Notice ID: 6b7dca6ce35118fd06ba40ecbfb10dddSolicitation
Y--River Chamber Completion at Charleroi Locks and Dam, Monongahela River, PA
Archived on December 3, 2015. Original response deadline: . Full description on SAM.gov.
Overview
- Response deadline
- 6:00 PM UTC+02:00
- Posted
- August 12, 2015
- Notice type
- Solicitation
- NAICS
- 237990: Other Heavy and Civil Engineering Construction
- Agency
- Department of WarDepartment of the Army
Notice details
- Office
- W072 ENDIST PITTSBURGH
- Place of performance
- USACE District, Pittsburgh 1000 Liberty Avenue, W.S. Moorhead Federal Building, 22nd Floor Pittsburgh PA 15222-4186 US
- PSC
- Y: CONSTRUCT OF STRUCTURES/FACILITIES
- Last updated
- Dec 5, 2025
Identifiers
- Solicitation number
- W911WN15B0005
- Notice ID
- 6b7dca6ce35118fd06ba40ecbfb10ddd
Description
The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the construction of the River Chamber Completion at Charleroi Locks and Dam, Monongahela River, PA. The major features of the requirement are identified below: 1. Middle Wall Monoliths M-1 to M-21. Construction consists of building steel cofferboxes in order to construct the new reinforced concrete Middle Wall that is approximately 835 feet by 35 feet in plan. Construction of the Middle Wall is to be performed using a combination of in-the-wet and in-the-dry construction methods. The lock wall monoliths will be built using a combination of tremie concrete and cast-in-place concrete within a cofferbox. Construction of the lock wall involves underwater excavation of both soil and rock; heavy lifting and placement of sheet piles, king piles and associated steel waler and strut installation for cofferbox construction from a floating plant; and installation of 72 inches diameter drilled shaft foundations that are constructed in-the-wet. 2. Middle Wall Control Tower and Shelter Buildings. Construction of one Control Tower and two Shelter Buildings is required. The Control Tower is approximately 30 feet by 20 feet in plan, and approximately 80 feet tall. The Shelter Buildings are each approximately 15 feet by 12 feet in plan, and approximately 25 feet tall. All building construction consists of cast-in-place reinforced concrete that will be constructed in-the-dry. 3. Secant Pile Wall. The Secant Pile Wall is approximately 600 feet long. The wall consists of a series of drilled rock sockets approximately 3 feet in diameter, that are backfilled with tremie concrete and heavy steel wide flange sections. Construction of the Secant Wall is to be performed in-the-wet. 4. Cofferdam Cells. Construction and removal of the temporary cofferdam system consists of two large diameter sheet pile cells, two small diameter sheet pile cells, and three intermediate sheet pile cells that are formed by arcs between the large diameter cells. The large diameter cells are each approximately 65 feet in diameter, the small diameter cells are each approximately 25 feet in diameter, and each of the intermediate cells are approximately 20 feet wide. 5. Heavy Demolition. Demolition items include the existing Original River Wall, existing downstream closure cell, existing wall closure, and the removal of various items within the existing Land Chamber in preparation for closure. Both in-the-wet and in-the-dry demolition is required. 6. Service Bridge (Footbridge). Installation of a new section of the service bridge (footbridge) is required. The new footbridge is approximately 260 feet long and consists of fabricated steel plate girders. 7. Various Cast-In-Place Reinforced Concrete. Items include bulkhead and miter sills, lock floor culverts, lock floor slab, River Wall top lifts and wall facing, and storage foundations. These items will be constructed in-the-dry. 8. Mechanical and Electrical. The contract requires substantial installation of various mechanical and electrical items within the lock walls and building systems. 9. Full lock functionality and testing of the mechanical and electrical systems. 10. Guide Wall Stabilization. Stabilizing of the existing Lower Guide Wall is required. Construction includes soil excavation and placement of large riprap stone berms. Both in-the-wet and in-the-dry construction is required. 11. Closure of the Existing Land Chamber. After completion of the new River Chamber, the existing Land Chamber will be closed. The closure requires construction of three large diameter sheet pile cells, one small diameter sheet pile cell, and five intermediate sheet pile cells that are formed by arcs between the large diameter cells. The large diameter cells are each approximately 50 feet in diameter, the small diameter cell is approximately 15 feet in diameter, and each of the intermediate cells are approximately 10 feet wide. 12. Heavy Marine Lifting. Several Government Furnished items are required to be transported and installed with use of a floating plant. Some items require heavy lifting including steel miter gates, Guard Wall precast concrete box beam and shaft enclosure, steel lock and valve bulkheads, steel