Bonneville Dam Spillway Gate Repair Pit Upgrades
Overview
- Response deadline
- 10:00 AM UTC−08:00
- Posted
- February 13, 2024
- Notice type
- Solicitation
- Set-aside
- Total Small Business Set-Aside (FAR 19.5)
- Agency
- Department of WarDepartment of the Army
Notice details
- Office
- W071 ENDIST PORTLAND
- Place of performance
- Cascade Locks, OR, 97014
- Last updated
- Dec 4, 2025
Identifiers
- Solicitation number
- W9127N23R0032
- Notice ID
- 1f0cbd9d474c4509941a0890df2bf1aa
Description
***13 FEB 24*** The drawings we have that cover this are in the file A.03 W9127N23R0032 DRAWINGS FIO (page 8-16 specifically). As for the Specifications that the drawings reference for the paint. We were able to track down the old contract for that as PDF B.06 00935 referencing the paint. Both files have been posted to sam.gov. ***09 FEB 24*** THIS SOLICITATION IS NOW IN PHASE II OF A DESIGN BUILD AND OPEN ONLY TO THOSE COMPANIES SELECTED TO PROCEED FROM PHASE I. *** 05 FEB 24*** The purpose of this amendment is to extend the solicitation perion to 10:00 A.M. PST on 05-MAR-2024. ***20 DEC 23*** Phase II soliocitation amendment posted, proposals due 10:00 A.M. on 20 FEB 24 Addition of provisions for certified cost and pricing data. *** 1 NOV 23 *** There is a conflict in the solicitation guidance regarding the arrangement for submitting information. 3.3 Volume I for Phase I shall be submitted electronically and include the following information: Tab A: Introductory Page Tab B: Standard Form 1442 Tab B: Joint Venture Agreements Tab C: Evidence of Ability to Obtain Bonding & Proof of Financial Ability 4. Phase I Volume I Pro-Forma Document Contents: 4.1 Tab A Introductory Page Content Requirements 4.2 Tab B - Standard Form 1442 Content Requirements 4.3 Tab C Joint Venture Agreements Content Requirements 4.4 Tab D Evidence of Ability to Obtain Bonding and Proof of Financial Ability Content Requirements: As long as the proposal contains the requested minimum information, it will not be eliminated from further consideration based on the above typo. *** 12 OCT 23 Solicitation updated to add attachments A and B. No amendment issued. *** The U.S. Army Corps of Engineers, Portland District, has a requirement to design and construct improvements to the Spillway Gate Repair Pit that will allow the Project Staff to repair and maintain a single gate leaf safely and efficiently within the pit. The Bonneville Spillway Gate Repair Pit allows Project Staff to perform spot repair and maintenance of Spillway Gate leaves (upper and lower gate sections). In general, the existing Spillway Gate Repair Pit does not satisfy the requirements of current design standards.
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Documents
No documents available.
Lifecycle
Solicitation:
W9127N23R0032- Pre-Solicitation
- Solicitation
Award typically follows within 30–90 days after the response deadline. (estimate)
- 2×Pre-SolicitationSep 8, 2023
BON1 Spillway Gate Repair Pit Upgrades
- 9×SolicitationCurrentOct 3, 2023
Bonneville Dam Spillway Gate Repair Pit Upgrades
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
Additional Details
Solicitation Number
W9127N23R0032
Archive Date
Mar 20, 2024
Office Address
PORTLAND, OR, 97204-3495