Notice ID: 474bbe4fd55d4210abc2796547e88353Solicitation

Missouri River BSNP Structures Repairs North & South FY 22

Archived on September 17, 2022. Original response deadline: . Full description on SAM.gov.

Overview

Response deadline
2:00 PM UTC−05:00
Posted
September 2, 2022
Notice type
Solicitation
Set-aside
Total Small Business Set-Aside (FAR 19.5)
NAICS
237990: Other Heavy and Civil Engineering Construction
Agency
Department of WarDepartment of the Army

Notice details

Office
W071 ENDIST OMAHA
Place of performance
Omaha, NE
Last updated
Dec 4, 2025

Identifiers

Solicitation number
W9128F22B0010
Notice ID
474bbe4fd55d4210abc2796547e88353

Description

***17 Aug 2022 - Site Visit Sign-In uploaded to attachments*** ***Firms that Submitted Acceptable Proposals in Step One*** 1. Fenton Construction, Inc. 2. Legacy Corporation of Illinois 3. Midwest Construction Company 4. Western Contracting Corporation ***Drawings and Specifications for Step-2 IFB has been uploaded on 4 August 2022*** The 2019 floods caused significant damage to the Missouri River Bank Stabilization and Navigation Project (BSNP) structures. The damaged structures include revetments, dikes, kickers, L-head dikes, and vanes.These structures are critical to maintaining a navigation channel on the Missouri River. Under this construction contract, the contractor will rehabilitate critical damaged BSNP structures by adding quarried rock to replace areas of deterioration. In areas with substantial loss of structural material, the work will effectively rebuild parts of the structure. The project location extends from Missouri River, Sioux City, IA to Rulo, NE in the States of IA, NE, and MO.

Full description on SAM.gov

Award Overview

No prior contract identified

No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.

Contacts

Documents

No documents available.

Lifecycle

Solicitation:W9128F22B0010
  1. Pre-Solicitation
  2. Solicitation

Award typically follows within 30–90 days after the response deadline. (estimate)