culvert liners, and steel floating mooring bitts. Construction work will occur in close proximity to waterway traffic. The existing landside lock chamber is currently operated 24 hours a day, 7 days a week. Maintaining unimpeded access (to the extent possible under this contract) of this facility to waterway traffic and maintaining stability of the existing middle wall are underlying goals of this contract. Environmental protection will include requirements to remain in compliance with the NPDES permitting at both VH and the Concrete Batch Plant. Operation and maintenance of the Government owned Concrete Batch Plant, concrete delivery system, and ancillary items will be required. Maintenance of the batch plant will include repair and/or replacement of various items necessary for continued operation of the plant. Disposal of suitable excavated materials and concrete rubble without embedded ferrous material will be required. The offloading area at Victory Hollow (VH), approximately 7 miles downstream of Charleroi Locks and Dam, will be utilized to stockpile and dispose of the suitable materials from the construction activities. Ferrous and other construction waste material will be disposed at a commercially permitted facility licensed to accept the waste or recycled if applicable Overlapping contract work - A portion of the new middle wall M22-M27 is being constructed concurrently with the River Chamber completion contract. The overlap will be incorporated into the River Chamber Completion Contract as follows: Concrete - While the M22-M27 contract is ongoing, all concrete will be produced by the M22-M27 contractor. As such, the concrete for the subject contract will be provided as Government Furnished Material and the contractor will only be paid costs associated with transporting and placing the concrete. After the M22-M27 contract is complete, the contractor will take over operation and maintenance of the Government owned Concrete Batch Plant, concrete delivery system, and ancillary items. The contractor will also be responsible for maintenance of the batch plant to include repair and/or replacement of various items necessary for continued operation of the plant. It is anticipated the contract documents will be structured using a base contract and multiple awardable options for various features of the project. At the end of the contract, a single fully operational 84 ft by 720 ft lock chamber will occur. The magnitude of the project is between $250,000,000 and $500,000,000. This procurement will be advertised on an Unrestricted basis. The Invitation for Bid (IFB) will be issued approximately June 5, 2015 online only through the Federal Business Opportunities website; therefore, requests for hardcopies of the specifications and drawings will not be honored.
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Contracting Officer
Primary Contact
Documents
No documents available.
Lifecycle
Solicitation:
W911WN15B0005- Pre-Solicitation
- Solicitation
Award typically follows within 30–90 days after the response deadline. (estimate)
- 16×Pre-SolicitationApr 15, 2015
Y--River Chamber Completion at Charleroi Locks and Dam, Monongahela River, PA
- SolicitationCurrentAug 12, 2015
Y--River Chamber Completion at Charleroi Locks and Dam, Monongahela River, PA
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
Dashields Locks and Dam Install 4 Corner Hydraulics Dashields Locks and Dam, Coraopolis, PennsylvaniaThe Dashields hydraulic system upgrade consists of demolition and removal of the existing hydraulic system and its related components, and installation of a new hydraulic system with supporting controls and buildings.Primary hydraulic system components to be demolished and removed are motors, pumps, reservoir, filters, filter housings, piping and pipe hangers, hydraulic fluid, valves, and manifolds. Any hydraulic piping that is embedded in concrete must be drained, cut flush with the concrete surface, capped or plugged, and abandoned in place. Nine (9) new hydraulic cylinders must be furnished by the contractor and five (5) will be furnished by the government. Electrical demolition work must include but not be limited to removal of specified buckets, cabinet doors, junction boxes, levers, buttons, indicators, limit switches, wiring, and hardware. Some concrete demolition work must be required for placement of new buildings and routing of new electrical cable and mechanical pipe.Three (3) new hydraulic power units (HPUs) must be furnished and installed on the land and middle lock walls inside two new 2-story HPU buildings at locations specified on the contract drawings. The fourth HPU will be furnished and installed on an elevated platform in the river wall at the location specified in the contract drawings. The HPU buildings and elevated platform must be designed and constructed by the contractor in accordance with the performance specification and the concept drawings included in the contract drawings. The HPUs must send hydraulic power to the existing hydraulic