Notice ID: bb5056405aad2266162d0811348efb77Presolicitation
Y--Charleroi Locks, River Chamber Completion, Monoliths M-22 to M-27
Archived on August 6, 2015. Original response deadline: . Full description on SAM.gov.
Overview
- Response deadline
- 7:00 AM UTC+02:00
- Posted
- April 11, 2014
- Notice type
- Presolicitation
- NAICS
- 237990: Other Heavy and Civil Engineering Construction
- Agency
- Department of WarDepartment of the Army
Notice details
- Office
- W072 ENDIST PITTSBURGH
- Place of performance
- USACE District, Pittsburgh 1000 Liberty Avenue, W.S. Moorhead Federal Building, 22nd Floor Pittsburgh PA 15222-4186 US
- PSC
- Y: CONSTRUCT OF STRUCTURES/FACILITIES
- Last updated
- Dec 5, 2025
Identifiers
- Solicitation number
- W911WN14B0001
- Notice ID
- bb5056405aad2266162d0811348efb77
Description
The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the construction of the River Chamber Completion, Monoliths M-22 to M-227 at Charleroi Locks and Dam, Monongahela River, PA. The major features of the requirement are identified below: Construction of the River Chamber Completion, Monoliths M-22 to M-27, consists of building steel cofferboxes in order to construct the new reinforced concrete Middle Wall monoliths numbered M-22 to M-27, fabrication and installation of precast concrete culverts within the Middle Wall cofferboxes, relocating the electrical and dam control utilities from the lock side to the dam abutment side including construction of a new elevated platform supporting a new temporary electrical generator, areas of partial and complete removal of the existing river wall and fixed crest weir concrete sections using in-the-wet methods, modifying existing sheet pile structures, removal of a sheet pile structure, stabilization of existing lock walls, instrumentation installation, and instrumentation monitoring. The work is to be performed using a combination of in-the-wet and in-the-dry construction methods. The lock wall monoliths will be built using a combination of tremie concrete and cast-in-place concrete within a cofferbox. The precast concrete culverts are three sided culverts and are to be fabricated off site at a commercial precast fabrication facility. Onsite fabrication of the precast concrete culvert will not be permitted. The M-22 to M-27 New Middle Wall section is approximately 260 feet by 35 feet in plan and is located riverward of the downstream end of the existing Middle Wall for the land lock chamber. Construction of the lock wall involves underwater excavation of both soil and rock; heavy lifting and placement of the precast culverts from a floating plant; sheet piles, king piles and associated steel waler and strut installation for cofferbox construction from a floating plant; drilled shaft foundations; as well as operation and maintenance of the Government owned Concrete Batch Plant, concrete delivery system, and ancillary items. Maintenance of the batch plant will include repair and/or replacement of various items necessary for continued operation of the plant. Disposal of suitable excavated materials and concrete rubble without embedded ferrous material will be required. The offloading area at Victory Hollow (VH), approximately 7 miles downstream of Charleroi Locks and Dam, will be utilized to stockpile and dispose of the suitable materials from the construction activities. Ferrous and other construction waste material will be disposed at a commercially permitted facility licensed to accept the waste or recycled if applicable. Construction work will occur in close proximity to waterway traffic. The existing landside lock chamber is currently operated 24 hours a day, 7 days a week. Maintaining unimpeded access (to the extent possible under this contract) of this facility to waterway traffic and maintaining stability of the existing middle wall are underlying goals of this contract. Environmental protection will include requirements to remain in compliance with the existing NPDES permitting at both VH and the Concrete Batch Plant. The magnitude of the project is between $25,000,000 and $100,000,000. This procurement will be advertised on an Unrestricted basis. The Invitation for Bid (IFB) will be issued approximately May 27, 2014 online only through the Federal Business Opportunities website; therefore, requests for hardcopies of the specifications and drawings will not be honored.
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Contracting Officer
Primary Contact
Carole Householder, 412-395-7274 USACE District, Pittsburgh
Documents
No documents available.