  1. 3×
    Pre-SolicitationMay 10, 2022

    Bank Stabilization & Navigation Project (BSNP) Structures Repair Project

    Notice ed017360ef07444293001ab82092e415 on SAM.gov

  2. 10×
    SolicitationCurrentJun 3, 2022

    Missouri River BSNP Structures Repairs North & South FY 22

    Notice 474bbe4fd55d4210abc2796547e88353 on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline
The project is located along the left descending bank of Lake Sharpe near the Lower Brule, SD town site. Lower Brule North Element 2 includes a 100-foot-wide riparian planting bench, a gravel maintenance path along the entire reach, a riprap revetment to protect the shoreline and island from erosion, and the creation of a 200-by-1,500-foot island constructed in water up to three feet deep. The sheltered open water area between the island and the shoreline will develop into approximately 5.17 acres of emergent wetland, and this will also create approximately 32 acres of riparian habitat. Related tasks include earth moving, grading, bank shaping, rock installation, water management, fill, and topsoil placement.
-Solicitation12/03/2026
On or about 23 October 2026, the Government intends to issue the Invitation for Bid (IFB) for LOWER BRULE NORTH SHORELINE STABILIZATION AND ECOSYSTEM RESTORATION, ELEMENT 2. The IFB will close on or about 3 December 2026. This is a 100% Small Business Set-Aside. Sit Visit: A Site Visit is scheduled for 3 November 2026. Additional information regarding the site visit will be provided in the solicitation in Section 00 21 00. Project Description: Element 2 of the project includes the construction of a 100-foot-wide riparian planting bench, a gravel maintenance path along the entire reach, and the creation of a 200-by-1,500-foot island within Reach 4 of the lake, in water up to three feet deep. The island will be planted with cottonwood trees and other culturally significant vegetation. To protect the lakeward side of the island from wind, wave action, and ice erosion, a riprap revetment will be installed. The sheltered open water area between the island and the shoreline is anticipated to naturally evolve into approximately 5.17 acres of emergent wetland. Additionally, this measure will result in the creation of roughly 32 acres of riparian habitat. DO NOT submit requests for plans and specifications. See Obtaining Solicitation Documents below. Completion Date: The Contractor will be required to commence work upon receipt of contract award and complete the work 550 days after receipt of Notice to Proceed. This is subject to change after IFB issuance. Provisions will be included for liquidated damages in case of failure to complete the work in the time allowed. Performance and Payment Bonds will be required. Estimated Construction Costs: The estimated construction cost of this project is between $10,000,000 and $25,000,000. NAICS Code: The Primary North American Industry Classification System (NAICS) code anticipated for solicitation is 237990, Heavy and Other Civil Engineering Construction, with a size standard for Small Business of $45M. All contractors must be registered and have an active and verified account in the System for Award Management (SAM) in order to receive a contract award from any DoD activity. Contractors may access the Internet site at: https://www.sam.gov/ to register and/or obtain information about the SAM program. Contractors must ensure that the applicable NAICS listed above is included in their profile prior to submission of offer. Contracting Officer Address: USACE Omaha District 1616 capital Ave Omaha, NE 68102-4901 Point Of Contact: All questions shall be submitted on ProjNet. ProjNet access, and additional guidance, will be given at time of issuance of the IFB Solicitation. Place of performance: Big Bend, Lower Brule, South Dakota 57548 Bid Submissions: BID SUBMISSION REQUIREMENTS HAVE CHANGED AND WILL NO LONGER BE ACCOMPLISHED VIA EMAIL. Contractors shall submit their bids via Procurement Integrated Enterprise Environment (PIEE) Solicitation Module no later than 1 hour before the date and time established in Block 13 of the Standard Form (SF) 1442, or Block 14 of the most recently issued SF 30 as applicable: **It is recommended that contractors create their PIEE Solicitation Module account as soon as possible and not wait till bid due date, as access may take time. The following information is provided for reference. Step 1: Complete vendor registration on https://piee.eb.mil/.Instructions for registration can be found through: https://www.acq.osd.mil/asda/dpc/ce/cap/docs/piee/PIEE_Solicitation_Module_Vendor_Access_Instructions.pdfStep 2: Upload offer in the Solicitation Module through https://piee.eb.mil/. Instructions for uploading an offer can be found through: https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/solicitation/proposals.xhtmlDo not assume submission will be instantaneous. File size and number of files submitted shall be considered. Contractors should allow adequate time for submission completion because the entire bid must be received by the due date and time specified in Block 13 of SF 1442, or SF 30 as