Notice ID: ee6a335b73084f978d11c2aaf3d776caCombined Synopsis/Solicitation
Carlyle Water Line and Hydrant Installation
Archived on May 12, 2022. Original response deadline: . Full description on SAM.gov.
Overview
- Response deadline
- 10:00 AM UTC−05:00
- Posted
- April 25, 2022
- Notice type
- Combined Synopsis/Solicitation
- Set-aside
- Total Small Business Set-Aside (FAR 19.5)
- NAICS
- 237110: Water and Sewer Line and Related Structures Construction
- Agency
- Department of WarDepartment of the Army
Notice details
- Office
- W07V ENDIST ST LOUIS
- Place of performance
- Carlyle, IL, 62231
- Last updated
- Dec 4, 2025
Identifiers
- Solicitation number
- W912P922Q0008
- Notice ID
- ee6a335b73084f978d11c2aaf3d776ca
Description
Contractor shall supply all equipment, labor, and materials used for the installation of new water lines in Dam East Recreation Area. The contractor shall trench, install & backfill approximately 2150 linear feet of 3 SDR21 pipe, 150 linear feet of 1 HDPE pipe, 2 3 MJ Gate Valves, 2 valve boxes, 11 1 CTS curb stops, 11 curb boxes, and 11 Woodford S3-2 yard hydrants. The contractor shall tap into existing 1 water line using a saddle & corp and connect all water lines to hydrants and valves as needed. A curb box shall be placed over the new CTS valves and a valve box shall be placed over the new MJ gate valves to provide access to all valves. When complete, the access holes will allow a water wrench to be used to turn the valves on and off. After all lines, valves, and hydrants have been installed, the contractor shall pressure test the complete system to ensure no leaks. All waterlines will be laid with detection wire and caution water line locating tape. The waterline trench will have water line locating tape located approximating 18 below finished grade. All installations and connections of the water line and hydrants shall be in accordance with State and local plumbing codes by an IL licensed plumber. Water line field locations will be field located by the Government. All materials for water line installation and associated connections shall be furnished by the contractor. Installation shall be all inclusive to include all cost for parts, pipe, hydrants, materials, trenching, backfill, marking tape, detection wire, labor, supervision, equipment, testing, and incidentals required to install water lines per linear foot. Installation of new water lines will require contractor to trench through two roadways. The contractor is responsible for backfilling and repairing roadways with asphalt material after completion of installation. The contractor is responsible for locating any and all public, private and/or Government owned utilities prior to commencing work. Any damage to any utilities caused by the Contractors operations shall be replaced by the contractor at no expense to the Government. Remit questions to Elena.C.Coleman@USACE.ARMY.MIL Site visit is scheduled April 19th at 9:00 a.m. 801 Lake Carlyle, IL 62231. POC is Jody Harris. Questions deadline is 4/20/22 at10:00 a.m. Central.
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Documents
No documents available.
Lifecycle
Solicitation:
W912P922Q0008- Combined Synopsis
- 3×Combined SynopsisCurrentApr 11, 2022
Carlyle Water Line and Hydrant Installation
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
Additional Details
Solicitation Number
W912P922Q0008
Archive Date
May 12, 2022
Office Address
SAINT LOUIS, MO, 63103-2833