Lifecycle
Solicitation:
W911WN14B0001- Pre-Solicitation
Formal solicitation typically follows within 30–60 days. (estimate)
- 2×Pre-SolicitationCurrentApr 11, 2014
Y--Charleroi Locks, River Chamber Completion, Monoliths M-22 to M-27
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
Dashields Locks and Dam Install 4 Corner Hydraulics Dashields Locks and Dam, Coraopolis, PennsylvaniaThe Dashields hydraulic system upgrade consists of demolition and removal of the existing hydraulic system and its related components, and installation of a new hydraulic system with supporting controls and buildings.Primary hydraulic system components to be demolished and removed are motors, pumps, reservoir, filters, filter housings, piping and pipe hangers, hydraulic fluid, valves, and manifolds. Any hydraulic piping that is embedded in concrete must be drained, cut flush with the concrete surface, capped or plugged, and abandoned in place. Nine (9) new hydraulic cylinders must be furnished by the contractor and five (5) will be furnished by the government. Electrical demolition work must include but not be limited to removal of specified buckets, cabinet doors, junction boxes, levers, buttons, indicators, limit switches, wiring, and hardware. Some concrete demolition work must be required for placement of new buildings and routing of new electrical cable and mechanical pipe.Three (3) new hydraulic power units (HPUs) must be furnished and installed on the land and middle lock walls inside two new 2-story HPU buildings at locations specified on the contract drawings. The fourth HPU will be furnished and installed on an elevated platform in the river wall at the location specified in the contract drawings. The HPU buildings and elevated platform must be designed and constructed by the contractor in accordance with the performance specification and the concept drawings included in the contract drawings. The HPUs must send hydraulic power to the existing hydraulic cylinders by means of new stainless-steel piping and new manifold mounted hydraulic components.The new hydraulic equipment must be operated by new electronic controls that will be installed inside new panels and new control consoles. The new control panels must be installed on each HPU with an additional control panel inside of the middle wall operations building. The new control consoles must be installed inside three existing and one new 1-story control shelter at locations specified in the contract drawings. The control shelter must be designed and constructed by the contractor in accordance with the performance specification and the concept drawings included in the contractdrawings.New buckets and supporting equipment must be installed inside existing motor control centers (MCCs). New hardware and power and control cabling must be installed as specified and as required for operation of the new electrical/mechanical equipment. Some concrete installation work must be required for placement of new buildings and routing of new electrical cable and mechanical pipe. A geotechnical and civil site analysis must be completed to confirm the structural integrity of all foundations for all new project components and to confirm proper drainage. Minimal new steel grating must be required for placement over top new concrete utility trenches. All new hydraulic and controls equipment must be tested and commissioned prior to project handoff. This project is to be completed at a locks and dam site along the Ohio River and thus requires the use of a floating work plant and work boat(s) for construction. Also, all as-built drawings must be stamped by a registered PE.The work shall be completed within 730 after written Notice to Proceed.The acquisition will be procured as 100% Set-Aside for Small Business. The resulting award will be for one (1) Firm-Fixed-Price (FFP) Contract. All responsible Offerors are encouraged to participate. The Request for Proposal (RFP) will be issued on or about 18 June 2026, online through Procurement Integrated Enterprise Environment (PIEE) which posts the opportunity to SAM.gov; therefore, requests for hardcopies of the solicitation will not be honored.The North American Industrial Classification System (NAICS) Code for this acquisition is 237990 - 0ther Heavy and Civil Engineering Construction.The Small Business Size Standard for this NAICS Code is $45,000,000.00.In order to submit an Offer on this project, your company must-1) Be registered in System for Award Management (SAM) and maintain an active registration status. 