Notice ID: ff6ebd27df6342c7afe1dd0fd0bcd4ccSolicitation
Chief Joseph Dam Powerhouse Sump Pumps and Controls
Archived on October 3, 2025. Original response deadline: . Full description on SAM.gov.
Overview
- Response deadline
- 10:00 AM UTC−08:00
- Posted
- October 3, 2024
- Notice type
- Solicitation
- NAICS
- 237990: Other Heavy and Civil Engineering Construction
- Agency
- Department of WarDepartment of the Army
Notice details
- Office
- W071 ENDIST SEATTLE
- Place of performance
- Bridgeport, WA
- Last updated
- Dec 6, 2025
Identifiers
- Solicitation number
- W912DW24R0025
- Notice ID
- ff6ebd27df6342c7afe1dd0fd0bcd4cc
Description
OVERVIEW: The U.S. Army Corps of Engineers (USACE), Seattle District, requires rehabilitation of the Chief Joseph Dam Powerhouse drainage and unwatering sump, pumps, motors, and controls. The work includes replacement of piping and valves, installation of new pumps, controls and removal of the existing pumps and controls. Incidental work includes replacement of a jib hoist, installation of a monorail hoist, replacement of sump lighting, and improvements to the sump access, including removal of existing and installation of new ladders, platforms, and hatches. The following is a list of the major items of work included in the scope of work. The work includes but is not limited to the following modifications to the existing components and systems:General Work1. Mobilization and Demobilization2. Demolish Pumps and Piping3. Demolish Control Systems and Breakers4. Demolish platforms, ladders, hatches, concrete, and structural systems for the tailrace discharge valve, drainage sump access, unwatering sump access, pump discharge valve support catwalk, and dry sump discharge valve access. 5. Clean unwatering pipes and dispose of waste material.6. Clean sump and dispose of waste material.Mechanical Systems Work1. Design, fabrication, installation, and testing of three 75HP vertical turbine pump assemblies including motor, mounting, sole plate and grout pad, vacuum breaker, packing gland, column shafting, bowls, and impellers.2. Replace isolation and check valves, piping, and pipe connections in both the dry and wet sumps.3. Design, fabrication, installation and testing of submersible pump cross sump transfer system including rail mounting system. 4. Install monorail and hoist for supporting access and maintenance to the cross-sump transfer.5. Replace dry sump drainage system including piping and a submersible pump.6. Replace 16? flow control piping and supports in unwatering sump.7. Remove and replace jib hoist and associated equipment and systems to uprate capacity.Controls Work1. Supply, Installation and commissioning of comprehensive pump control systems including relays, terminal blocks, and circuit breakers, soft starters, ultrasonic level sensors, resistance temperature detectors, machine condition monitoring, and float switches for new pumps, equipment, and systems.Structural Work:1. Design, Fabricate, Install platforms, ladders, hatches, foundations, and structural systems. 2. Furnish all labor, equipment, and materials to design and provide seismic restraints for new systems and equipment. 3. Concrete coring for new pipes through existing sump walls.The magnitude of this construction contract cost is between $5,000,000 and $10,000,000. A Request for Proposal (RFP) will be issued to interested contractors using the Best Value Trade-off (BVTO) method for trade-offs between non-price factors and price. The resulting contract will be a Fixed-Price Contract, representing full payment for the clearly defined work. Please refer to attached solicitation for complete details.
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Contracting Officer
Primary Contact
Secondary Contact
Documents
No documents available.
