Notice ID: 16d4b3d93a8e4db8ba86cfec0a30da81Award NoticeAwarded
Fort Peck Outdoor Station Service Transformer B Install (Ft Peck, Montana)
Awarded on June 6, 2024. Full description on SAM.gov.
Awarded tounder W9128F24C0022 (source: SAM.gov award notice)• $6.1M
Overview
- Posted
- July 9, 2024
- Notice type
- Award Notice
- NAICS
- 237130: Power and Communication Line and Related Structures Construction
- Agency
- Department of War
Notice details
- Place of performance
- Fort Peck, MT, 59223
- Last updated
- Dec 4, 2025
- Award date
- Jun 6, 2024
- Award amount (SAM.gov award notice)
- $6.1M
Identifiers
- Solicitation number
- W9128F24R0045
- Notice ID
- 16d4b3d93a8e4db8ba86cfec0a30da81
- Award number (PIID)
- W9128F24C0022
Description
Amendment 0002 The purposes of this amendment are to: 1. Provide the corrected solicitation drawings set, which includes the S-series drawing sheets necessary for the solicited project. 2. Update Division 00 22 00 11.1.1. Submission Requirements, Schedule Constraints, item 3. All terms and conditions remain unchanged. See the following attachments for details: W9128F24R0045_ Am-0002 Fort Peck - Outdoor SS Transf Replacement Ctr Dwgs_Signed_8 Mar 24 - Amd 0002 ---------------------------------------------------------------------------------------------------------------------------------------------------------- "PROJNET was closed early in error. PROJNET has been opened for comments and will be available through 9 March 2024" -------------------------------------------------------------------------------------------------------------------------- Amendment 0001 The purposes of this amendment are to: Correct the site visit date typo from 22 Feb 2023 to 22 Feb 2024 Update the NTP date to 14 May 24 Incorporate changes to the specifications into the solicitation. All terms and conditions remain unchanged. See the following attachments for details: W9128F24R0045_AMD0001 03 30 53.09 26 Am-0001 ---------------------------------------------------------------------------------------------------------------------------------------------------------------------- Site Visit : A site visit is scheduled for 22 Feb 2024 at 10 am MDT. Contractors interested in seeing the site need to make a reservation with Irene Whitmer telephone (406) 526-3431or by e-mail at Irene.E.Whitmer@usace.army.mil. We currently working on Amendment 0001 to " W9128F24R0045 1 of 4" to reflect the aforementioned date Project Description: Install outdoor station service transformer B, assume transformer will be moved from current location. Replace four existing 4160 switchgear including 4 vertical draw-out 4160-volt circuit breakers with horizontal draw out breakers of modern design and safety features. Replace existing 4160-volt potential and current transformers associated with the 4160-volt bus. The Contractor will be required to commence work upon receipt of contract award and complete the work 1045 calendar days after receipt of Notice to Proceed, this is subject to change after solicitation issuance. Estimated Construction Costs (only include if applicable): The estimated construction cost of this project is between $1,000,000 and $5,000,000. NAICS Code: The Primary North American Industry Classification System (NAICS) code anticipated for solicitation is 237130; Power and Communication Line and Related Structures Construction, with a size standard for Small Business of $45M. Contracting Office Address: USACE Omaha District 1616 Capital Ave, Omaha, NE 68102-4901 Point Of Contact: Technical inquiries and questions relating to this solicitation shall be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org. See attachment " W9128F24R0045 1 of 4" for Project ID and Bidder Inquiry Key. Place of Performance: COE FT PECK PROJECT OFFICE USACE OMAHA CENWO-OD-FP 301 EAST KANSAS STREET FORT PECK MT 59223-0208 Note: Offerors please be advised that an online registration requirement in System for Award Management (SAM) database http://www.sam.gov/ exists and directed solicitation provisions concerning electronic annual Representations and Certifications on SAM. Representations and certifications are required to be up-dated annually as a minimum to keep information current, accurate and complete.
Award Overview
Award Number
W9128F24C0022
Award Amount (SAM.gov award notice)
$6.1M
Award Date
Jun 6, 2024
Awardee
Awardee UEI
F8ESZW6XDMJ5
Awardee CAGE Code
0FY55
Original Solicitation
Notice ID: 16d4b3d93a8e4db8ba86cfec0a30da81
Posted Date: Jul 9, 2024
Original Response Deadline: Not specified
More From This Vendor
Top 5 most recent
- $15.5MSigned Aug 6, 2026
- $15.5MSigned Jul 14, 2026
- $45.4MSigned Jul 1, 2026
- $15.0MSigned May 21, 2026
- $18.8MSigned Mar 18, 2026
Contacts
Documents
No documents available.