applicable. Bids received after the date and time stated within Block 13 of the SF 1442 or Block 14 of the most recent SF 30, as applicable, will be considered late and will not be considered for award. To avoid rejection of a bid, the bidder must ensure the submission is virus-free. The government will follow FAR 14.406 if a bid is unreadable. Part 15 is not applicable to this acquisition. Do not assume submission will be instantaneous. File size and number of files submitted shall be considered. Bidder/Teammate/Subcontractors should allow adequate time for submission completion because the entire bid (i.e. bidders submission and all teammate/subcontractor(s) independent submissions) must be received by the bid due date and time specified in Block 13 of SF 1442, or SF 30 as applicable. Obtaining Solicitation Documents: Solicitation documents will be posted in the PIEE Solicitation Module. A link to the solicitation documents on https://piee.eb.mil will be available on SAM.gov. The links below provide resources for accessing the PIEE Solicitation Module. Web Based Training for the PIEE Solicitation Module - https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/index.xhtml Department of Defense Procurement Toolbox - https://dodprocurementtoolbox.com/site-pages/solicitation-module Note: Offerors please be advised that an online registration requirement in System for Award Management (SAM) database http://www.sam.gov/ exists and directed solicitation provisions concerning electronic annual Representations and Certifications on SAM. Representations and certifications are required to be updated annually as a minimum to keep information current, accurate and complete. The electronic annual representations and certifications are effective for one year from date of submission or update to SAM. PHONE CALLS WILL NOT BE ACCEPTED.
-Pre-SolicitationOpen
***Revision 3, 21 September 2026: Changes made to the following sections: Responses Section changed Constance Ellard to Nadine Catania ***Revision 2, 12 May 2026: Changes made to the following sections: Responses Section changed Constance Ellard to Nicole Parker ***Revision 1, 12 May 2025: Changes made to the following sections: "QUALIFICATION REQUIREMENT", Paragraph 1. Experience "RESPONSES", Paragraph 1. Experience ANNOUNCEMENT This is a PREQUALIFICATION OF SOURCES announcement, issued in accordance with DFARS 236.272 and the U.S. Army Corps of Engineers Acquisition Instruction (UAI) 5136.272. No reimbursement will be made for any costs associated with providing information in response to this announcement or any follow up information requests. Respondents will be notified of the results of the prequalification process. The U.S. Army Corps of Engineers (USACE), Omaha District is seeking to create Prequalified Sources List (PSL) for levee repairs in the states of Iowa, Missouri, and Nebraska. As a result of flooding in the spring of 2024, there are damages to 30 federal and non-federal levee systems with over 500 miles of earthen levees with the Omaha District. The levees are in the Missouri River Basin on the Missouri River and its tributary rivers and creeks within the Omaha District. The attached list of projects entitled “PSL Projects Missouri River Basin” (Attachment 1) contains a description of each planned levee repair project. The majority of levee repair construction shall be self-performed by the prime contractors under this prequalification. The objective of the PSLs is to identify and select responding firms that demonstrate the capacity and capability to successfully support critical levee repairs without relying entirely on subcontractors. Subcontracting will be allowed, but will not be part of the prequalification process. Identifying and selecting prequalified sources will be based solely on the responding firm's ability to meet the specific criteria that assess the firm's bonding capability, previous experience completing construction of levee projects or cut/fill grading operations, and past performance. The selection process will be objective in that responding firms either meet or fail to meet the criteria. Failure to meet any one of the criteria will result in non-selection. The criteria ensure selection of clearly qualified contractors with experience and capability relevant to the anticipated requirements, provide competition, and minimize subjectivity in USACE's assessment. The PSL will be available for use while other acquisitions are underway for similar requirements. The PSL will be reviewed annually to ensure a legitimate need exists. Presently, USACE anticipates at least 30 contract actions during the next 2 years. As such, it is likely that a legitimate need will continue for the next 24 months. Magnitudes of disclosure will be provided at the time of solicitation for each project. After the PSL is established, USACE intends to proceed by issuing solicitations using FAR Part 14 procedures (i.e., sealed bidding). The North American Industry Classification System (NAICS) code for procurements using the Prequalified Sources List is 237990, Other Heavy and Civil Construction, which has a small business size