GovChime
Notice ID: 1c68163c284f47fb92494590eaa94c26Solicitation

BONNEVILLE LOCK AND DAM POWERHOUSE 1 METERING ENHANCEMENT

Archived on July 9, 2024. Original response deadline: . Full description on SAM.gov.

Overview

Response deadline
11:00 AM UTC−07:00
Posted
June 18, 2024
Notice type
Solicitation
NAICS
238210: Electrical Contractors and Other Wiring Installation Contractors
Agency
Department of WarDepartment of the Army

Notice details

Office
W071 ENDIST PORTLAND
Place of performance
Cascade Locks, OR, 97014
Last updated
Dec 4, 2025

Identifiers

Solicitation number
W9127N24R0008
Notice ID
1c68163c284f47fb92494590eaa94c26

Description

10 June 2024: The purpose of this Amendment is to update the Bidder Inquiry information. See Summary of Changes. All other terms and conditions remain unchanged. 06 June 2024: The purpose of this Amendment is to add draw ings/plans that w ere inadvertently left out of the Solicitation package. All other terms and conditions remain unchanged. Project Scope: The scope of this project consists of the Contractor furnishing all supervision, engineering, labor, materials, and equipment to perform the following work in accordance with the detailed requirements of this contract. Background: Bonneville Power Administration (BPA) would like to enter the Energy Imbalance Market (EIM), to do so, BPA needs additional high accuracy class instrument transformers. The requirement for CTs (Current Transformers) to be installed approximately 26 feet above the existing roof elevation, above truss-beam. New mounting supports will also need to be installed for the CTs and pedestals on top of the existing roof. The structural and electrical design, provided by the Hydro Design Center (HDC), provides supports for the new CTs, station post insulators, and busses at locations that provide the required electrical clearances. The HDC designs also evaluates the requirements of supporting the new CTs, station post insulators and busses on legacy roof structural system. The Government will provide the metering-grade CTs and PTs (Potential Transformers), and three deflection insulators. PTs will be replaced in existing location. The Contractor will maintain the maximum distances from ground for each phase to add the real time metering accuracy PTs and CTs as directed by the requirements. Description of Requirement: The Bonneville Power Administration (BPA) has the required metering CTs and PTs in inventory and will provide these to The U.S. Army Corps of Engineers, Portland District, as Government-Furnished Equipment (GFE) for the metering enhancement installation contract. This eliminates the over one-year lead time for commercial procurement of the CTs and PTs after contract award, which would be an unacceptable delay. Bonneville Project O&M staff have committed to furnishing and installing the low-voltage conduit and wiring to the RTU room in the powerhouse. BPA will design and separately install the new control board in the RTU room and will complete the wiring connections. This reduces the installation contractor's scope to fabrication and installation of the new CT supporting structures as detailed in the Plans and Specifications, installing the CT's, replacing the PTs on their existing supporting structures, and field acceptance testing of the GFE instrument transformers. The project is located at Bonneville Dam in Multnomah County, Oregon. Magnitude of Construction: $1,000,000.00 to $5,000,000.00 Set Asides and Codes: Full and Open Competition. The North American Industrial Classification Code (NAICS) for this potential requirement would be 238210, Electrical Contractors and Other Wiring Installation Contractors . The related size standard is $19M. The Product Service Code (PSC) is Z1KA - Maintenance of Dams.

Full description on SAM.gov

Award Overview

No prior contract identified

No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.

Contacts

Documents

No documents available.

Lifecycle

Solicitation:W9127N24R0008
  1. Pre-Solicitation
  2. Solicitation

Award typically follows within 30–90 days after the response deadline. (estimate)