Lifecycle
Solicitation:
W9128F24R0045- Pre-Solicitation
- Solicitation
- Awarded
This opportunity has been awarded.
- 2×
- 6×SolicitationFeb 15, 2024
Fort Peck Outdoor Station Service Transformer B Install (Ft Peck, Montana)
- AwardedCurrentJul 9, 2024
Fort Peck Outdoor Station Service Transformer B Install (Ft Peck, Montana)
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
This contract was awarded on November 12, 2026 to Martin Brothers Construction for $26,711,770.00. | 59% | Awarded | Open |
Introduction: The U.S. Army Corps of Engineers, Japan District (POJ), is performing market research for an upcoming Design-Bid-Build (DBB) requirement entitled, “DLA DWCF B1907 Backup Power Generator, Yokosuka, Japan.". This announcement represents a market survey that is intended for planning purposes only. The purpose of this notice is to identify sources capable of performing this project and to receive responses from those firms to assist the Government's acquisition planning. This survey does not constitute a commitment by the Government for any follow-on announcements, solicitation, or award. This notice is NOT a solicitation. The Government will not pay for any information provided as a result of this market survey. This market survey is intended for local sources only. Local sources are those sources physically located and licensed to conduct business in Japan. Firms interested and capable of performing this work are highly encouraged to submit a response (submission requirements are located within this notice). We are committed to partnering with industry as much as we can throughout this process and therefore encourage all interested companies to respond to this sources sought. Market research and industry feedback is an essential part of the acquisition process. The information requested in this announcement will be used within POJ to facilitate decision-making and will not be disclosed outside the agency. However, respondents submitting business information pursuant to this announcement should consult 41 C.F.R. parts 105-60 and other implementing regulations concerning the release of such information to third parties under the Freedom of Information Act (FOIA). All information submitted by respondents that they consider confidential and not releasable to third parties outside of USACE, and its employees, agents, consultants, and representatives, must be clearly and conspicuously marked. SYSTEM FOR AWARD MANAGEMENT (SAM) All interested companies, including joint ventures, shall be registered in the SAM database in order to be eligible for award of Government contracts. https://www.sam.gov LOCAL SOURCES Firms which have not done business with U.S. Army Corps of Engineers, Japan Engineering District, are requested to visit the following website: https://www.poj.usace.army.mil/Business-With-Us/ for general information. This contract will be performed in its entirety in the country of Japan and is intended only for local sources. Only local sources will be considered under this solicitation. Local sources are sources (e.g. corporations, partnerships, or Joint Ventures [For a Joint Venture, the Joint Venture as an independent entity must satisfy the local source requirements or, in the alternative, each member of the Joint Venture must individually satisfy the local source requirements]) that are physically located in Japan and authorized (i.e. licensed and registered) to perform construction in Japan. Specifically, a prospective offeror must be duly authorized to operate and conduct construction business in Japan and must fully comply with all applicable laws, decrees, labor standards, and regulations of Japan during the performance of the resulting contracts. In addition, offerors must possess a Japanese civil construction (doboku isshiki koji) license or Japanese architectural construction (kenchiku isshiki koji) license by the proposal due date and time. The U.S. Government will verify that the offeror has the license through the Ministry of Land, Infrastructure, Transport and Tourism (MLIT) website at https://etsuran2.mlit.go.jp/TAKKEN. It is the responsibility of the offeror to ensure that it has the license (Japanese civil construction or Japanese architectural construction), and that it is accurately shown on the MLIT website, by the proposal due date and time. Failure to comply with this requirement will be cause for rejection of your offer. The U.S. Government will not offer “United States Official Contractor” status under Article XIV of the US-Japan Status of Forces Agreement (SOFA) to U.S. contractors normally resident in the United States; nor will the U.S. Government certify employees of such contractors as “Members of the Civilian Component” under Article I(b) of the SOFA. PROJECTS INFORMATION: Project Title: DLA DWCF B1907 Backup Power Generator Project Location: Yokosuka Japan Project FSC: Y1MZ - Construction of EPG (Electric Power Generation) Facilities—Other, Including Transmission Project NAICS: 237130 - Power and Communication Line and Related Structures Construction Project Magnitude: Between ¥500,000,000 and ¥2,000,000,000 (Japanese YEN) Project Description: Design-Bid-Build. Install a backup generator to support the mission at Building 1907. The new backup generator is expected to provide backup power to B1907 for the next 10 years at minimum. The generator has been sized to handle the following planned future loads: five new VLMs assumed to be rated the same as the existing VLMs(total of ~45 kW), operation of all four existing conveyor elevators (currently only two are operational at this time; two conveyors are fed from a 200A @ 210V, 3ph/3w feed), and an expected 20% increase in loads for the server rooms (total of ~20 kW). Anticipated Period of Performance: 518 Calendar Days Procurement Method: The Government intends to issue an Invitation for Bid (IFB) Solicitation. The Government anticipates that a solicitation will be issued approximately in May 2027. This survey does not constitute a commitment by the Government for any follow-on announcements, solicitation(s), or award(s). Any solicitation(s) pursued will be intended for local sources only. Local sources are those sources physically located and authorized to perform construction work in Japan. Draft plans and specifications are being provided for INFORMATIONAL PURPOSES. Offerors are cautioned that these drawings and specifications are in DRAFT FORMAT. ========================================================================== REQUESTED INFORMATION Interested firms are requested to reply with the following information no later than 11 December 2026 Japan Standard Time. Please submit your responses via e-mail to Mr. Ryan Marzetta, Contracting Officer at ryan.j.marzetta@usace.army.mil and Mr. Jiro Miyairi, Contract Specialist at jiro.miyairi@usace.army.mil Name of your company, address, phone number, email, SAM UEI, CAGE Code, and English Speaking Point of Contact (POC) name. Does your company have CMMC certification? If yes, what level and when does it expire. Identify your current construction bonding levels: a. Single Contract Amount b. Aggregate Maximum Contract Amoun c. Name of Sureties Identify which project(s) your firm is interested in and describe your firm's interest, capability and experience relative to the work described in the interested Project Description. Please provide at least one (1) project, but no more than three (3) projects, that is comparable to this project your company has completed (for government or commercial customers) in the past six (6) years. a. Project Title and Location b. Customer/Agency c. Project Value and Brief Description d. Date Completed or Percent Complete e. Your role (Prime, Subcontractor, Designer of Record, Joint Venture, etc) Technical Questions a. Does the Period of Performance seem reasonable? If not, provide what your company believes to be the Period of Performances (PoP) for the project. b. Are you expecting any long lead items? If so, which items and how long will it take to procure. c. Will a 1100 KVA package unit generator readily available in Japan. Will it need to be custom made? Do you have any other concerns related to the Draft technical specifications and drawings? Are there any other comments or suggestions that may increase your interest? Additional Info: U.S. Army Corps of Engineers, Japan District, Camp Zama, Japan Contracting Office Address: USACE District, Japan Attn: CEPOJ-CTN Unit 45010 APO, AP 96343-5010 Points of Contact: Jiro Miyairi 046-407-8837 jiro.miyairi@usace.army.mil Ryan Marzetta 046-407-8725 ryan.j.marzetta@usace.army.mil | 59% | Market Research | 12/11/2026 |
Amendment 0004 and RFI Set #4 Posted July 27, 2026***************************Amendment 0003 and RFI Set #3 has been uploaded on July 17, 2026*****************************************************************************The purpose of Amendment 2 is to extend the proposal due date to July 31, 2026 and make revisions to the solicitation. See the summary of changes on page 2 of Amendment 0002. Responses to RFI - Set #2 has been posted. ***********************************The purpose of Amendment 0001 is to extend the proposal due date to July 13, 2026 and make revisions to the solicitation. See the summary of changes on page 2 of the attached amendment. Due to the number of RFIs received, the USACE is still preparing responses and responses will be posted as soon as they are available. A select number of RFIs have been posted with this Amendment. ***************************************************************************************************************************************************************************************************This procurement