standard of $45M. BONDING REQUIREMENTS Pursuant to the Miller Act, performance and payment bonds shall be provided for each contract awarded under the PSL. Typically, Notice to Proceed (NTP) will not be issued until after the successful bidder provides sufficient bonding. However, in some time-sensitive situations, USACE may issue NTP at award, which will be stated in the solicitation. QUALIFICATION REQUIREMENTS To be considered qualified for the PSLs, firms must meet the following minimum requirements 1. Experience: Proven competence as the prime contractor performing construction of at least three earthwork projects or cut/fill grading operations including either levee construction, levee degrading and reconstruction, and/or large scale cut/fill projects. Each project submitted for experience must have included a minimum cut/fill quantity of 10,000 cubic yards of material. Each project should have a value of at least $750,000. Relevant experience includes hauling/placement and engineered compaction of soil/sands material, hauling/placement of aggregate material, hauling/placement of rip rap material, placement of geotextile/geogrid, and other engineered slope stabilization solutions, sheet pile construction, seeding, haul material, haul road construction, and/or mass cut/fill operations requiring grading of material. (***Revision 1***) Two (2) of the three (3) projects submitted shall show a minimum selective placement per project of 500 tons of riprap on slopes up to 1V:1.5H with a D50 greater or equal than 12-inches. Selective placement includes placing riprap on an underlying bedding or geotextile without disturbing/shifting the bedding or geotextile.*** 2. Past Performance: Information that demonstrates satisfactory ratings by the client for each of the projects cited in Experience above that indicates a recommendation to use the contractor for future projects. A CPARS evaluation or its equivalent from the client meets this requirement. The firm's self-assessment of its own performance is not requested and will not be substituted for the client's assessment. Additionally, past performance may be based on the Contracting Officer’s or Contracting Officers’ Representatives’ knowledge of and previous experience with similar purchases acquired. In addition to the above information required to be submitted with the proposal, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, and any information available to the Government, past performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), Federal Awardee Performance and Integrity Information System (FAPIIS), and any other known sources not provided by the offeror. Past Performance may also be evaluated based on information about contractor performance from existing performance documentation from any past contracts. Additional past performance information from other contracts may be considered by the qualification authority. This information could include contract terminations, safety violations, cure notices, tax delinquencies, non-compliance with subcontracting plans, compliance with labor laws, assessment of liquidated damages, and adversarial management practices or behaviors as viewed by the client. USACE reserves the right to consider past performance information from any source it deems relevant. 3. Bonding: A firm must have a single bonding capability of $5 million and aggregate of $10 million SET-ASIDES All firms submitting documentation meeting the standards for prequalification will be placed on the PSL. However, placement on the PSL does not guarantee a firm will be solicited for every requirement. The contracting officer will consider the following set- asides: Small Business Set-Aside: Pursuant to FAR Part 19, the contracting officer may elect to set-aside any solicitation within the PSL for a specific small business category. Small business classification will be determined by the representations and certifications in SAM for NAICS 237990, Other Heavy and Civil Construction. Local Area Set-Aside: Pursuant to FAR Part 26.2, the contracting officer may elect to set-aside any solicitation within the PSL for local firms residing in or primarily doing business in the disaster area. For the State of Iowa, the disaster area includes the following counties: Cherokee, Harrison, Lyon, Monona, Montgomery, Pottawattamie, O'Brien, Osceola, Plymouth, Scott, Shelby, Sioux, and Woodbury. For the State of Nebraska, the disaster area includes the following counties/areas: Boyd, Burt, Butler, Clay, Colfax, Dakota, Dawson, Dodge, Douglas, Dundy, Fillmore, Hamilton, Hayes, Hitchcock, Holt, Howard, Keith, Lincoln, McPherson, Nance, Nemaha, Platte, Polk, Red Willow, Richardson, Sarpy, Saunders, Scotts Bluff, Thomas, and Washington. If additional counties are declared disaster areas for the spring 2024 flood event, they will be considered to meet the definition of the local area for the purposes of this prequalification notice. If a firm did not reside in one of the disaster areas listed above as of June 19, 2024 and requests to be classified as local, it must submit compelling evidence that its primary business is derived from