  1. 2×
    Pre-SolicitationJan 16, 2024

    Bonneville Dam Metering Enhancements

    Notice f571ac23e72847d6816af0cf784de451 on SAM.gov

  2. 5×
    SolicitationCurrentMay 23, 2024

    BONNEVILLE LOCK AND DAM POWERHOUSE 1 METERING ENHANCEMENT

    Notice 1c68163c284f47fb92494590eaa94c26 on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline
This solicitation is for the contractor to furnish all personnel, equipment, supplies and materials necessary to install (16) security lights AND (8) utility poles and power supply for Green River Lock and Dam#1, located at 5026 Dam Road, Reed, KY 42451. All work shall be performed in strict compliance with the attached scope of work and all other terms, clauses, and conditions incorporated herein. Quotes are due on 10 August 2026 at 1:00 PM Eastern Time. NOTE: THIS RFQ IS 100% SET ASIDE FOR SMALL BUSINESS. The NAICS code for this procurement is 238210. The size standard is $19M. The solicitation will be available on the web only. Telephone and Fax requests for this solicitation will not be honored. Project files are Portable Document Format (PDF) files and can view, navigated, or printed using Adobe Acrobat Reader. To download the solicitation for this project, contractors are required to register at the Federal Business Opportunities. Amendments will be available from the beta.sam.gov website by download only. Prior to submission of quotes all contractors must have an active registration in the System for Award Management (SAM) database. To register or update information go to http://www.SAM.gov. Questions may be addressed to ProjNet. This announcement serves as the advance notice.
57%
Solicitation08/10/2026
This solicitation is for the contractor to furnish all materials, supplies, tools, parts, equipment, transportation, labor, supervision, communication, and quality control to remove and replace existing control tower bridge crane and trolley at Cagles Mill Lake located at 11979 S. County Rd. 375 W., Poland, Indiana 47868. All work shall be performed in strict compliance with the attached specifications and all other terms, clauses, and conditions incorporated herein. Quotes are due on 28 July 2026 at 10:00 AM Eastern Time. NOTE: THIS RFQ IS 100% SMALL BUISNESS SET A SIDE. The NAICS code for this procurement is 238290. The size standard is $22M. The solicitation will be available on the web only. Telephone and Fax requests for this solicitation will not behonored. Project files are Portable Document Format (PDF) files and can view, navigated, or printed using Adobe Acrobat Reader. To download the solicitation for this project, contractors are required to register at the Federal Business Opportunities. Amendments will be available from the sam.gov website by download only. Prior to submission of quotes all contractors must have an active registration in the System for Award Management (SAM) database. To register or update information go to http://www.SAM.gov. Questions may be addressed to ProjNet. This announcement serves as the advance notice.
53%
Solicitation07/28/2026
** See attached amendment 0003 for details.** ** See attached amendment 0002 for details**.** See attached amendment 0001 for details**. the contractor will be required to provide all labor, material, equipment, and supervision to design, supply, and replace/combine the existing fire alarm controls (Gamewell),mass notification/voice evacuation (Federal Signal), and radio transceiver (King Fisher) into one panel for each building/warehouse (~49 ea). Contractor will also replace the existing central receiving system in the Central Dispatch (Building 235) to receive signal from the new panels, including a backup receiving system in Building 100.
52%
Solicitation10/13/2026
Title: LLA Navigation Lock Switchgear Replacement: The work is located at the Lower Granite Dam, Pomeroy, Washington. The solicitation will be issued as a Best Value Trade-Off (BVTO) Request for Proposal (RFP) and result in a single firm-fixed price construction contract. This procurement is a small business set aside. 100% Performance and payment bonds will be required for this project. The North American Industry Classification System (NAICS code for this project is 238210 Electrical Contractors and Other Wiring Installation Contractors and the associated small business size standard is $19 million. Solicitation number W912EF27RA002 will be posted to the SAM.gov Contract Opportunities website on or about mid November 2026. The proposal due date will be contained in the solicitation and any solicitation amendments that may be issued. The solicitation will be made available for download on the SAM.gov Contract Opportunities website. Offerors are responsible for checking the referenced page for any updates to the Notice. The Government is not responsible for any loss of Internet connectivity or for an offeror's inability to access the documents posted at the referenced website. Proposals will be due approximately 30 days after the solicitation is posted. The exact proposal due date will be indicated in the solicitation. System for Award Management (SAM): Offerors must register in the SAM at https://sam.gov/content/home prior to receiving an award. NOTE: The response date that is required to post this notice is not in any way a due date for any submission. This is a pre-solicitation notice only. Scope: The scope of the work involves replacing existing medium and low voltage switchgear lineups and their associated feeder cables with modernized medium and low voltage switchgear and motor control center lineups at Lower Granite Dam Navigation Lock. The main features of work includes: Provide and install one (1) new medium voltage switch gear. Provide and install one (1) new low voltage switch gear. Provide and install two (2) new motor control center lineups. Provide modernized controls for existing electrical loads. Provide one (1) new 4,160/480-V 