will be conducted under PSC: Y1MG, NAICS: 237130. The size standard for this code is $45,000,000. This is a total Small Business Set Aside. All questions should be directed to the Contract Specialist, Nairi Freeman, nairi.freeman@usace.army.mil. Estimated Cost Range is between $10,000,000 to $25,000,000. FUNDS ARE NOT PRESENTLY AVAILABLE FOR THIS ACQUISITION. NO CONTRACT AWARD WILL BE MADE UNTIL APPROPRIATED FUNDS ARE MADE AVAILABLE. SEE FAR CLAUSE 52.232-18 AVAILABILITY OF FUNDS. RFP/Solicitation Number: W9123826RA016. Project Title: U.S. Army 63rd Readiness Division MILCON ERCIP Microgrid. Project Location: Mountain View, Santa Clara County, California. This project provides energy resilience for 14+ days for mission critical functions, utilizing renewable and fossil fuel energy sources. Installation of a microgrid system that will have full islanding capability. The microgrid system will incorporate a ground-mounted 750kW photovoltaic (PV) solar system with low voltage switchgear for building energy shifting; a 750kWh battery energy storage system (BESS); an 800kW diesel backup generation system, with a 10,000-gallon fuel storage tank. The microgrid system will include a master microgrid controller, and automatic smart switches controlling the generation resources within the Reserve Center. Microgrid will be installed on a closed restricted network (CRN) requiring an Authority to Operate (ATO) IAW DODI 8510.01. System cybersecurity requirements will be designed IAW UFC 4-010-06 Cybersecurity for Facility Related Control Systems. All proposals will be due on June 29, 2026, at 12:00PM PDT. The specific date and time is identified in the solicitation. OFFERORS ARE ADVISED THIS PROJECT MAY BE DELAYED, CANCELLED, OR REVISED AT ANY TIME DURING SOLICITATION, SELECTION, EVALUATION, AND/OR FINAL AWARD PROCESS. Plans and specs will not be provided in hard copy or CD format. NOTE: a) In preparation for prospective to submit offers when the RFP is issued, it is imperative that all prospective Offerors (including their subcontractors) be registered in the System for Award Management (SAM - www.SAM.gov) and the Procurement Integrated Enterprise Environment (PIEE) website in order to be able to view and download solicitation information, and to submit offers. b) Solicitation documents, plans, and specifications are only available to be download from PIEE, which may be accessed at https://wawf.eb.mil OR https://piee.eb.mil OR https://piee.eb.mil/xhtml/unauth/home/login.xhtml. c) Offers MUST BE submitted electronically through the PIEE website. d) Registration should be completed one (1) week prior to the anticipated solicitation release date. USACE will not notify Offerors of any changes to the solicitation; Offerors must monitor PIEE and SAM for the solicitation to be posted, and for any posted changes or amendments. e) See attachments - PIEE Solicitation Module Vendor Access Instructions-, -SOP PIEE Proposal Manager Offeror-, and -SOP PIEE Posting Offer- for instructions on getting access to the PIEE Solicitation Module and submitting Offeror proposals. | 59% | Solicitation | 07/31/2026 |
This procurement will be conducted under PSC: Y1MG, NAICS: 237130. The size standard for this code is $45,000,000. This is a total Small Business Set Aside. All questions should be directed to the Contract Specialist, Nairi Freeman, nairi.freeman@usace.army.mil. Estimated Cost Range is between $10,000,000 to $25,000,000. RFP/Solicitation Number: W9123826RA016. Project Title: U.S. Army 63rd Readiness Division MILCON ERCIP Microgrid. Project Location: Mountain View, Santa Clara County, California. This project provides energy resilience for 14+ days for mission critical functions, utilizing renewable and fossil fuel energy sources. Installation of a microgrid system that will have full islanding capability. The microgrid system will incorporate a ground-mounted 750kW photovoltaic (PV) solar system with low voltage switchgear for building energy shifting; a 750kWh battery energy storage system (BESS); an 800kW diesel backup generation system, with a 10,000-gallon fuel storage tank. The microgrid system will include a master microgrid controller, and automatic smart switches controlling the generation resources within the Reserve Center. Microgrid will be installed on a closed restricted network (CRN) requiring an Authority to Operate (ATO) IAW DODI 8510.01. System cybersecurity requirements will be designed IAW UFC 4-010-06 Cybersecurity for Facility Related Control Systems. The solicitation will be available on/about April 15, 2026, for viewing/downloading. All proposals will be due on/about May 15, 2026, at 12:00PM PDT. The specific date and time will be identified in the solicitation. OFFERORS ARE ADVISED THIS PROJECT MAY BE DELAYED, CANCELLED, OR REVISED AT ANY TIME DURING SOLICITATION, SELECTION, EVALUATION, AND/OR