Lifecycle
Solicitation:
W912DW24R0025- Pre-Solicitation
- Solicitation
Award typically follows within 30–90 days after the response deadline. (estimate)
- Pre-SolicitationJul 2, 2024
Pre-solicitation-Chief Joseph Dam Powerhouse Sump Pump and Controls
- 7×SolicitationCurrentJul 23, 2024
Chief Joseph Dam Powerhouse Sump Pumps and Controls
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
CHJ 480V _ SQ1_SQ3_ DSQ1_DSQ2_Rep. Amend 0001 - 1. Update the solicitation number from W912DW26RA053 to W912DW27RA020 on Chief Joseph 480V SQ1 - SQ3, DSQ1 - DSQ2 Replacement Drawings and Chief Joseph 480V SQ1 - SQ3, DSQ1 - DSQ2 Replacement Specs. 2. Add Request for Visitation Authority (RVA). | - | Solicitation | 12/18/2026 |
THIS PROJECT WILL ADD NEW SECURITY BARRIERS (FENCE, GATE,) FOR ADDITIONAL PERSONNEL SAFETY AND PROJECTSECURITY.THE CONTRACTOR SELECTED TO PERFORM THIS WORK WILL BE REQUIRED TO PERFORM WORK TO INCLUDE:. CONCRETE SAW CUTTING FOR ELECTRICAL UNDERGROUND TRENCH.. SIDEWALK CONCRETE DEMOLITION AND NEW SIDEWALK CONCRETE. MISCELLANEOUS CONCRETE FOOTINGS. INSTALLATION OF MISC BOLLARDS. SELECT FENCE DEMOLITION. ASPHALT REPAIR- REMOVE EXISTING VEHICULAR SWING GATE AND INSTALL MOTOR-OPERATED CANTILEVERED GATE- INSTALL FENCE AND PEDESTRIAN GATE AROUND BASE OF EXISTING EXTERIOR STAIRCASE.- INSTALL, RIGID METALLIC CONDUIT AND UNDERGROUNDSCH40 PVC CONDUIT, AS SHOWN IN THE PLANS | - | Combined Synopsis | 06/09/2026 |
Amendment 0003: See attached amendment and related document for complete details. Amendment 0002: See attached amendment and related document for complete details. Amendment 0001: See attached amendment and related document for complete details. Chief Joseph Dam Station Service Exciters. Project Location: Bridgeport, WA. The solicitation is an unrestricted full and open competitive acquisition. NAICS 237990 Other Heavy and Civil Engineering Construction. Small Business Size Standard $45,000,000. Disclosure of the magnitude of construction project: Between $1,000,000 and $5,000,000. This solicitation is utilizing the Trade-off process procurement method as described in Federal Acquisition Regulation (FAR) Part 15 to award a firm fixed-price (FFP) contract. Please refer to the attached solicitation document, specifications, drawings, and attachments for details. | - | Solicitation | 05/07/2026 |
EVENT DETAILS: Date: 3 December 2026 Time: 0930-1430 PT Format: Presentation & Site walk Registration Due Date: 23 November 2026, 1200 PT; Please register by returning completed Request for Visit Authority (RVA) by email to: Sarah Malowicki, Project Manager, at sarah.m.malowicki@usace.army.mil, AND Londres Medranda, Contract Specialist, at londres.medranda@usace.army.mil. Confirmation email will be sent upon receipt of completed RVA. Who Should Attend: Interested vendors, including small businesses, large businesses, and other industry partners. Attendance is limited to 2 personnel per company. Attendance is limited to United States Citizens. Attendance at this event is not mandatory. Pre-registration is required. DESCRIPTION: In accordance with the Revolutionary Federal Acquisition Regulation Overhaul (RFO) 15.101(a) Early exchanges with industry, the United States Army Corps of Engineers (USACE), Seattle District (NWS) is hosting an Industry Day on 3 December 2026 at Chief Joseph Dam in Bridgeport, Washington. This Industry Day provides an opportunity for interested parties to inspect the existing 15.5KV Main Unit XJ Breaker disconnects first-hand. By hosting this first-hand inspection, the government aims to gather technical feedback and explore industry alternatives for modernizing this equipment. We are seeking input from qualified, experienced sources, capable of performing this modernization work. PROJECT BACKGROUND: At Chief Joseph Dam the current Unit 1-16 XJ Breaker disconnects are original BBC (Brown Boveri Corporation) equipment and rated 6000A according to the BBC shop drawings. The switch operators are pneumatically driven, and are actuated by operation of a complex key interlocking scheme with the circuit breaker. The load side and source side disconnects are mechanically linked and simultaneously operated by a single shared pneumatic actuating system. The current Units 17-27 breaker disconnects are original GE equipment. The load side and source side disconnects are mechanically linked and simultaneously controlled by mechanically operated hand crank. USACE is evaluating options to improve reliability, maintainability, remote-operating capability, and overall generating-unit availability. • Option 1: Refurbish and restore existing disconnect switches to an approved condition equivalent to