GovChime
Notice ID: 153c06c654c24ddcb37d5c148fdfa10fSources SoughtArchived

FY26 Brazos Island Harbor (BIH) Texas, Entrance and Jetty Channel Hopper Maintenance Dredging, Cameron County, Texas

Archived on February 19, 2026. Original response deadline: . Full description on SAM.gov.

Overview

Response deadline
10:00 AM CST
Posted
January 20, 2026
Notice type
Sources Sought
NAICS
237990: Other Heavy and Civil Engineering Construction
Agency
Department of WarDepartment of the Army

Notice details

Office
US ARMY CORPS OF ENGINEERS.ENGINEER DIVISION SOUTHWESTERN.ENDIST GALVESTON.W076 ENDIST GALVESTON
Place of performance
Texas, 78597
Last updated
Nov 4, 2026
First published
Last updated on SAM.gov

Identifiers

Solicitation number
W912HY26X1B38
Notice ID
153c06c654c24ddcb37d5c148fdfa10f

Description

 The scope of the FY26 Brazos Island Harbor (BIH) Entrance and Jetty Channel maintenance dredging job will consist of dredging approximately 450,000 cubic yards of the Brazos Island Harbor, with five projected (5) options that relate to trail suction dredging and beach placement on South Padre Island.

Schedule No. 1, Hopper dredging of BIH Entrance Channel station -13+000 to station -6+00; estimated volume; 125,000 CY. And Hopper dredging of BIH Jetty Channel station -6+000 to 0+000; estimated volume: 225,000 CY.

Placement Area: Near Shore Feeder Berm 1A/1B

Options 1-3: Sea Turtle Trawling 15 days each. No additional time added to contract duration if awarded.

Option 4: Beach Placement at two locations on South Padre Island in lieu of Near Shore Feeder Berm 1A/1B. If awarded, additional time of 14 calendar days will be added to contract duration.

Option 5: Sea Turtle Trawling 15 days. No additional time added to contract duration if awarded.  

Dredging and beach placement option are subject to environmental windows for swimming and nesting sea turtles.

Period of Performance: Complete the entire work ready for use not later than 120 calendar days after the date the Contractor receives the Notice to Proceed. Completion time for Options 1-5 is 14 calendar days.

Full description on SAM.gov

Award Overview

No prior contract identified

No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.

Contacts

Contracting Officer

Primary Contact

Secondary Contact

Documents

Files (1)

  • Attachment 1 - Sources Sought Notice_BIH_W912HY26X1B38_20 Jan 2026.pdf

    114 KBAdded in Sources Sought version 3Posted
    Download

Lifecycle

  1. 3
    Version 3Sources SoughtArchivedCurrent

    FY26 Brazos Island Harbor (BIH) Texas, Entrance and Jetty Channel Hopper Maintenance Dredging, Cameron County, Texas

    Notice 153c06c654c24ddcb37d5c148fdfa10f on SAM.gov

  2. 6
    Version 6PresolicitationArchived

    Type changed from Sources Sought to Presolicitation

    FY26 Brazos Island Harbor (BIH) Texas, Entrance and Jetty Channel Hopper Maintenance Dredging, Cameron County, Texas

    Notice 7d1183e50cff4913bb46136535967ea9 on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline
Brazos Island Harbor Entrance and Jetty Channels Maintenance Dredging, Cameron County, Texas Amendment 0002
97%
Solicitation08/03/2026
FY26 HOUSTON SHIP CHANNEL, TEXAS BAYPORT FLARE HOPPER DREDGING Amendment 0001
93%
Solicitation11/10/2026
THIS IS AN UNRESTRICTED SOLICITATION FOR HOUSTON SHIP CHANNEL, TEXAS, REDFISH TO MORGANS POINT, HOPPER DREDGING, IN HARRIS, CHAMBERS AND GALVESTON COUNTIES, TEXAS IN HARRIS, CHAMBERS AND GALVESTON COUNTIES, TEXAS
88%
Solicitation02/24/2026
Gulf Intracoastal Waterway High Island to Causeway with Channel to Port Bolivar Maintenance Dredging
83%
Solicitation11/03/2026
The primary objective of Package #8 Segment 4 East E2 Clinton (E2C) consists of constructing an upland dredged material confined placement area (DMPA) to receive maintenance dredging material from future dredging Project 11 - Segment 4, located within the Houston Ship Channel near the Washburn Tunnel Crossing in Houston, Texas.The specific items in the scope of work include clearing, grubbing and stripping; grading; construction of outfall channels, drainage channels, perimeter ditching and other drainage features; perimeter embankment construction; drop outlet structure construction; erosion control measures; site security measures; geotechnical construction testing; topographic surveys before the start of construction, and during and after construction activities; placement of topsoil, and hydromulch seeding; demobilization and site cleanup; and related ancillary work.
83%
Solicitation01/08/2026

Additional Details

Solicitation Number

W912HY26X1B38

Archive Date

Feb 19, 2026

Office Address