2) Be registered in the Procurement Integrated Enterprise Environment (PIEE) for the Solicitation Module with the PROPOSAL MANAGER Manger role. System for Award Management (SAM) RegistrationRegistering in SAM.gov includes both entity validation and entity registration.To register in SAM:a. Navigate to SAM.govb. Select Sign-In (top right)c. Select Create an Account then Follow the Instructions. d. After Account is Set-up, Select Sign In.e. Under the Entity Management widget, Select Get Started button. f. Select Register Entity. As part of entity registration, a Unique Entity ID will be assigned.For Additional Information on SAMTo Register Your Entity (company), please visit https:/www.fsd.gov/gsafsd_sp?id=gsa_index . Here you will find the following, Get Started with Your Registration Check Registration Status ACTIVE, INACTIVE, PENDING Update Your Registration Become an Entity Administrator Validate Your Entity *Access User Guides *By selecting this option, you can obtain a Quick Start Guide for Contract Registrations.Also, here you will find in addition to the User Guides - FAQs, Videos, and Definitions.PLEASE NOTEIt is mandatory that all companies be registered in SAM in order to receive federal contracts.There is no charge to register or maintain your company (entity) registration.Login.gov manages usernames and passwords for SAM.gov. *Important* Registration InformationRegistration can take at least ten (10) business days to be active in SAM.gov.Registration must be in active status upon offer submission and remain active during award period.Registration must be renewed every 365 days to remain active.The Federal Service Desk (FSD) for SAM questions, may be contacted. Phone Number: 866-606-8220Hours of Operation: Monday-Friday 8 a.m. to 8 p.m. ETProcurement Integrated Enterprise Environment (PIEE) Solicitation Module RegistrationTo register for PIEE follow the below instructions. Register in PIEE:a. Navigate to https://piee.eb.mil/b. Select Register [top right]c. Select Vendord. Create a User ID and Password and follow the prompts [next]e. Create Security Questions [next]f. Complete your User Profile Information [next]g. Complete your Supervisor or Approving Official Information [next]h. Complete Rolesi. Step 1. Select SOL-Solicitationii. Step 2. Select Proposal Manageriii. Step 3. Click Add Rolesiv. Step 4. Fill in your Location Code (CAGE Code) [next]i. Provide a justification for your registration [next]j. Follow the remaining prompts to submit your registrationThe Procurement Integrated Enterprise Environment (PIEE) help desk may be reached by calling telephone number 866-618-5988 for assistance. 30 June 2026 - Amendment 0001 issued. 23 July 2026 - Amendment 0002 Issued 31 July 2026 - Amendment 0003 issued. 13 August 2026 - Amendment 0004 issued. | 72% | Solicitation | 08/20/2026 |
Dashields Locks and Dam Install 4 Corner Hydraulics Dashields Locks and Dam, Coraopolis, PennsylvaniaThe Dashields hydraulic system upgrade consists of demolition and removal of the existing hydraulic system and its related components, and installation of a new hydraulic system with supporting controls and buildings.Primary hydraulic system components to be demolished and removed are motors, pumps, reservoir, filters, filter housings, piping and pipe hangers, hydraulic fluid, valves, and manifolds. Any hydraulic piping that is embedded in concrete must be drained, cut flush with the concrete surface, capped or plugged, and abandoned in place. Nine (9) new hydraulic cylinders must be furnished by the contractor and five (5) will be furnished by the government. Electrical demolition work must include but not be limited to removal of specified buckets, cabinet doors, junction boxes, levers, buttons, indicators, limit switches, wiring, and hardware. Some concrete demolition work must be required for placement of new buildings and routing of new electrical cable and mechanical pipe.Three (3) new hydraulic power units (HPUs) must be furnished and installed on the land and middle lock walls inside two new 2-story HPU buildings at locations specified on the contract drawings. The fourth HPU will be furnished and installed on an elevated platform in the river wall at the location specified in the contract drawings. The HPU buildings and elevated platform must be designed and constructed by the contractor in accordance with the performance specification and the concept drawings included in the contract drawings. The HPUs must send hydraulic power to the existing hydraulic cylinders by means of new stainless-steel piping and new manifold mounted hydraulic components.The new hydraulic equipment must be operated by new electronic controls that will be installed inside new panels and new control consoles. The new control panels must be installed on each HPU with an additional control panel inside of the middle wall operations building. The new control consoles must be installed inside three existing and one new 1-story control shelter at locations specified in the contract drawings. The control shelter must be designed and constructed by the contractor in accordance with the performance specification and the concept drawings included in the contractdrawings.New buckets and supporting equipment must be installed inside existing motor control centers (MCCs). New hardware and power and control cabling must be installed as specified and as required for operation of the new electrical/mechanical equipment. Some concrete installation work must be required for placement of new buildings and routing of new electrical cable and mechanical pipe. A geotechnical and civil site analysis must be