cylinders by means of new stainless-steel piping and new manifold mounted hydraulic components.The new hydraulic equipment must be operated by new electronic controls that will be installed inside new panels and new control consoles. The new control panels must be installed on each HPU with an additional control panel inside of the middle wall operations building. The new control consoles must be installed inside three existing and one new 1-story control shelter at locations specified in the contract drawings. The control shelter must be designed and constructed by the contractor in accordance with the performance specification and the concept drawings included in the contractdrawings.New buckets and supporting equipment must be installed inside existing motor control centers (MCCs). New hardware and power and control cabling must be installed as specified and as required for operation of the new electrical/mechanical equipment. Some concrete installation work must be required for placement of new buildings and routing of new electrical cable and mechanical pipe. A geotechnical and civil site analysis must be completed to confirm the structural integrity of all foundations for all new project components and to confirm proper drainage. Minimal new steel grating must be required for placement over top new concrete utility trenches. All new hydraulic and controls equipment must be tested and commissioned prior to project handoff. This project is to be completed at a locks and dam site along the Ohio River and thus requires the use of a floating work plant and work boat(s) for construction. Also, all as-built drawings must be stamped by a registered PE.The work shall be completed within 730 after written Notice to Proceed.The acquisition will be procured as 100% Set-Aside for Small Business. The resulting award will be for one (1) Firm-Fixed-Price (FFP) Contract. All responsible Offerors are encouraged to participate. The Request for Proposal (RFP) will be issued on or about 18 June 2026, online through Procurement Integrated Enterprise Environment (PIEE) which posts the opportunity to SAM.gov; therefore, requests for hardcopies of the solicitation will not be honored.The North American Industrial Classification System (NAICS) Code for this acquisition is 237990 - 0ther Heavy and Civil Engineering Construction.The Small Business Size Standard for this NAICS Code is $45,000,000.00.In order to submit an Offer on this project, your company must-1) Be registered in System for Award Management (SAM) and maintain an active registration status. 2) Be registered in the Procurement Integrated Enterprise Environment (PIEE) for the Solicitation Module with the PROPOSAL MANAGER Manger role. System for Award Management (SAM) RegistrationRegistering in SAM.gov includes both entity validation and entity registration.To register in SAM:a. Navigate to SAM.govb. Select Sign-In (top right)c. Select Create an Account then Follow the Instructions. d. After Account is Set-up, Select Sign In.e. Under the Entity Management widget, Select Get Started button. f. Select Register Entity. As part of entity registration, a Unique Entity ID will be assigned.For Additional Information on SAMTo Register Your Entity (company), please visit https:/www.fsd.gov/gsafsd_sp?id=gsa_index . Here you will find the following, Get Started with Your Registration Check Registration Status ACTIVE, INACTIVE, PENDING Update Your Registration Become an Entity Administrator Validate Your Entity *Access User Guides *By selecting this option, you can obtain a Quick Start Guide for Contract Registrations.Also, here you will find in addition to the User Guides - FAQs, Videos, and Definitions.PLEASE NOTEIt is mandatory that all companies be registered in SAM in order to receive federal contracts.There is no charge to register or maintain your company (entity) registration.Login.gov manages usernames and passwords for SAM.gov. *Important* Registration InformationRegistration can take at least ten (10) business days to be active in SAM.gov.Registration must be in active status upon offer submission and remain active during award period.Registration must be renewed every 365 days to remain active.The Federal Service Desk (FSD) for SAM questions, may be contacted. Phone Number: 866-606-8220Hours of Operation: Monday-Friday 8 a.m. to 8 p.m. ETProcurement Integrated Enterprise Environment (PIEE) Solicitation Module RegistrationTo register for PIEE follow the below instructions. Register in PIEE:a. Navigate to https://piee.eb.mil/b. Select Register [top right]c. Select Vendord. Create a User ID and Password and follow the prompts [next]e. Create Security Questions [next]f. Complete your User Profile Information [next]g. Complete your Supervisor or Approving Official Information [next]h. Complete Rolesi. Step 1. Select SOL-Solicitationii. Step 2. Select Proposal Manageriii. Step 3. Click Add Rolesiv. Step 4. Fill in your Location Code (CAGE Code) [next]i. Provide a justification for your registration [next]j. Follow the remaining prompts to submit your registrationThe Procurement Integrated Enterprise Environment (PIEE) help desk may be reached by calling telephone number 866-618-5988 for assistance. 30 June 2026 - Amendment 0001 issued. 23 July 2026 - Amendment 0002 Issued 31 July 2026 - Amendment 0003 issued. 13 August 2026 - Amendment 0004 issued. | 82% | Solicitation | 08/20/2026 |