the disaster area. A mere statement to this effect or incomplete calculations are inadequate. The contracting officer may elect to utilize both local area and small business set-asides in the same solicitation within the PSL. The contracting officer may also elect to advertise solicitations for levee repairs contracts outside of the PSL entirely. These decisions will be made on a case-by-case basis with considerations including (but not limited to) adequate competition, small business goals, number of small business bidders, administrative efficiency, pricing trends, and industry feedback. ROLLING ADMISSIONS After the PSL has been established, firms that wish to be added to a PSL may submit responses at any time according to the instructions stated in this announcement. USACE reserves the right to hold responses received after the first 30 days of this PSL announcement to review in an efficient manner, but for no more than 90 days. A firm will typically be notified of USACE’s review within 7 days of the review. A firm who is initially determined to not meet the qualification standards may re-submit its response no more than once annually thereafter provided its qualifications have changed. SOLICITATION PROCESS USACE will provide all firms in the PSL notification of its intent to advertise a solicitation via an e-mail to the firm’s designated e-mail address. The notification will include a brief summary of the requirement and identify any small business or local area set-asides. The contracting officer will endeavor, but is not required, to provide the notice to PSL firms at least 7 days prior to issuing the solicitation. Prior to the issuance of a solicitation, USACE will post at least one interim design package for each solicitation to the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module for a prequalified firm to review at its discretion. Solicitations and drawings will be sent via email. Solicitation amendments will be posted to the same forum as the original solicitation. USACE may distribute a solicitation via e-mail to everyone included in the PSL. Sealed bid solicitations will reflect the date of bid opening and will generally allow 14 days to submit a bid. More time will be allowed for those solicitations that are large or complex and warrant more bidding time. Upon identification of the apparent low bidder, the bid will be reviewed for conformity to the solicitation requirements (i.e., responsiveness) and contractor responsibility must be considered. After an affirmative determination of contractor responsibility and price reasonableness, USACE will proceed with contract award. The bid abstract will be made available to the entire PSL via e-mail. Firms or entities outside of the PSL will not be provided bid results. However, the award information (company name, address, and total amount) for a federal contract will be released publicly on SAM.gov. REQUESTS FOR INFORMATION Interested parties shall submit questions concerning this announcement via Bidder Inquiry in ProjNet at www.projnet.org/projnet. 1. To submit and review inquiry items, interested parties will need to be a current registered user or self- register in the system. To self-register, go to the aforementioned web page and click on the BID tab, select Bidder Inquiry, Select agency USACE, and enter the Bidder Inquiry Key for this announcement (listed below), your email address, and then click <login>. Verify all information on the next screen is correct and click <continue>. 2. From this page, you may view all bidder inquiries or add an inquiry. 3. Interested parties will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by USACE Technical Review Team. 4. The Special Notice number is: W9128F25R0041 5. The Bidder Inquiry key is: SS96KS-R5CXUH 6. Interested Parties are requested to review the Bidder Inquiry System for answer to questions prior to submission of a new inquiry. 7. The Bidder Inquiry call center can be contacted with questions concerning the use of Bidder Inquiry. The call center operates weekdays from 8am to 5pm Central time. The telephone number for the call center is 800-4289-HELP. RESPONSES Interested firms shall respond to this Prequalification of Sources announcement no later than 9 June 2025 to be eligible for the first solicitations issued. All interested firms must be actively registered at www.sam.gov using NAICS 237990 to be eligible for award of federal contracts. Email your electronic response to Nicole Parker at nicole.l.parker@usace.army.mil and Clinton Russell at clinton.e.russell@usace.army.mil. Responses to this Prequalification of Sources announcement shall not exceed 12MB and shall contain: 1. Experience: Narrative identifying at least three self-performed earthwork contracts in accordance with Paragraph 1 of QUALIFICATION REQUIREMENTS. Narrative must be in sufficient detail to determine the type of work, location, timeframe, value, quantities, client, and whether it was a prime contract or subcontract. Each project must have a value of at least $750,000 (minimum) and 10,000 (minimum) cubic yards of material. (***Revision 1***) Two (2) of the three (3) submitted projects shall show a minimum selective placement (per project) of 500 tons of riprap on slopes. Selective placement of riprap is defined as placing on an underlying bedding or geotextile without disturbing/shifting the bedding or geotextile.