completed to confirm the structural integrity of all foundations for all new project components and to confirm proper drainage. Minimal new steel grating must be required for placement over top new concrete utility trenches. All new hydraulic and controls equipment must be tested and commissioned prior to project handoff. This project is to be completed at a locks and dam site along the Ohio River and thus requires the use of a floating work plant and work boat(s) for construction. Also, all as-built drawings must be stamped by a registered PE.The work shall be completed within 730 after written Notice to Proceed.The acquisition will be procured as 100% Set-Aside for Small Business. The resulting award will be for one (1) Firm-Fixed-Price (FFP) Contract. All responsible Offerors are encouraged to participate. The Request for Proposal (RFP) will be issued on or about 18 June 2026, online through Procurement Integrated Enterprise Environment (PIEE) which posts the opportunity to SAM.gov; therefore, requests for hardcopies of the solicitation will not be honored.The North American Industrial Classification System (NAICS) Code for this acquisition is 237990 - 0ther Heavy and Civil Engineering Construction.The Small Business Size Standard for this NAICS Code is $45,000,000.00.In order to submit an Offer on this project, your company must-1) Be registered in System for Award Management (SAM) and maintain an active registration status. 2) Be registered in the Procurement Integrated Enterprise Environment (PIEE) for the Solicitation Module with the PROPOSAL MANAGER Manger role. System for Award Management (SAM) RegistrationRegistering in SAM.gov includes both entity validation and entity registration.To register in SAM:a. Navigate to SAM.govb. Select Sign-In (top right)c. Select Create an Account then Follow the Instructions. d. After Account is Set-up, Select Sign In.e. Under the Entity Management widget, Select ?Get Started? button. f. Select Register Entity. As part of entity registration, a Unique Entity ID will be assigned.For Additional Information on SAMTo Register Your Entity (company), please visit https:/www.fsd.gov/gsafsd_sp?id=gsa_index . Here you will find the following, Get Started with Your Registration Check Registration Status ? ACTIVE, INACTIVE, PENDING Update Your Registration Become an Entity Administrator Validate Your Entity *Access User Guides *By selecting this option, you can obtain a Quick Start Guide for Contract Registrations.Also, here you will find in addition to the User Guides - FAQs, Videos, and Definitions.PLEASE NOTEIt is mandatory that all companies be registered in SAM in order to receive federal contracts.There is no charge to register or maintain your company (entity) registration.Login.gov manages usernames and passwords for SAM.gov. *Important* Registration InformationRegistration can take at least ten (10) business days to be active in SAM.gov.Registration must be in active status upon offer submission and remain active during award period.Registration must be renewed every 365 days to remain active.The Federal Service Desk (FSD) for SAM questions, may be contacted. Phone Number: 866-606-8220Hours of Operation: Monday-Friday 8 a.m. to 8 p.m. ETProcurement Integrated Enterprise Environment (PIEE) Solicitation Module RegistrationTo register for PIEE follow the below instructions. Register in PIEE:a. Navigate to https://piee.eb.mil/b. Select Register [top right]c. Select Vendord. Create a User ID and Password and follow the prompts [next]e. Create Security Questions [next]f. Complete your User Profile Information [next]g. Complete your Supervisor or Approving Official Information [next]h. Complete Rolesi. Step 1. Select SOL-Solicitationii. Step 2. Select Proposal Manageriii. Step 3. Click Add Rolesiv. Step 4. Fill in your Location Code (CAGE Code) [next]i. Provide a justification for your registration [next]j. Follow the remaining prompts to submit your registrationThe Procurement Integrated Enterprise Environment (PIEE) help desk may be reached by calling telephone number 866-618-5988 for assistance. | 72% | Pre-Solicitation | 06/18/2026 |
REQUEST FOR INFORMATION (RFI) / MARKET RESEARCH NOTICENotice: This is a Request for Information (RFI) for market research and informational purposes only. *Please see the attachments for instructions* | 72% | Market Research | 05/12/2026 |
