSOOR (DDG 1001) CNO Availability

    Notice 542c96cfc71c407db74f4d8115a33797 on SAM.gov

  2. 4
    Version 4Special NoticeCurrent

    Type changed from Sources Sought to Special Notice

    REQUEST FOR INFORMATION (RFI) DDG 1000 Class Modernization: USS Michael Monsoor (DDG 1001) Conventional Prompt Strike (CPS) Depot Modernization Period (DMP); Large Missile Vertical Launch System (LMVLS) Heavy Lift and Industrial Installation

    Notice c96fb8d16b2a4fa59ada92cbde9a02c8 on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline

Additional Details

Solicitation Number

N00024-27-R-4444

Archive Date

Dec 30, 2026

Office Address

WASHINGTON NAVY YARD, DC, 20376-5000