Overview

Response deadline
2:00 PM GMT-5
Posted
October 9, 2026
Notice type
Presolicitation
Set-aside
No Set aside used
NAICS
238910: Site Preparation Contractors
Agency
Department of State

Notice details

Office
US EMBASSY KINGSTON
Place of performance
Saint Andrew, Saint Andrew
PSC
J038: MAINT/REPAIR/REBUILD OF EQUIPMENT- CONSTRUCTION/MINING/EXCAVATING/HIGHWAY MAINTENANCE EQUIPMENT
Last updated
Oct 28, 2026
First published
Last updated on SAM.gov
Additional reporting
Recovery Act

Identifiers

Solicitation number
PR16330526
Notice ID
b556277dcd5444b78f1c77c33060368d

Description

Description

The United Stated Embassy in Kingston, Jamaica, plans to issue a Request for Quotations (RFQ) for trenching, conduit and ground-well installation in various locations on the Embassy compound.

Scope of Work: The contractor will provide all labor, equipment, supervision, material specific to the back filling and compaction and management needed to complete the job

Infrastructure Support System - Handhole / Underground Conduit System

Trenching

  • Nine locations have been identified requiring trench work.
  • Thirteen locations have been identified requiring trench work.
  • Before excavation, the Contractor shall locate and verify all existing utilities in the proposed trench alignment.
  • If excavation interferes with existing drains, piping, or structures, the Contractor shall immediately notify, in writing, the COR and provide temporary protection for these systems before proceeding.

Trenching from Handholes

  • The Contractor shall make wall penetrations into existing manholes/handholes as required for the number and size of conduits entering and exiting each structure, in accordance with the drawings.

Conduit

  • Existing conduit shall remain in place unless the drawings specifically direct removal or modification.
  • Under grass, soil, the Contractor shall install Schedule 80 PVC conduit with a minimum cover of 24 inches (610 mm) from finished grade to top of conduit, or as indicated on the drawings, whichever is greater.
  • All underground 90 degree bends with a 12inch (305 mm) radius shall use prefabricated sweeping bends.
  • Above grade, all underground PVC conduit shall transition to rigid galvanized steel (RGS) using PVC to RGS couplers.
  • The Contractor shall install pull lines in all new conduit runs.

Soil and Backfill Materials

Soil Materials

The Contractor shall provide all labor and materials for soil and backfill, where required.

  • Select Backfill: ASTM D 2487 soil classification groups SW, SP, and SM, or combinations thereof; free of rock or gravel larger than 3 inches (75 mm), debris, waste, frozen materials, vegetation, and other deleterious matter.
  • Asphalt/Concrete Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 95% passing a 11/2inch (40 mm) sieve and not more than 8% passing a 1/4inch (6.4 mm) sieve.
  • Base Gravel: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; 100% passing a 1inch (25 mm) sieve and not more than 8% passing a 1/4inch (6.4 mm) sieve.
  • Sand Cushion: ASTM C 33 fine aggregate, natural or manufactured sand.

Placement and Compaction

  • Place backfill and fill in layers not exceeding:
    • 8 inches (203 mm) loose thickness for heavy compaction equipment;
    • 4 inches (102 mm) loose thickness when compacted by hand-operated tampers.
  • Place backfill and fill evenly to the required elevations, uniformly along their full length.
  • Compact soil materials to not less than the following percentages of maximum dry unit weight per ASTM D 1557:
    • Under lawns or unpaved areas: scarify and re-compact top 6 inches (152 mm) below subgrade and compact each layer to 85%.
    • Utility trenches: compact each layer of initial and final backfill to 85%.

Anticipated Period of Performance: a base period of twenty-one (21) days after contract award

Eligibility and Registration

Offerors must hold an active registration in the System for Award Management (SAM.gov) when they submit a proposal and at award.

Local Insurance and Defense Based Act (DBA) Insurance.

Solicitation Availability

The Embassy will post the solicitation and all amendments only on SAM.gov at https://sam.gov. Interested parties should monitor SAM.gov for the release and any amendments. The Embassy will not issue paper copies.

Disclaimer

This notice is for informational purposes only and is not a request for proposals. It does not commit the Government to issue a solicitation or award a contract. The Government will not pay for any information or materials submitted in response to this notice.

Interested Parties are required to send their interest to Kingstonquotes@state.gov on or before October 26, 2026 at 2pm local time.

Full description on SAM.gov

Award Overview

Contacts

Contracting Officer

Primary Contact

U.S. Embassy Kingston Procurement Office

Secondary Contact

Documents

Files (2)

  • PR16330526_SAM.gov Pre Solicitation Notice_Trench Digging.pdf

    244 KBAdded in Presolicitation version 1Posted
    Download
  • PR16330526_Pre Solicitiation Notice_Trench Digging.pdf

    191 KBAdded in Presolicitation version 1Posted
    Download

Lifecycle

  1. 1
    Version 1PresolicitationCurrent

    Pre-Solicitation Notice - Trenching, Conduit and Ground-well Installation

    Notice b556277dcd5444b78f1c77c33060368d on SAM.gov

Similar Opportunities

Additional Details

Solicitation Number

PR16330526

Archive Date

Nov 10, 2026

Place of Performance Country

JAMAICA

Office Address

WASHINGTON, DC, 20520