*** If your firm was a subcontractor, the value and quantities stated should be those of the subcontract, not the entire contract. Do not submit projects completed by teaming partners or planned subcontractors unless there is an approved joint venture or mentor-protégé agreement. Narrative attachments shall be returned in a searchable Adobe PDF. Page Limitation: 10 pages. 2. Past Performance: Information that demonstrates satisfactory ratings by the client for all projects cited and submitted for Experience. The information should indicate the client’s recommendation of the firm for future projects. A CPARS evaluation or its equivalent from the client would meet this requirement. If no rating exists, submit the attached Past Performance Questionnaire (PPQ) (Attachment 1) completed by the client. The name, address, phone, and e-mail of the client must be included in the submission. Information submitted by the firm regarding its own assessment of Past Performance may be disregarded. Page Limitation: None. 3. Bonding: A current signed letter shall be provided from your firm's surety documenting the single bonding capability of at least $5 million and the aggregate bonding capability of at least $10 million. Page Limitation: 2 pages. 4. Designated E-mail: Designate a single e-mail address for your firm to be utilized for all solicitation notices, solicitation postings, amendments, and bid abstracts under this PSL. It is recommended that this e-mail not be tied to any single person. The e-mail account must be able to receive e-mails of 10MB file size. If multiple e-mail addresses are provided, only the first e-mail address will be utilized. 5. Certifications: Certification, including the following information, by the principal of the firm regarding: a. Unique Entity Identifier (UEI) code, CAGE code, eligibility for federal contract awards, and active registration in SAM. b. Business Classification: Certify your business’s size standard under NAICS 237990 with a $45 million size standard. Include any other small business representations as well. In the event of a conflict with what is certified and what is in SAM, representations from SAM will be utilized by USACE. c. Local Firm: Certify whether your firm is a local firm pursuant to Paragraph 2 of SET- ASIDES in this notice. SAM will be utilized to verify residency certification. If you are certifying as a local firm pursuant to the primary business provision, you must submit compelling evidence that your primary business is derived from the disaster area. USACE is the final authority on determination of whether a firm is classified as local for the purposes of local area set-asides under this PSL. Firms that did not have residency or primary business revenues established in the disaster area as of June 19, 2024 may not be classified as local. d. Accuracy and Completeness: Certify that all information contained in the response is accurate and complete. Experience, Past Performance, and Bonding will be evaluated for purposes of meeting prequalification standards. Designated E-mail and Certifications are not prequalification standards that are passed or failed, but will affect notification and eligibility for solicitations under the PSL. Attachments: PSL Projects Missouri River Basin (Attachment 1) Past Performance Questionnaire (Attachment 2)
-Solicitation06/09/2025
**** Abstract has been posted **** Amendment 0001 has been added to this Solicitation. Reminder that this amendment must be acknowledged and submitted with an offer.The proposed action is for renovation and/or reconstructing portions of an existing facility, and the Scope of Work is included in specification section 01 11 00 Summary of Work. The work includes but is not limited to, demolition of existing features to include stoops, siding, pavement, doors, etc.; civil site work to include grading, asphalt paving, erosion control and utility installation; concrete placement, Concrete Masonry Unit (CMU) repair, door installations, window and louver screen repair, electrical and mechanical system installation, as prescribed in the solicitation documents. The work shall include all direct and indirect costs including profit, risk and contingency to perform the scopes of work included in this solicitation. Any areas utilized by the contractor within the DoD property shall be in the original or improved condition as determined by the Contracting Officer upon completion of the work. SITE VISIT INFORMATION A site visit is scheduled for Thursday 16 April 2026 at 10:00am CT. Contractors interested in seeing the site need to make a reservation with the POC below: Name: David Nuss, Address: 9501 John J. Pershing Drive, Omaha, NE 68112, Telephone: 402-305-1957, Email: David.E.Nuss@usace.army.mil.
-Solicitation05/05/2026