original design intent, as technically feasible. Integrate motorized mechanisms on the switch arms to enable remote operation, and comprehensively overhaul and test the existing main unit breakers to ensure optimal system protection. • Option 2: Replace the disconnect switches with new electrically operated units and refurbish the existing breakers. • Option 3: Replace both the disconnect switches (with new electrically operated units) and the main unit circuit breakers. • Option 4: Replace the entire switchgear assembly with new enclosures, modern electrically operated disconnect switches, and new circuit breakers (includes associated controls, protection, buswork and new enclosure). Chief Joseph Dam has several critical limitations that affect this project, primarily related to space constraints. This Industry day will present the options under consideration, obtain industry feedback on technical feasibility and constructability, and identify potential risks, constraints and cost drivers. USACE is requesting feedback on the following questions and relevant, non-binding information: Does your company have the ability, capacity, interest and willingness to perform the proposed options? Does your company have experience with comparable medium-voltage/high-current generation-station disconnect and breaker modernization projects? We are not currently requiring quotes or bids, however rough estimates would be greatly appreciated. Recommended technical approaches or alternatives Major schedule outage, access, safety, supply-chain or constructability risks. Do you believe all aspects of this requirement could be successfully performed by the small business sector under NAICS 237990 (Size standard $45M)? (Yes/No). If No, what estimated percentage do you think can be subcontracted out to small business? Small Business (SB) ______% Small Disadvantaged Business (SDB) ________% Woman-Owned SB (WOSB) _______% Veteran Owned SB (VOSB) _______% Service Disabled VOSB (SDVOSB) _______% Historically Underutilized Business Zone (HUBZone) _______% Important Notice: Attendance and participation is not required for consideration on future contracts related to this work. The U.S. Government is not obligated to pay for any information, documentation, demonstrations, or data provided, nor will it reimburse any costs incurred by your organization in preparing responses, traveling to, or participating in this Industry Day and physical equipment inspection. All costs associated with attending this event and participating in this information exchange are solely at the responding party’s expense. Small Business Program Inquiries: Enshane Hill-Nomoto: Enshane.Nomoto@usace.army.mil https://www.nws.usace.army.mil/Business-With-Us/Small-Business/ Thank you for your interest in this USACE project. | - | Special Notice | 11/23/2026 |
The U.S. Army Corps of Engineers (USACE), Walla Walla District, is seeking information from interested business concerns capable of performing a construction project entitled Mill Creek Section 205 Flood Risk Management Improvements. The work is located in and near the Cities of Walla Walla and College Place, Walla Walla County, Washington. The Mill Creek Flood Control Project begins approximately two miles east of downtown Walla Walla and extends approximately seven miles downstream near College Place at the Gose Street Bridge. One hundred percent performance and payment bonds will be required. In accordance with RFO FAR Clause 52.228-1, a bid guarantee will also be required. The estimated magnitude of construction is between $10,000,000 and $25,000,000. The anticipated North American Industry Classification System (NAICS) code is 237990, Other Heavy and Civil Engineering Construction, with a corresponding small-business size standard of $45,000,000 in average annual receipts. This sources-sought notice is issued for market-research purposes only to identify business concerns with the capability to perform work of this nature, magnitude, and complexity. THIS IS NOT A SOLICITATION FOR BIDS OR PROPOSALS. This notice does not constitute a commitment by the Government to issue a solicitation or award a contract. The Government will not reimburse respondents for costs associated with preparation or submission of responses. Responses will be used to assist the Government in determining the appropriate acquisition strategy, including whether a small-business set-aside is appropriate. Interested business concerns should submit the following information: 1. Capability Statement. Provide a statement expressing interest in this requirement and describing the firm's capability to perform work of the anticipated magnitude