PURPOSE: The U.S. Army Corps of Engineer (USACE), Philadelphia District (NAP), anticipates a requirement for the Maintenance Dredging of the Salem River in Salem River in Salem, NJ. DESCRIPTION: Contract work will consist of Maintenance Dredging of the Salem River, NJ federal navigation channel to the authorized depth of 16 ft MLLW plus 2 ft overdepth, non-contour dredging, with the exception of the turning basin which will be 16 ft MLLW plus 1 ft overdepth. Dredging operations will clear approximately 116,000 cubic yards of fine-sand and silty sediment from the channel and turning basin. Beneficial use placement of the dredged channel sediments will be accomplished at designated locations within the US Fish and Wildlife Service?s Supawna Meadows National Wildlife Refuge, Goose Pond area. Turning Basin dredging may have a different placement area at Tilbury Island. The contractor is required to have specialized experience since work requires the beneficial use placement of dredged sediments in sensitive marsh environments of a National Wildlife Refuge. Contractor must be able to demonstrate prior experience on dredging projects involving beneficial use placement techniques within environmentally sensitive coastal marshes and wetlands and knowledge of the dynamic conditions that exist for these placements. No dredging can occur between 1 March and 30 June due to environmental restrictions. DISCLOSURE OF MAGNITUDE OF THE PROPOSED CONSTRUCTION PROJECT: $1,000,000 and $5,000,000.NAICS CODE AND SBA SIZE STANDARD: 237990, Dredging and Surface Cleanup Activities; $37,000,000PERIOD OF PERFORMANCE: The estimated period of performance is 300 calendar days from Notice to Proceed (NTP)SYSTEM FOR AWARD MANAGEMENT (SAM): Bidders are required to be registered in the System for Award Management (SAM) database (https://sam.gov) and PIEE at the time a bid is submitted in order to comply with the annual representations and certifications requirements. Registration for PIEE is required as this is the only place bids shall be submitted. Bids must be submitted in PIEE Solicitation Module. Bids must be submitted in PIEE Solicitation Module. ADDITIONAL INFOMRATION: Specific information pertaining to this procurement will be available in the solicitation. The solicitation documents will be posted on the SAM.gov website, https://sam.gov and PIEE Solicitation Module. It is and will continue to be the responsibility of all potential Bidders to monitor the SAM.gov website for any amendments, updates, responses to questions and answers, etc. as the Government will not be maintaining a mailing list. | 72% | Solicitation | 03/02/2026 |
Description of Work: Contract work will consist of Maintenance Dredging of the Salem River, NJ federal navigation channel to the authorized depth of 16 ft MLLW plus 1 ft overdepth, non-contour dredging, to clear approximately 200,000 cubic yards of predominantly fine-grained sediment from the channel. Beneficial use placement of the dredged channel sediments will be accomplished at designated locations within the US Fish and Wildlife Service’s Supawna Meadows National Wildlife Refuge, Goose Pond area. Optional work will include a second mobilization and additional quantity of approximately 75,000 cy. The contractor is required to have specialized experience since work requires the beneficial use placement of dredged sediments in sensitive marsh environments of a National Wildlife Refuge. Contractor must be able to demonstrate prior experience on dredging projects involving beneficial use placement techniques within environmentally sensitive coastal marshes and wetlands and knowledge of the dynamic conditions that exist for these placements. Final environmental consultations will dictate when dredging and placement may occur but dredging and placements restrictions are anticipated between 1 March and 30 June. Solicitation Number will be issued at a later time and date. Sources Sought: This is a Sources Sought Notice and is for information purposes only. THIS IS NOT A REQUEST FOR PROPOSALS, QUOTATIONS, OR BIDS. A Market Survey is being conducted to determine if there are adequate HUBZone, 8(a), Service Disabled Veteran Owned, and Small Business contractors for the following proposed work. The Army Corps of Engineers, Philadelphia District, is interested in awarding one (1) Firm Fixed Price Contract for Maintenance Dredging of the Salem River, Salem County, New Jersey. Estimated cost range of the project is between $5,000,000.00 and $10,000,000.00. The period of performance is 270 calendar days for the Base work. An Award for the Contract is anticipated for 18 May 2023. Performance and Payment Bonds will be required for 100% of contract award. The NAICS Code for this project is 237990 and the small business size standard is $39.5 Million. To be considered small for purposes of Government procurement, a firm must perform at least 40 percent of the volume dredged with its own equipment or equipment owned by another small dredging concern. Responses to this sources sought announcement will be used by the Government to make appropriate acquisition decisions. All interested HUBZone, 8(a), Service Disabled Veteran Owned, Small Business contractors should submit a narrative demonstrating their experience in the specified work, as well as, their technical capabilities. Please include size/classification of your firm, bonding capacity (single project and aggregate), details of similar projects, completion dates, references and contract amount. Narratives shall be no longer than FIVE (5) pages. Responses should be sent to Zaquette Everett at zaquette.everett@usace.army.mil on or before 08 March 2023 11:59 p.m. Eastern. | 72% | Market Research | 03/08/2023 |
Additional Details
Solicitation Number
W911WN14B0001
Archive Date
Aug 6, 2015