The U.S. Army Corps of Engineers (USACE) Omaha District intends to determine the extent of capable small businesses and other than small business firms that have the availability in providing the requirement described below. USACE is considering issuing a Total Small Business Set-Aside, Two-Step Invitation for Bid (IFB) that will result in one (1) Firm Fixed-Price contract for the Missouri River Levee L594-601 Repair on the Missouri River in Mills and Fremont County, Iowa. The North American Industry Classification System (NAICS) Code is 237990, (Other Heavy and Civil Engineering Construction). Estimated Magnitude of Construction: Between $50,000,000 and $100,000,000. Bid bonds will be required to be submitted with the Step Two bid submission. Payment and Performance Bonds will be required for the full amount (100%) at the time of contract award before the Notice to Proceed (NTP) can be issued. PROJECT SCOPE: Missouri River Levee L594-601 project includes repairing damages of breaches and filling scour holes of various lengths and depths, loss of critical levee sections, crest damage, landside and riverside embankment erosion, berm damage, levee ramp damage, levee surfacing, toe drain, drainage structure damage, relief well damage, pump station damage, other equipment or instrumentation damage, loss of vegetation, seepage boils, and slope failure. The work will be along the left bank of the Missouri River, approximately between the towns of Bartlett, Iowa and Pacific Junction, Iowa. USACE is seeking comments from the construction community for the following: Use of Project Labor Agreements (PLA) for this project; Whether a small business set-aside would be competitive considering the bonding requirements and potential PLA requirements. A PLA is defined as a pre-hire collective bargaining agreement between a Prime contractor and one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S. C. 158(f). ***PLEASE ANSWER THE QUESTIONS VIA THE LINK AT THE BOTTOM OF THIS NOTICE *** Federal Acquisition Regulation (FAR 22.503) Policy provides that: (a) Executive Order (E.O.) 14063, Use of Project Labor Agreements for Federal Construction Projects, requires agencies to use project labor agreements in large-scale construction projects to promote economy and efficiency in the administration and completion of Federal construction projects. (b) When awarding a contract in connection with a large-scale construction project (see 22.502), agencies shall require use of project labor agreements for contractors and subcontractors engaged in construction on the project, unless an exception at 22.504(d) applies. (c) An agency may require the use of a project labor agreement on projects where the total cost to the Federal Government is less than that for a large-scale construction project, if appropriate. (1) An agency may, if appropriate, require that every contractor and subcontractor engaged in construction on the project agree, for that project, to negotiate or become a party to a project labor agreement with one or more labor organizations if the agency decides that the use of project labor agreements will— (i) Advance the Federal Government's interest in achieving economy and efficiency in Federal procurement, producing labor-management stability, and ensuring compliance with laws and regulations governing safety and health, equal employment opportunity, labor and employment standards, and other matters; and (ii) Be consistent with law. (2) Agencies may consider the following factors in deciding whether the use of a project labor agreement is appropriate for a construction project where the total cost to the Federal Government is less than that for a large-scale construction project: (i) The project will require multiple construction contractors and/or subcontractors employing workers in multiple crafts or trades. (ii) There is a shortage of skilled labor in the region in which the construction project will be sited. (iii) Completion of the project will require an extended period of time. (iv) Project labor agreements have been used on comparable projects undertaken by Federal, State, municipal, or private entities in the geographic area of the project. (v) A project labor agreement will promote the agency's long term program interests, such as facilitating the training of a skilled workforce to meet the agency's future construction needs. (vi) Any other factors that the agency decides are appropriate Interested prime contractors must have an active System for Award Management (SAM) registration. Firms can register via the SAM website at https://sam.gov/. If an offeror is a Joint Venture (JV), the JV entity must have valid SAM registration in the SAM database representing the JV as one (1) business/firm/entity. The point of contact for all questions/inquiries is Contract Specialist Karen Caskey at email above karen.l.caskey@usace.army.mil. Please incorporate responses to the following questions within your submission: The questions are in the following link: https://forms.osi.apps.mil/r/a1KEhTK5aR?origin=lprLink The link is also available in the link section below.
-Market Research03/19/2026

Additional Details

Solicitation Number

W9128F22B0010

Archive Date

Sep 17, 2022

Office Address

OMAHA, NE, 68102-4901