GovChime
Notice ID: 2e1876cc4e7184e466d4c0bcf11e07ccAward NoticeAwarded

Z--City of Emmett, Idaho Levee Rehabilitation Award

Awarded on March 28, 2013. Full description on SAM.gov.

Awarded tounder W912EF-13-P-5043 (source: SAM.gov award notice)• $20.5K

Overview

Posted
April 2, 2013
Notice type
Award Notice
Agency
Department of WarDepartment of the Army

Notice details

Office
US ARMY ENGINEER DISTRICT WALLA WAL
PSC
Z: MAINT, REPAIR, ALTER REAL PROPERTY
Last updated
Dec 5, 2025
Award date
Mar 28, 2013
Award amount (SAM.gov award notice)
$20.5K

Identifiers

Solicitation number
W912EF13Q0066
Notice ID
2e1876cc4e7184e466d4c0bcf11e07cc
Award number (PIID)
W912EF-13-P-5043

Description

City of Emmett, Idaho Levee Rehabilitation

Full description on SAM.gov

Award Overview

Award Number

W912EF-13-P-5043

Award Amount (SAM.gov award notice)

$20.5K

Award Date

Mar 28, 2013

Awardee

Original Solicitation

Notice ID: 2e1876cc4e7184e466d4c0bcf11e07cc

Posted Date: Apr 2, 2013

Original Response Deadline: Not specified

Contacts

Contracting Officer

Primary Contact

Connie Cochran, 509-527-7216 USACE District, Walla Walla

Documents

No documents available.

Lifecycle

Solicitation:W912EF13Q0066
  1. Awarded

This opportunity has been awarded.