1,000 kVA transformer. Provide lighting load centers to replace existing panels. Provide new concrete housekeeping pads for new electrical equipment. Provide new cable trays and conduits where required by circuit reconfigurations and to bring fill ratios to levels that meet electrical codes. Provide an HMI screen to replace an existing annunciator panel. Demolish existing medium and low voltage switchgear, motor controls centers, and transformers. Demolish the existing 480VAC feeders routed from existing low voltage switchgear and motor control centers. Seal hatch and any expansion joints, or cracks, to prevent water intrusion in an existing electrical room. This work is anticipated to be performed in 2028 and 2029, with cutover power construction work being completed during the 2028 and 2029 navigation lock outages. Access to the navigation lock deck and electrical substation rooms will be available for workers and equipment. THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THE SOLICITATION EITHER BEFORE OR AFTER THE CLOSING DATE. NO REIMBURSEMENT WILL BE MADE FOR ANY COSTS ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO THIS PRE-SOLICITATION NOTICE OR ANY FOLLOW-UP INFORMATION REQUEST. All on-site work shall be performed in accordance with the Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1). Establish and manage an effective on-site Safety and Health program in accordance with EM 385-1-1 that will require the development and submission of a comprehensive project specific Accident Prevention Plan for Government acceptance. In addition, develop and submit for Government acceptance Activity Hazard Analyses for each phase of work and a project specific Fall Protection Plan that comply with EM 385-1-1. A Site Safety and Health Officer (SSHO) employed by the prime contractor is required for each shift of the contractor's on-site operations. The SSHO shall possess a minimum of 5-years’ experience in construction safety on similar projects, shall have completed the 30-Hour OSHA Construction Safety training within the last 5 years, and shall have completed at least 24 hours of safety training from accredited safety training sources each year for the past 5 years. Establish and manage an effective Contractor Quality Control (CQC) System that will require the development and submission of a comprehensive project specific CQC Plan for Government acceptance. A CQC System Manager employed by the prime contractor is required to be on-site for each shift of the Contractor's operations. The CQC System Manager must possess a minimum of 5 years relevant experience in a supervisory or management position such as Quality Control Manager, Quality Assurance Manager, or Construction Manager directly involved in the management of construction quality at the project site. In addition, the CQC System Manager shall have completed the course entitled “Construction Quality Management for Contractors” within the last 5 years. Use the Government-furnished Resident Management System (RMS) – Contractor Mode to record, maintain, and submit various information throughout the contract period. RMS is a Windows-based program capable of operating on a stand-alone personal computer or on a network. The Government will make the quality control system (QCS) software available to the Contractor at time of notice to proceed. The project involves the development and management of Contractor furnished submittals for items such as pre-construction plans, product data, test reports, and contract close-out documentation as required by the technical specifications of the contract. Miscellaneous work within the project includes the delivery of As-Built Drawings, O&M Manuals, Contractor- Prepared Shop Drawings, and spare parts to the customer. Solicitation Number W912EF27RA002 will be posted to the SAM.gov approximately on around mid to late November 2026. The solicitation is a Request for Proposal Important Note: The SAM.gov Contract Opportunities Response Date listed elsewhere in this synopsis is for SAM.gov archive purposes only. It does not necessarily reflect the actual proposal due date. There is no response date included in this notice. The proposal due date and time will be contained in the solicitation and any solicitation amendments that are issued. Anticipated Award date is early to mid-March 2027. A site visit will be offered approximately 2 weeks after the solicitation is made available to offerors. See solicitation for details about the site visit. ACCESS FOR FOREIGN NATIONALS: Security clearance for foreign nationals to attend a site visit requires approximately 4 weeks; therefore, clearance should be requested immediately. To request clearance, please submit the names of all foreign nationals proposed for site visit attendance, along with documentation to verify that he/she was legally admitted into the United States and has authority to work and/or go to school in the US. Such documentation may include a US passport, Certificate of US citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), foreign passport with 1-551 stamp or attached INS Form 1-94 indicating employment authorization, Alien Registration Receipt Card with photograph (INS Form 1-151 or 1-551), Temporary Resident Card (INS Form 1-688}, Employment Authorization Card (INS Form l-688A}, Reentry Permit (INS Form 1-327}, Refugee Travel Document (INS Form 1-571}, Employment Authorization Document issued by the INS which contains a photograph (INS Form I-688B}. Send this information by email to leanne.r.walling@usace.army.mil and jani.c.long@usace.army.mil Foreign nationals must have received clearance prior to being granted access to the project site.
49%
Pre-Solicitation11/13/2026
