Notice ID: 30ad258761ee43d4ad2d3eb4adbdccb1Special Notice
Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-1
Archived on March 30, 2021. Original response deadline: . Full description on SAM.gov.
Overview
- Response deadline
- 10:00 AM UTC−05:00
- Posted
- March 4, 2021
- Notice type
- Special Notice
- Set-aside
- Small Business Set Aside - Total
- Agency
- Department of WarDepartment of the Army
Notice details
- Office
- W07V ENDIST ST PAUL
- Last updated
- Sep 25, 2026
Identifiers
- Solicitation number
- W912ES21B0005
- Notice ID
- 30ad258761ee43d4ad2d3eb4adbdccb1
Description
Abstarct of Bids
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Contracting Officer
Primary Contact
Scott E. Hendrix
Secondary Contact
Kevin P. Henricks
Documents
No documents available.
Lifecycle
Solicitation:
W912ES21B0005- Pre-Solicitation
- Solicitation
- Pre-SolicitationDec 3, 2020
Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-1
- 6×SolicitationJan 15, 2021
Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-1
- Special NoticeCurrentMar 4, 2021
Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-1
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
This is a Sources Sought/Request for Information only. This is NOT a Solicitation Announcement, nor is it a Request for Proposal. This request does not obligate the Government in any contract award. The U.S. Army Corps of Engineers, Wilmington District, is conducting research to determine the market capabilities of potential contractors to perform Coastal Storm Risk Management. The area of consideration for this dredging service is: Surf City, Pender County, North Carolina. CSRM Estimated Quantity: 6,500,000 CY. Environmental Window: N/A. The work consists of furnishing plant, labor, materials, and equipment to perform dredging, transporting, placing and shaping beach fill and performing all pre and post construction beach surveys. Approximately 1 borrow areas is available for the project and located offshore of Topsail Island Beaches at the south end of the island. The Surf City Coastal Storm Risk Management Project consists of placing 6,500,000 CY of Dune and Berm beach fill along approximately 33,300 LF of Surf City Beach. This project shall use either an ocean certified hopper and/or an ocean certified pipeline dredge. The project also consists of extending approximately 40 existing walkover structures in Surf City and the stabilization of approximately 46 to 56 acres of new dune. The solicitation is expected to be available in FY2027.See the attached document with additional details. | 68% | Market Research | 07/17/2026 |
The US Army Corps of Engineers, Wilmington District, is soliciting comments from the construction community addressing the potential use of Project Labor Agreements (PLA) for a large-scale construction project (exceeding $35 million) within the Surfy City, North Carolina area. This procurement is for Coastal Storm Risk Management (CSRM) for Surf City, North Carolina. The work consists of furnishing plant, labor, materials, and equipment to perform dredging, transporting, placing and shaping beach fill and performing all pre and post construction beach surveys. Approximately 1 borrow areas is available for the project and located offshore of Topsail Island Beaches at the south end of the island. The Surf City Coastal Storm Risk Management Project consists of placing 6,500,000 CY of Dune and Berm beach fill along approximately 33,300 LF of Surf City Beach. This project shall use either an ocean certified hopper and/or an ocean certified pipeline dredge. The project also consists of extending approximately 40 existing walkover structures in Surf City and the stabilization of approximately 46 to 56 acres of new dune. The solicitation is expected to be available in FY2027. See the attached document with additional details. | 66% | Special Notice | 07/17/2026 |
66% | Awarded | Open | |
Market Survey Background Information The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of the New York and New Jersey Harbor – Arthur Kill 50 foot Reach Federal Navigation Project to a depth of -50 feet Mean Lower Low Water (MLLW) plus 1 foot of allowable over-depth. The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of material from the critical shoal area. The dredged material would be dredged and subsequently placed at a suitable, contractor provided, state permitted upland placement site(s). The dredged material is expected to consist primarily of silt, clay, and some sand. Based on the past dredging projects within the New York Harbor, and anticipated restrictions found in the New York State Department of Environmental Conservation Water Quality Certificate, the proposed work can only be performed by utilizing a mechanical clamshell dredge with environmental bucket. Additionally, tug-boats, sealed hull barges and survey vessels will be needed to perform the work during the dredging, transport, processing and placement activities. The dredging, transport and placement at a suitable, contractor provided, state permitted upland placement site(s) would be required to meet all federal, state, and local criteria required by the government agencies having jurisdiction where the dredging and placement sites are located. All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the Notice to Proceed and maintain an integrated production rate of at least 3,000 cubic yards per calendar day for the dredging and placement of the dredged material. The presence of the dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact. The proposed work is anticipated to take place in the summer / fall of 2027. SURVEY OF THE DREDGING INDUSTRY The following confidential survey questionnaire is designed to apprise USACE of prospective dredging contractors’ project execution capabilities. Please provide your response to the following questions. All questions are in regard to the Arthur Kill 50 foot Reach maintenance dredging project. General 1. Have you ever worked on dredging jobs similar in nature to this project? If so, please describe the project and for whom the work was performed. Identify a point of contact and phone number, as a reference of relevant experience. 2. Have you performed dredging within the waters of the Port of New York and New Jersey? 3. Do you have experience with the placement of dredged material at a suitable, contractor provided, state permitted upland placement site? Please list your experience. 4. What percentage of work (volume of material dredged, transported, processed and ultimately placed) can you perform with your own equipment or equipment owned by another dredging contractor? 5. Would you be willing to bid on the project previously described? If the answer is No, please explain why not. 6. Would you be bidding on this project as a sole contractor, prime contractor with subcontractor(s) or as a joint venture? 7. Is there a dollar limit on the size of contract that you would bid? If so, what is that limit? 8. What is the largest dredging contract, in dollars, on which you were the prime contractor? 9. What is your bonding capacity per contract? What is your total bonding capacity? 10. Do you have experience using USACE Resident Management System (RMS) 3.0 for delivering Submittals, Daily Dredging Reports and Pay Estimates? 11. In the event that the USACE transitions from Resident Management System (RMS) to an alternative construction management system during the contract, will the contractor be ready to adapt to the new management system? 12. Do you have experience applying USACE EM 385-1-1 (Mar 2024) and all requirements? Deficiencies observed on site will require immediate attention and action to meet all applicable safety codes. Equipment 13. What type of dredge equipment do you own and/or operate that is suitable for the work described? Do you own a mechanical dredge with a closed environmental clamshell bucket? Please list each piece of equipment capable of performing the work described, i.e. dredging, transfer, transportation, processing and final placement of the material. For each dredge that you list, please specify its bucket size(s), and any other salient characteristics. 14. Identify which dredge(s), including support equipment (tug, crew boat, scows, etc.), you would employ on this project. Also, for each dredge, identify the maximum dredging depth. 15. Do you own material scows? If so, how many do you have available for use? Please list the name of the scow, its type (ocean-going, sealed hull, etc) and the capacity. 16. Do you have the capability to process the dredged material on your own? If so please explain. If not, what commercial provider of dredge material processing will you engage for this project? What is the daily processing capacity in either case? 17. Will you be able to meet a production rate of 3,000 cubic yards per calendar day and complete all work? 18. Do you have experience with the use of an automated Dredged Material Monitoring System (Black Box / Silent Inspector) employing a Dredged Material Inspector (DMI)? | 63% | Market Research | 12/02/2026 |
Contract award Webbers Falls Tainter Gate Replacement and Repair. | 63% | Awarded | Open |
Additional Details
Solicitation Number
W912ES21B0005
Archive Date
Mar 30, 2021
Office Address
SAINT PAUL, MN, 55101-1323