  1. AwardedCurrentApr 2, 2013

    Z--City of Emmett, Idaho Levee Rehabilitation Award

    Notice 2e1876cc4e7184e466d4c0bcf11e07cc on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline
Heise-Roberts Right Bank Upper System Damage Site # 1 ? This site is located on the right bank levee system approximately 1 mile upstream of Lorenzo Bridge. At this levee segment, the river is eroding the streambank to the point of encroaching on the toe of the levee. This levee segment is not armored with riprap. The levee needs riprap revetment to protect the toe and slope of the levee prior to the next flood event. Excavating down approximately 8? to the toe of the levee and armoring the levee with riprap on the riverside side of the levee is necessary to protect the levee from eroding. This site is approximately 600 linear feet in length.Heise-Roberts Right Bank Upper System Damage Site # 2 ? This site is located on the right bank levee near Lorenzo Bridge. At this levee segment the large, dumped stone upstream of the railroad bridge abutment has been undercut and washed downstream. Additional riprap is needed to key in the remaining riprap and protect the toe of the levee and areas of erosion on the slope of the levee. This site is approximately 600 linear feet in length.Heise-Roberts Right Bank Lower System Damage Site # 3 ? This site is located on the right bank levee system near Roberts Bridge. This site has experienced erosion at the toe of slope, and the riprap has slid down the slope of the levee, leaving the upper levee exposed to erosion. Riprap revetment would need to be keyed in with existing riprap to protect the upper part of the levee and existing riprap needs to be keyed in to create a stable toe. This site is approximately 300 linear feet in length.Heise-Roberts Left Bank Levee System Damage Site # 4 - This site is located on the left bank levee system, approximately 1.5 miles downstream of Lorenzo Bridge. This site is at an impingement point that eroded a large amount of riverbank that was repaired during a flood fight. A Riprap toe bench needs to be placed and keyed in with the existing slope riprap revetment placed during previous flood fight conditions. This site is approximately 600 linear feet in length.
76%
Market Research06/04/2026
THIS IS A SOURCES SOUGHT NOTICE. THIS IS FOR MARKET RESEARCH PURPOSES ONLY. This is NOT a solicitation. This is not a Request for Bid, Proposal, or Quote. It does not constitute a solicitation and shall not be construed as a commitment to the Government. NO SOLICITATION OR ATTACHMENTS are available for this notice. Responses in any form are not offers and the Government is under no obligation to award a contract as a result of this announcement. No funds are available to pay for preparation of responses to this announcement. No reimbursement will be made for any costs associated with providing information in response to this survey. Any information submitted by respondents to this Sources Sought notice is strictly voluntary. Responses will not be returned to the responder. Not responding to this notice does not preclude participation in any future Request for Quote (RFQ), Invitation for Bid (IFB) or Request for Proposal (RFP), if any are issued. This survey is for market research purposes only. Only contractors capable of performing this type of work should respond to this notice. INTRODUCTION The U.S. Army Corps of Engineers (USACE), Detroit District, is issuing this Sources Sought notice and conducting market research as a means to identify interest and capabilities of both small and large business entities to provide design and construction services for the Davis Building Rehabilitation project located at the Soo Locks Complex in Sault Sainte Marie, Michigan. The information collected will be used to help determine the appropriate strategy to solicit and award the project. BASED ON THE RESPONSES TO THIS SOURCES SOUGHT NOTICE/MARKET RESEARCH, THIS REQUIREMENT MAY BE SET-ASIDE FOR SMALL BUSINESSES (IN FULL OR IN PART) OR PROCURED THROUGH FULL AND OPEN COMPETITION. All small business set-aside socioeconomic categories will be considered. Telephone inquiries will not be accepted or acknowledged, and no feedback or evaluations will be provided to companies regarding their submissions. REQUIREMENT* for the Davis Building Rehabilitation project Summary Scope: The contractor will provide all materials, labor, equipment, supervision, and administration as necessary for repairs, rehabilitation, and construction to the historic Davis Pump Well Building located at the Soo Locks in Sault Sainte Marie, MI. The historic building was built in the early 1900s and is located on the island between the Poe Lock and the Davis Lock (now the New Lock currently in construction). Referenced picture of the Davis Building attached to this notice. Primary purpose of the building was to facilitate the dewatering of the locks for regular operations, but pumps are now decommissioned and removed due to construction of the New Lock. The facility is intended to be repurposed to facilitate up to 50 maintenance personnel including, but not limited to, locker rooms, break rooms, kitchen/laundry and staff offices. The Davis Building currently provides approximately 4,200 square-feet of ground floor office space with approximately 4,200 square-foot of basement that houses mechanical and electrical systems. Due to project location, barge-based transportation and load handling equipment will be required. The schedule is estimated to take 36 months, which includes up to 12 months for design and 24 months for construction. Project will include but is not limited to the following: Repair or replace deteriorating clips holding the limestone fascia to the building. Design and implement a water mitigation plan to manage stormwater runoff from roof downspouts and prevent moisture intrusion in the basement. Replace all windows and doors. Design and construct