and complexity. Identify special qualifications, certifications, key personnel, self-performance capabilities, equipment, and any proposed teaming arrangements relevant to the summary scope of work. 2. Relevant Experience. Provide at least three projects completed within the past seven years that are similar in scope, complexity, and magnitude. For each project, provide: -- Project title and location; -- Customer/owner; -- Contract value; -- Period of performance; -- Brief description of the work performed; -- The firm's role, including prime contractor, joint-venture member, or subcontractor; -- Major work self-performed by the firm; and -- Point of contact, including name, title, telephone number, and email address. 3. Bonding Capacity. Provide the firm's single-project bonding capacity and aggregate bonding capacity. 4. Business Size and Socioeconomic Status. Identify the firm's business size under NAICS 237990 and any applicable socioeconomic designations, including small business, Small Disadvantaged Business, 8(a), Historically Underutilized Business Zone (HUBZone) small business, Woman-Owned Small Business, Veteran-Owned Small Business, and Service-Disabled Veteran-Owned Small Business. 5. SAM Registration. Provide the firm's Unique Entity Identifier (UEI) and confirm whether its System for Award Management registration is active. Submit responses by email to: Chandra Crow, Contract Specialist U.S. Army Corps of Engineers, Walla Walla District Email: Chandra.D.Crow@usace.army.mil Responses are due no later than 3:00 p.m. Pacific Time, December 4, 2026. Summary of Scope of Work: The Mill Creek Flood Control Project provides flood-risk management for the City of Walla Walla and adjacent areas in Walla Walla County, Washington. The project includes upstream channel, concrete channel, and downstream channel sections. The anticipated construction work includes flood-risk-management improvements and repairs at multiple locations along and within the upstream and downstream Mill Creek channel sections. Work may include: -- Raising existing levees by up to approximately three feet at five locations; -- Landward enlargement of levees while maintaining 2H:1V side slopes; -- Placement of additional gabion revetment at one location; -- Placement of additional riprap at transition areas, including ramp-to-levee and levee-to-bridge-abutment transitions; -- Construction of new concrete walls and/or raising of existing concrete walls at levee and bridge-transition locations; -- Construction of a concrete access ramp; -- Removal of trees and vegetation along the landside levee toe; -- Removal and in-kind replacement of existing fencing, as necessary to perform the work; -- Removal of a ceiling section in a covered portion of the existing concrete channel; -- Reinforcement of an existing timber-plank-covered support wall within the channel below an existing building; and -- Stabilization of two existing concrete-channel-wall sections using soil anchors and shotcrete facing. Work will occur on Federal and non-Federal/private property. The anticipated project may require work-site access planning, coordination with affected property owners and utilities, traffic control, in-kind replacement of fencing and utilities as required, and work within or adjacent to the active channel. The project is intended to improve Mill Creek system capacity by raising levees in low-assurance areas and to improve system reliability by repairing and reinforcing the concrete channel through downtown Walla Walla. Desired Contractor Capabilities: Interested firms should demonstrate experience with comparable civil-works construction, including: -- Levee raising, embankment construction, earthwork, compaction, and slope construction; -- Cast-in-place concrete work for new walls, wall raises, and access ramps; -- Concrete repair, concrete-channel rehabilitation, and structural concrete demolition; -- Gabion revetment and riprap placement; -- Soil-anchor installation, testing, and shotcrete application; -- In-channel or near-channel construction, including water-control/diversion measures and work-window planning; -- Temporary works, shoring, and protection of existing structures during construction; -- Utility protection, relocation, and restoration; -- Traffic control and maintenance of public, property-owners, and emergency access; -- Concurrent management of multiple construction sites; and -- Planning and providing safe access to constrained work areas through cranes, temporary access systems, or other appropriate means. | - | Market Research | 12/07/2026 |
Additional Details
Solicitation Number
W912DW24R0025
Archive Date
Oct 3, 2025