THIS IS A SOURCES SOUGHT NOTICE ONLY. THIS IS NOT A REQUEST FOR PROPOSALS. THERE WILL NOT BE A SOLICITATION, SPECIFICATIONS, NOR DRAWINGS AVAILABLE AT THIS TIME. The U.S. Army Corps of Engineers – Norfolk District is anticipating a future procurement for a firm-fixed-price construction contract for the Gathright Dam Motor Control Center Electrical Repairs Project in Covington, Virginia. Description of Work: The United States Army Corps of Engineers, Norfolk District, is seeking eligible firms capable of performing motor power, control, and instrumentation electrical renovations for the intake tower located at Gathright Dam, Virginia. The primary electrical scope entails the replacement of existing 480-volt motor control centers (designated MCC2 and MCC3) with new motor control centers complete with starters, controls, incoming and outgoing feeders, incoming and outgoing conduits, control circuits, and field wiring. Incidental work includes contractor field verification of conduit pathways, replacement of conduits directly affected by equipment replacements or compromised by corrosion in accordance with the conduit and cable schedule, and the replacement in-kind of transformer XFMR-3. In addition, the project requires the comprehensive replacement and modernization of the facility control system. Work includes the demolition of existing control panels, power panels, and communication panels, followed by the installation of new Programmable Logic Controller (PLC) panels, Remote Input/Output (RIO) panels, Human-Machine Interface (HMI) screens, and all associated network wiring, cabling, and conduit infrastructure. Work to include replacement of the instrumentation for the wet well gate displacement (linear displacement sensors) to be tied into the new control system and updates to lighting to manage the nearing end-of-life of the old metal-halide high bay lights and fluorescent wallpack lights. The contractor will also be responsible for programming the new PLCs and reprogramming the existing Sutron system. All operations must be carefully phased and coordinated, as facility buildings will remain occupied throughout the duration of contract performance. There is also a bid option for a warehouse-style high bay luminaire lifting mechanism at a low-enough power-per-luminaire to tie into the associated existing lighting circuit. The estimated construction price range for this project is between $1,000,000.00 and $5,000,000.00. NAICS Code 238210, Electrical Contractors and Oher Wiring Installation Contractors, applies to this project with a small business size standard of $19,000,000.00. PSC J061, Maintenance, Repair, and Rebuilding of Equipment – Electric Wire and Power Distribution Equipment, applies to this project. The Government is not obligated to and will not pay for any information received from potential sources as a result of this sources sought. Construction Time: The construction period of performance will be approximately 360 calendar days from issuance of the Notice to Proceed (NTP). The official synopsis citing the solicitation number will be issued on System for Award Management (SAM) at www.sam.gov. INDUSTRY SURVEY The following confidential survey questionnaire is designed to apprise the Corps of prospective contractors' project execution capabilities. Please provide your response to the following questions. All questions are in regard to the Gathright Dam Motor Control Center Electrical Repairs in Covington, Virginia. Firm's response to this Synopsis shall be limited to 5 pages and shall include the following information. 1. Firm's name, address, point of contact, phone number, and e-mail address. 2. Firm's interest in bidding on the solicitation when it is issued. 3. Firm's capability to perform a contract of this magnitude and complexity (include firm's capability to execute construction, comparable work performed within the past 5 years): Brief description of the project, (customer name, timeliness of performance, and dollar value of the project) - provide at least 3 examples. 4. Firm's Business Size - LB, SB, 8(a), HUBZone, SDVOSB, or WOB. 5. Firm's Joint Ventures (existing), including Mentor Protégés and teaming arrangement information is acceptable. 6. Firm's Bonding Capability (construction bonding level per contract and aggregate construction bonding level, both expressed in dollars) via letter from a bonding company. Please only include a narrative of the requested information. Additional information will not be reviewed. This Sources Sought Synopsis should not be construed in any manner to be an obligation of the U.S. Army Corps of Engineers, Norfolk District to issue a contract, or result in any claim for reimbursement of costs for any effort you expand responding to this request. No solicitation is currently available. The Government will utilize this information in determining an acquisition strategy. Please state all of the socio-economic categories in which your company belongs—(8)(a), Hub-zone, Service-Disabled Veteran Owned Small Business, Woman Owned. Please submit capability packages and responses to the above questions via email to Caleb Bookout at Brian.C.Bookout@usace.army.mil, copying Luke D. Hedlund at Luke.D.Hedlund@usace.army.mil. Responses must be submitted no later than Close of Business 19 November 2026 . The official synopsis citing the solicitation number will be issued on SAM.gov at https://sam.gov/content/home. All prospective contractors are required to be registered in the System for Award Management (SAM) database prior to contract award. Offerors and contractors may obtain information on registration and annual confirmation requirements by calling 1-866-606-8220 or via the Internet at https://www.sam.gov. Representations and Certifications Applications apply to this solicitation. Representations and Certifications may be completed online via the SAM. No attachments or links have been added to this opportunity.
47%
Market Research11/19/2026

Additional Details

Solicitation Number

W9127N24R0008

Archive Date

Jul 9, 2024

Office Address

PORTLAND, OR, 97204-3495