FINAL AWARD PROCESS. Plans and specs will not be provided in hard copy or CD format. NOTE: a) In preparation for prospective to submit offers when the RFP is issued, it is imperative that all prospective Offerors (including their subcontractors) be registered in the System for Award Management (SAM - www.SAM.gov) and the Procurement Integrated Enterprise Environment (PIEE) website in order to be able to view and download solicitation information, and to submit offers. b) Solicitation documents, plans, and specifications are only available to be download from PIEE, which may be accessed at https://wawf.eb.mil OR https://piee.eb.mil OR https://piee.eb.mil/xhtml/unauth/home/login.xhtml. c) Offers MUST BE submitted electronically through the PIEE website. d) Registration should be completed one (1) week prior to the anticipated solicitation release date. USACE will not notify Offerors of any changes to the solicitation; Offerors must monitor PIEE and SAM for the solicitation to be posted, and for any posted changes or amendments. e) See attachments - PIEE Solicitation Module Vendor Access Instructions-, -SOP PIEE Proposal Manager Offeror-, and -SOP PIEE Posting Offer- for instructions on getting access to the PIEE Solicitation Module and submitting Offeror proposals. | 59% | Pre-Solicitation | Open |
Presolicitation Notice TITLE: FTG247 Replace UPS at IDT1, Fort Greely, Alaska Identify set aside type PSC Code: Y1BF – Construction of Missile System Facilities NAICS Code: 237130 – Power and Communication Line and Related Structures Construction Solicitation Number: W911KB25R0032 Description: This is a pre-solicitation notice for a total small business set aside Request for Proposal (RFP) to replace the existing 80KVA Uninterruptable Power Systems (UPSs) with distributed redundant 75 Kilovolt-Ampere (KVA) UPSs. New UPS panelboards will be added to allow for redundant receptacles for all the mission equipment within the High-Altitude Electromagnetic Pulse (HEMP)-shielded equipment room. Emergency Power Off (EPO) will be upgraded to the latest MDA GMD standards. Power Control and Monitoring System (PCMS) and Power Quality Monitoring System (PQMS) will also be extended into IDT1 from the Fort Greely Power Plant (FPP).The estimated dollar magnitude of this project is anticipated between $1,000,000 and $5,000,000. The performance period will be approximately 540 calendar days. The procurement will be conducted using source selection procedures and the award will be based on best value tradeoff source selection procedures, considering the price and non-price factors cited in this announcement and the solicitation. All Offerors must be registered in the System for Award Management (SAM) (https://www.sam.gov/SAM/). Joint ventures must be registered in SAM as the joint venture. Offerors are advised to begin this process when they prepare their proposal in order to ensure this registration is in place should they be selected for the award. Lack of registration in the SAM database will make an Offeror ineligible for award. Anticipated NTP: 13 June 2025 with a 540 calendar-day period of performance; the Davis Bacon Act will apply. (1) PROJECT INFORMATION: Replacethe existing 80KVA Uninterruptable Power Systems (UPSs) with distributed redundant 75 Kilovolt-Ampere (KVA) UPS at Fort Greely, Alaska. (2) SELECTION CRITERIA: Evaluation criteria to be listed in the solicitation are anticipated to be: Factor 1 – Past Performance (Confidence Assessment) Factor 2 – Technical Approach Factor 3 – Summary Milestone Schedule Factor 4 – Price and Pro Forma Information (3) OBTAINING THE SOLICITATION: The solicitation for this project will be provided in electronic format only and is currently scheduled to be available for download on or about 31 March 2025 at the PIEE Solicitation Module website at https://piee.eb.mil/sol/xhtml/unauth/index.xhtml via Solicitation number (W911KB25R0032). Any future amendments to the solicitation will also be available for download from this website. All responsible sources may submit an offer which will be considered by the agency. All notifications of changes to this solicitation shall be made through the internet only. It is the Offeror’s responsibility to check for any posted changes to this solicitation. NOTE: Electronic proposal submissions will only be accepted via the PIEE Solicitation Module website at: https://piee.eb.mil/sol/xhtml/unauth/index.xhtml. IN ORDER TO SUBMIT A PROPOSAL, VENDORS MUST REGISTER IN THE PIEE SYSTEM AND MUST HAVE A PROPOSAL MANAGER ROLE ESTABLISHED. ADDITIONAL INFORMATION REGARDING PROPOSAL MANAGER, PROPOSAL MANAGER FUNCTIONS AND POSTING OFFERS CAN BE FOUD AT https//pieetraining.eb.mil/wbt/xhtml/wbt/sol/solicitation/proposals.xhtml | 58% | Pre-Solicitation | 12/12/2026 |
Additional Details
Solicitation Number
W9128F24R0045
Archive Date
Jul 19, 2024