Building 66017 Repair Restrooms at KAFB
Awarded on September 18, 2026. Full description on SAM.gov.
Overview
- Posted
- September 18, 2026
- Notice type
- Award Notice
- Set-aside
- 8(a) Sole Source (FAR 19.8)
- NAICS
- 236220: Commercial and Institutional Building Construction
- Agency
- Department of WarDepartment of the Army
Notice details
- Office
- US ARMY CORPS OF ENGINEERS.ENGINEER DIVISION SOUTH PACIFIC.ENDIST ALBUQUERQUE.W075 ENDIST ALBUQUERQUE
- Place of performance
- 0, New Mexico, 87117
- PSC
- Y1AZ: CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS
- Last updated
- Oct 28, 2026
- First published
- Last updated on SAM.gov
- Award date
- Sep 18, 2026
- Award amount (SAM.gov award notice)
- $161.3K
Identifiers
- Solicitation number
- W912PP26QA026
- Notice ID
- 593694402c664ccaa836b3e898f5058a
- Award number (PIID)
- W912PP26PA036
Description
This action was awarded as an 8(a) Sole Source Set-Aside under the authority of section 8(a) of the Small Business Act.
The contractor shall furnish all parts, material, labor, equipment and supervision necessary to complete the work for Building 66017 Repair Restrooms.
Demolition
- Contractor must remove and dispose of existing ceiling grid, ceiling tiles, gyp ceilings, light fixtures, and mechanical diffusers and grills within scope of work boundary. (Approx. 150 Sq. Ft.)
- Contractor must remove and dispose of existing restroom plumbing fixtures within SOW boundary.
- Contractor must remove and dispose of existing restroom walls within SOW boundary.
- Contractor must remove and dispose of existing exterior door and frame. Prep opening for wall infill.
- Contractor must remove and dispose of existing exterior metal steps.
- Contractor must remove and dispose of existing interior vestibule door and frame.
- Contractor must remove and dispose of existing flooring and resilient wall base in existing restrooms and vestibule.
- All receptacles located within demolished walls must be removed and conduit and wiring must be removed back to nearest J-box.
- Contractor must remove and set aside existing drinking fountain for reuse in new work. All utility lines not reutilized in new work must be capped under floor or in nearest wall not being removed.
- Contractor must remove and dispose of existing fire alarm pull station – wiring back to nearest J-box.
- Contractor must remove existing fire extinguisher and bracket and set aside for reuse in new work.
- Construction
- Contractor must construct new ceiling with metal studs and moisture resistant gypsum wall board in each restroom. Ceiling to be taped, textured, and
painted (P-1).
-
- Contractor must provide and install new exhaust fan (EF-1) in each restroom
as indicated on drawings. Contractor must configure existing exhaust system to new fan locations. Exhaust fans must be connected to restroom light switch.
-
- Contractor must provide and install new LED light fixtures (LF-1) utilizing existing circuitry. Contractor must provide and install light switches with stainless steel cover plates for each restroom.
- Contractor must provide and install mechanical diffusers as indicated on plans, connect back to existing HVAC system.
- Contractor must provide and construct new restroom partition walls as indicated on plans – wall construction to be moisture resistant gypsum wall board on metal studs. Studs to be metal 3-5/8” or 6” if required to facilitate plumbing. Contractor must tape, texture, and paint walls (P-2).
- Contractor must provide and install Fiberglass Reinforced Paneling wall covering up to 60” AFF around interior of restroom walls.
- Contractor must provide and install new water closets (WC-1, WC-2) in each restroom, each water closet must be tied into existing utilities (supply water, sanitary drain) as required for proper functioning.
- Contractor must provide and wall mounted lavatories (LV-1) and faucet (FC-1) in each restroom, each lavatory must be tied into existing utilities (supply hot and cold water, sanitary drain) as required for proper functioning.
- Contractor must provide and install grab bars as indicated on drawings. Installation must meet requirements of ANSI 117.1 and the Americans with Disabilities Act (ADA), current version.
- Contractor must provide and install shower surround, shower curtain rod, shower head with detachable wand. Shower pan and head must be connected to existing utilities (hot and cold supply water, sanitary drain) as required for proper functioning. Shower must meet requirements of ASNI 117.1 & ADA.
- Contractor must provide and install mirrors (M-1) at each lavatory.
- Contractor must install government provided restroom accessories, including toilet paper dispensers, soap dispensers, paper towel dispensers, and sanitary napkin waste cans.
- Contractor must provide and install new wood doors, hardware, and frames where indicated on drawings. Doors hardware must include privacy lock with occupancy indicator.
- Contractor must provide and install exterior infill wall at location of previous door. Wall must be weatherproof, insulated and finished flush to match on both interior and exterior faces.
- Contractor must provide and install opaque privacy film at existing window.
- Contractor must install drinking fountain with bottle filler set aside during demolition at location indicated on drawing. Drinking fountain must be tied into existing utilities (supply water, sanitary drain) as required for proper functioning. Relocate existing light switch as required.
- Contractor must reinstall existing fire extinguisher and bracket.
- Contractor must provide and install coat hooks in each restroom.
- Contractor must provide and install signage on restrooms complying with KAFB and ADA standards.
- Contractor must provide and install floor drain (FD-1).
- Contractor must install government furnished vinyl flooring (FL-1) and resilient wall base (WB-1) in SOW area.
Award Overview
Award Number
W912PP26PA036
Award Amount (SAM.gov award notice)
$161.3K
Award Date
Sep 18, 2026
Awardee
Awardee UEI
E4MARCDDH3K3
Awardee CAGE Code
66JZ9
Awardee Address
Albuquerque, NM 87107, UNITED STATES
Line Item Number
0001
Original Solicitation
Notice ID: 593694402c664ccaa836b3e898f5058a
Posted Date: Sep 18, 2026
Original Response Deadline: Not specified
Contract Details
Contract data not yet available
Contract details typically appear within 2-4 weeks after award; DoD awards are published about 90 days after signature.
Contacts
Contracting Officer
Primary Contact
Documents
No documents available.
Lifecycle
- 3Version 3Award NoticeArchivedCurrent
Building 66017 Repair Restrooms at KAFB
Similar Opportunities
Additional Details
Solicitation Number
W912PP26QA026
Archive Date
Oct 3, 2026
Office Address
ALBUQUERQUE, NM, 87109-3435