Dashields Locks and Dam Install 4 Corner Hydraulics Dashields Locks and Dam, Coraopolis, PennsylvaniaThe Dashields hydraulic system upgrade consists of demolition and removal of the existing hydraulic system and its related components, and installation of a new hydraulic system with supporting controls and buildings.Primary hydraulic system components to be demolished and removed are motors, pumps, reservoir, filters, filter housings, piping and pipe hangers, hydraulic fluid, valves, and manifolds. Any hydraulic piping that is embedded in concrete must be drained, cut flush with the concrete surface, capped or plugged, and abandoned in place. Nine (9) new hydraulic cylinders must be furnished by the contractor and five (5) will be furnished by the government. Electrical demolition work must include but not be limited to removal of specified buckets, cabinet doors, junction boxes, levers, buttons, indicators, limit switches, wiring, and hardware. Some concrete demolition work must be required for placement of new buildings and routing of new electrical cable and mechanical pipe.Three (3) new hydraulic power units (HPUs) must be furnished and installed on the land and middle lock walls inside two new 2-story HPU buildings at locations specified on the contract drawings. The fourth HPU will be furnished and installed on an elevated platform in the river wall at the location specified in the contract drawings. The HPU buildings and elevated platform must be designed and constructed by the contractor in accordance with the performance specification and the concept drawings included in the contract drawings. The HPUs must send hydraulic power to the existing hydraulic cylinders by means of new stainless-steel piping and new manifold mounted hydraulic components.The new hydraulic equipment must be operated by new electronic controls that will be installed inside new panels and new control consoles. The new control panels must be installed on each HPU with an additional control panel inside of the middle wall operations building. The new control consoles must be installed inside three existing and one new 1-story control shelter at locations specified in the contract drawings. The control shelter must be designed and constructed by the contractor in accordance with the performance specification and the concept drawings included in the contractdrawings.New buckets and supporting equipment must be installed inside existing motor control centers (MCCs). New hardware and power and control cabling must be installed as specified and as required for operation of the new electrical/mechanical equipment. Some concrete installation work must be required for placement of new buildings and routing of new electrical cable and mechanical pipe. A geotechnical and civil site analysis must be completed to confirm the structural integrity of all foundations for all new project components and to confirm proper drainage. Minimal new steel grating must be required for placement over top new concrete utility trenches. All new hydraulic and controls equipment must be tested and commissioned prior to project handoff. This project is to be completed at a locks and dam site along the Ohio River and thus requires the use of a floating work plant and work boat(s) for construction. Also, all as-built drawings must be stamped by a registered PE.The work shall be completed within 730 after written Notice to Proceed.The acquisition will be procured as 100% Set-Aside for Small Business. The resulting award will be for one (1) Firm-Fixed-Price (FFP) Contract. All responsible Offerors are encouraged to participate. The Request for Proposal (RFP) will be issued on or about 18 June 2026, online through Procurement Integrated Enterprise Environment (PIEE) which posts the opportunity to SAM.gov; therefore, requests for hardcopies of the solicitation will not be honored.The North American Industrial Classification System (NAICS) Code for this acquisition is 237990 - 0ther Heavy and Civil Engineering Construction.The Small Business Size Standard for this NAICS Code is $45,000,000.00.In order to submit an Offer on this project, your company must-1) Be registered in System for Award Management (SAM) and maintain an active registration status. 