a new subterranean locker room in place of the existing pump well access ramp that is no longer needed and complete all necessary earthwork, backfill, structural compaction, and surface grading to eliminate the ramp opening and restore surface elevations flush with surrounding grade. Construct a mezzanine level above the first-floor office space (within the first-floor footprint) to accommodate additional locker room space. Reconfigure existing restrooms to maximize utilization. Upgrade all mechanical, electrical, and IT systems to accommodate building occupancy, usage, and security. Install fire alarms and suppression system. NOTE: Lead and asbestos abatement is anticipated as part of this project. *Please note the description of the requirement is subject to change. The North American Industrial Classification System (NAICS) code is anticipated to be 237990 - Other Heavy and Civil Engineering Construction, which has a small business size standard of $45M in average annual receipts. Place of Performance: Sault Ste. Marie, Chippewa County, MI Both Large and Small Business firms who are interested are encouraged to respond to this Sources Sought Notice. Responses to this Sources Sought Notice will be used by the Government to make appropriate acquisition decisions. Anticipated Solicitation: Winter 2026 Anticipated Period of Performance: 36 Months SOURCES SOUGHT RESPONSES If your organization has the potential capacity and capability to perform this type of work, please complete the attached questionnaire and submit via email to Contract Specialist, Joseph Orlando at joseph.orlando@usace.army.mil and Contracting Officer, Lisa May at lisa.m.may@usace.army.mil no later than November 12, 2026 at 2:00 PM (Eastern). Please reference in the subject line "SOURCES SOUGHT Davis Building Rehabilitation” All data received in response to this Sources Sought that is marked or designated as corporate or proprietary will be fully protected from any release outside the Government. The Government is not committed nor obligated to pay for the information provided, and no basis for claims against the Government shall arise as a result of a response to this Sources Sought notice. RESPONDENTS WILL NOT BE CONTACTED REGARDING THEIR SUBMISSION OR INFORMATION GATHERED AS A RESULT OF THE SOURCES SOUGHT NOTICE.
72%
Market Research11/12/2026
Sources Sought for St Francis Town Levee Renovation, St Francis, AR SEE ATTACHMENTS FOR MORE INFORMATON
72%
Market Research11/23/2026
69%
Solicitation11/20/2026
The U.S. Army Corps of Engineers, Enterprise Dredge Delivery Center (EDDC) requires a contract to provide maintenance dredging for (3) dredging projects. The areas of consideration for these dredging services are: Calcasieu Bar River Channel, Pascagoula Harbor, and Panama City Harbor. Calcasieu River Bar Channel: Work for the Calcasieu River Bar Channel will require one fully crewed and equipped self-propelled trailing suction type hopper dredge. The dredge must have the capability to dredge maintenance material up to a depth of -45ft MLLW and place dredged material into the Ocean Dredge Material Disposal Sites (ODMDS).Pascagoula Harbor: Work for the Pascagoula Harbor maintenance dredging will require a hopper dredge. The dredge must have the capability to dredge maintenance material up to a depth of -46 ft MLLW and place dredged material in the Ocean Dredge Material Disposal Site (ODMDS). Dredged material shall be placed within Pascagoula ODMDS. The transport distance to the designated placement area varies depending on dredge assignment but typically is within 3-5 miles of the dredge cut. Panama City Harbor: Work for the Panama City Harbor maintenance dredging will require a medium to small hopper. The dredge must have the capability to dredge maintenance material up to a depth of -40 ft MLLW and place dredged material within channel adjacent to the entrance jetty. Dredged material shall be placed within the channel adjacent to the jetty. The transport distance to the designated placement area varies depending on dredge assignment but typically is within one mile of the dredge cut. The Contractor shall commence dredging no later than 30 January 2027 in Calcasieu River Bar Channel. The order of work is as follows: (1) Calcasieu River Bar Channel, (2) Pascagoula Harbor, (3) Panama City Harbor. This solicitation is unrestricted. The contract issued will be Firm Fixed Price. This solicitation will be issued in electronic format only and will be available on or about 23 October 2026. The bid opening date will be specified in the solicitation when it is issued. No additional media (CD-ROM, floppy disks, facsimiles, etc.) will be provided. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored. The North American Industry Classification System (NAICS) code is 237990, Other Heavy and Civil Engineering Construction and the size standard is $37,000,000.00. Offerors must be registered in the System for Award Management (SAM) in order to be eligible to receive an award from any Government solicitation. Call 1-866-606-8220 for more information or visit the SAM website at www.sam.gov. After completing SAM, in order to download documents contractors and their subcontractors must register at www.sam.gov. In order to locate solicitation, Contractors can go to www. sam.gov and search for the solicitation number. Contractors can register to be put on a plan holders list that others can access through the www.sam.gov website. It is the Offerors responsibility to check the Internet address provided as necessary for any posted changes to this solicitation and all amendments. For additional information or assistance, please contact Cori Caimi, Contract Specialist, email cori.a.caimi@usace.army.mil or Rosalind Shoemaker, Contracting Officer, phone (910) 251-4436, email rosalind.m.shoemaker@usace.army.mil.
68%
Solicitation12/07/2026

Additional Details

Solicitation Number

W912EF13Q0066

Archive Date

May 2, 2013