2) Be registered in the Procurement Integrated Enterprise Environment (PIEE) for the Solicitation Module with the PROPOSAL MANAGER Manger role. System for Award Management (SAM) RegistrationRegistering in SAM.gov includes both entity validation and entity registration.To register in SAM:a. Navigate to SAM.govb. Select Sign-In (top right)c. Select Create an Account then Follow the Instructions. d. After Account is Set-up, Select Sign In.e. Under the Entity Management widget, Select ?Get Started? button. f. Select Register Entity. As part of entity registration, a Unique Entity ID will be assigned.For Additional Information on SAMTo Register Your Entity (company), please visit https:/www.fsd.gov/gsafsd_sp?id=gsa_index . Here you will find the following, Get Started with Your Registration Check Registration Status ? ACTIVE, INACTIVE, PENDING Update Your Registration Become an Entity Administrator Validate Your Entity *Access User Guides *By selecting this option, you can obtain a Quick Start Guide for Contract Registrations.Also, here you will find in addition to the User Guides - FAQs, Videos, and Definitions.PLEASE NOTEIt is mandatory that all companies be registered in SAM in order to receive federal contracts.There is no charge to register or maintain your company (entity) registration.Login.gov manages usernames and passwords for SAM.gov. *Important* Registration InformationRegistration can take at least ten (10) business days to be active in SAM.gov.Registration must be in active status upon offer submission and remain active during award period.Registration must be renewed every 365 days to remain active.The Federal Service Desk (FSD) for SAM questions, may be contacted. Phone Number: 866-606-8220Hours of Operation: Monday-Friday 8 a.m. to 8 p.m. ETProcurement Integrated Enterprise Environment (PIEE) Solicitation Module RegistrationTo register for PIEE follow the below instructions. Register in PIEE:a. Navigate to https://piee.eb.mil/b. Select Register [top right]c. Select Vendord. Create a User ID and Password and follow the prompts [next]e. Create Security Questions [next]f. Complete your User Profile Information [next]g. Complete your Supervisor or Approving Official Information [next]h. Complete Rolesi. Step 1. Select SOL-Solicitationii. Step 2. Select Proposal Manageriii. Step 3. Click Add Rolesiv. Step 4. Fill in your Location Code (CAGE Code) [next]i. Provide a justification for your registration [next]j. Follow the remaining prompts to submit your registrationThe Procurement Integrated Enterprise Environment (PIEE) help desk may be reached by calling telephone number 866-618-5988 for assistance. | 82% | Pre-Solicitation | 06/18/2026 |
NESP LD25 1200 ft Lock --------- The new lock at Lock 25 will be constructed in the downstream direction in the auxiliary miter gate bay, which has minimum provisions for an adjacent 360-foot-long lock and is referred to as Location 3 in the System Feasibility Study (September 2004). This contract will consist of construction of a new 1,200-foot drilled shaft-founded lock in the auxiliary miter gate bay, a 1,200-foot upstream ported guard wall, and a 650-foot downstream guard wall. The existing 600-foot lock will remain in place and once the new lock is constructed and operational, will become an auxiliary lock chamber used primarily by recreation traffic or when the 1,200 ft lock is out of service. ------------ SEE ATTACHMENT FOR FULL DETAILS OF UPCOMING REQUIREMENT SOLICITATION. --------- Attachment 0004 Plans (Volume 1-7) and Attachment 0005 Navisworks Federated Model must be requested via email to Contract Specialist, Whitney Dee at whitney.r.dee@usace.army.mil. Upon request they will be sent via DoD SAFE, since the files are too large to attach within PIEE or send via email. ------ SEE UPDATE LABELED 0817 FOR FULL DETAILS OF UPCOMING PRE-PROPOSAL SITE VISIT. -------------------- AMENDMENT 0001 provides updates in accordance with some of the ProjNet Bidder Inquiries and Government Responses posted through 31 August 2026. Additional questions and answers and updates will be provided in forthcoming amendments. See all attachments for full details.-------------------- AMENDMENT 0002 provides updates in accordance with some of the ProjNet Bidder Inquiries and Government Responses posted through 15 September 2026. Additional questions and answers and updates will be provided in forthcoming amendments. See all attachments for full details.-------------------- AMENDMENT 0003 provides updates in accordance with some of the ProjNet Bidder Inquiries and Government Responses posted through 5 October 2026. Additional questions and answers and updates will be provided in forthcoming amendments. See all attachments for full details.-------------------- AMENDMENT 0004 provides updates in accordance with some of the ProjNet Bidder Inquiries and Government Responses posted through 20 October 2026. Additional questions and answers and updates will be provided in forthcoming amendments. See all attachments for full details.-------------------- AMENDMENT 0005 extends the proposal due date to 10:00AM CST, Wednesday, December 9, 2026. See all attachments for full details..-------------------- AMENDMENT 0006 provides updates in accordance with the final set of ProjNet Bidder Inquiries and Government Responses. See all attachments for full details. | 75% | Solicitation | 12/09/2026 |
Amendment 0002 - See attached Amendment 0002 - The purpose of this amendment is to incorporate clauses that were unintentionally removed by the Army Contract Writing System and to extend the bid submission date by 11 days from 11:00 A.M. Pacific on 19-NOV-2026 to 11:00 A.M. Pacific on 30-NOV-2026; the bid opening will occur at 1:00 P.M. on the date bids are due. Amendment 0001 - See attached Amendment 0001 and updated solicitation notice below for all details regarding the site visit date and link up location changes: The U.S. Army Corps of Engineer (USACE) Portland District is soliciting construction firms who are interested in submitting a competitive firm-fixed-price bid for this project. This solicitation announcement is for the repair and rehabilitation of two Tainter Valves (TV3 and TV4) at the John Day Lock and Dam (JDA). See the attached Solicitation, which includes the Specifications, and the attached Planset for all details. Because a similar requirement at The Dalles Lock and Dam will be solicited after this solicitation, the Government will host the following two site visits on Tuesday, 03 November 2026: 1. 9:00 A.M. @ John Day Dam (Oregon side), Exit 109 from I-84, John Day Dam Rd, Rufus, OR 97050. Check in with security at the front gate and then proceed to the parking lot across the road from the construction trailer; see the link up location map in the solicitation amendment notice. 2. 2:00 P.M. @ The Dalles Dam (Washington side), Lyle, WA 98635. Take US-197N and exit towards The Dalles Dam Boat Launch and park on the left hand side of the road immediately after turning left 90 degrees towards the Boat Launch; see the link up location map in the solicitation amendment notice. Contractors will be able to see a removed Tainter Valve at The Dalles Dam. Send an email to Andrew Sprys and Justin Figueredo by 11:00 A.M. on Wednesday, 28 October 2026, with the following information to register for the site visits: Solicitation Number: W9127N27BA009, Project Title: JOHN DAY DAM NAVIGATION LOCK TAINTER VALVE (TV) REPAIRS TV3 AND TV4, Name(s) of individual(s) attending site visit, Name of Company, Phone Number, Email Address, Are all individuals U.S. Citizens? Participants of the scheduled site visit must abide by the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, latest version) in accordance with Section 5, Personal Protective and Safety Equipment. It is the responsibility of the participants to wear personal protective and safety equipment as required by this regulation. Failure to comply could result in denial of access to site visit location. Site visit attendees must be U.S. citizens and possess a REAL ID to access the sites. Any subsequent visits will require prearrangement with the Contracting Division personnel listed above and may not be guaranteed/approved. Acceptable forms of proof of citizenship for anyone born outside the USA is: 1. US Birth Certificate: Must be certified and issued by either a US State or the US State Department. 2. US Passport Undamaged: Issued by the US Dept of State, without limitation, does not need to be current, is/was valid for 10 years for adults and 5 years for children under 16. 3. US Passport Card Undamaged: Issued by the US Dept of State, without limitation, does not need to be current. 4. US Certificate of Citizenship: Issued by US Citizenship and Immigration Service. 5. Consular Report of Birth Abroad: Issued by the US State Department. 6. US Naturalization Certificate: Issued by US Citizenship and Immigration Service. 7. Enhanced Drivers License: from Michigan, Minnesota, New York, Vermont, or Washington. Acceptable ID: 1. Real ID drivers license. 2. Enhanced drivers license. 3. Federal Identification Cards PIC/CAC/PIV/Etc. 4. Transportation Worker Identification Card (TWIC). 5. United States Passport or United States Passport Card. 6. Drivers license issued by the Department of State. Magnitude of Construction: The estimated cost of the project is between $1,000,000 to $5,000,000. Cybersecurity Maturity Model Certification (CMMC) level: The CMMC level anticipated for this requirement is CMMC Level 1 (Self). This CMMC level, or higher (see 32 CFR part 170), will be required prior to award and maintained for the duration of the contract for each contractor information system that will process, store, or transmit Federal contract information (FCI) or controlled unclassified information (CUI) during performance of the contract. THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THIS SOLICITATION EITHER BEFORE OR AFTER THE RESPONSE DATE AND TIME. NO REIMBURSEMENT WILL BE MADE FOR ANY COSTS ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO THIS SOLICITATION OR ANY FOLLOW-UP INFORMATION REQUESTS. | 72% | Solicitation | 11/30/2026 |
REQUEST FOR INFORMATION (RFI) / MARKET RESEARCH NOTICENotice: This is a Request for Information (RFI) for market research and informational purposes only. *Please see the attachments for instructions* | 71% | Market Research | 05/12/2026 |
Additional Details
Solicitation Number
W911WN15B0005
Archive Date
Dec 3, 2015