Repair AMSA / ECS - Arden Hills Army Reserve Center, Minnesota
Archived on December 31, 2025. Original response deadline: . Full description on SAM.gov.
Overview
- Response deadline
- 2:00 PM EST
- Posted
- December 1, 2025
- Notice type
- Sources Sought
- NAICS
- 236220: Commercial and Institutional Building Construction
- Agency
- Department of WarDepartment of the Army
Notice details
- Office
- US ARMY CORPS OF ENGINEERS.ENGINEER DIVISION GREAT LAKES AND OHIO.ENDIST LOUISVILLE.W072 ENDIST LOUISVILLE
- Place of performance
- Arden Hills, Minnesota
- Last updated
- Nov 5, 2026
- First published
- Last updated on SAM.gov
Identifiers
- Solicitation number
- W912QR-26-AHARC
- Notice ID
- 365aabe2a2a34f7eba4120e51a017bc1
Description
A market survey is being conducted to determine if there are a reasonable number of interested small business concerns to set this future project aside for them. If your firm is a Small Business, certified HUBZone, 8A, Woman-Owned Small Business or Service-Disabled Veteran Owned Small Business and you are interested in this project please respond appropriately.
Project Location: Arden Hills ARC, Arden Hills, MN
Project Description: This project is a Design/Build project that will include:
Repairing a failing, 31,658 SF Area Maintenance Support Activity/Equipment Concentration Site (AMSA/ECS) vehicle maintenance facility at the Arden Hills Army Reserve Center (ARC) at Arden Hills, MN. This project will repair failing facility components, extend the economic life of the facility by 25 years and provide a modern maintenance facility that enables readiness for the Army Reserve units stationed there. Other methods of meeting this requirement were analyzed, to include building demolition and new construction, but were deemed non-viable due to the cost of repair vs. the cost of demolition and new construction. Building components and systems to be repaired include the Heating, Ventilation, and Air Conditioning (HVAC), electrical distribution, fire alarm and suppression systems, ceilings, windows, doors, floor coverings, interior reconfiguration, and interior finishes. Project includes retrofit installation of new 10T crane with 20' hook height and raising overall building roof to accommodate new crane hook height. The project will also repair the exterior facade and finishes. All hazardous materials (HAZMAT) removed as part of the demolition will be disposed of following all state and federal guidelines.
Contract duration is estimated at 900 calendar days. The estimated cost range is between $25,000,000 and $100,000,000. NAICS code is 236220. All interested Small Businesses, certified HUBZONE, 8A, Woman-Owned Small Business or Service-Disabled Veteran Owned Small Business contractors should respond to this survey via the Microsoft Form link below by Tuesday, December 16, 2025 by 2:00 PM Eastern Standard Time.
Responses should include:
1. Identification and verification of the company’s small business status.
2. Contractor’s Unique Entity Identifier (UEI).
3. Documentation from the firm’s bonding company showing current single and aggregate performance and payment bond limits.
4. Description of Experience – Provide descriptions on up to three (3) projects completed by you as the prime contractor or if the offeror is a Small Business, they can provide Past Performance of affiliates in accordance with DFARS 215.305(a)(2)(C). To be relevant the projects submitted should be greater than 95% construction complete or completed within the last 5 years and are similar to this project in scope and complexity. Demonstrate experience including self-performing 15% of the construction. Provide documentation demonstrating experience for projects of similar type projects. Each project must include the name, title, project role, e-mail address, and telephone number of at least one reference. References may be used to verify project size, scope, dollar value, percentages and quality of performance.
- Projects similar in Scope to this project include: Major renovation of buildings similar to an Area Maintenance Support Activity (AMSA), Vehicle Maintenance Shop (VMS), Organizational Maintenance Shop (OMS). Equipment Concentration Site (ECS) facility, Commercial Fleet Maintenance Center, Heavy Equipment Maintenance Facility, Industrial Equipment Depot, or other facilities which are intended for ground-vehicle maintenance and include secured, paved, and illuminated parking. A major renovation is described as a “complete renovation of the facility”, or replacement of major building systems and components such as roof, HVAC, electrical, plumbing, fire alarm and suppression systems, ceilings, windows, doors, floor coverings, interior reconfiguration, and interior finishes.
- Projects similar in size to this project include: Renovated Building(s) with a combined square footage of at least 20,000 SF on a single project of one or more building(s).
- Based on definitions above, for each project submitted include:
- Current percentage of construction complete and the date when it was or will be completed.
- Size of the project – State SF of renovation.
- Scope of the project – Describe the work
- The dollar value of the construction contract
- The percentage of work that was self-performed as project and/or construction management services or physical construction type work.
- Whether the project was design build or design/bid/build
- Identify the number of subcontractors by construction trade utilized for each project.
5. Small Businesses are reminded under FAR 52.219-14, Limitations on Subcontracting; they must perform at least 15% of the cost of the contract, not including the cost of materials, with the firm’s own employees for general construction-type procurement. Include the percentage of work that will be self-performed on this project, and how it will be accomplished.
Submission Requirement: The only authorized transmission method of responses is via filling out the survey form. No other transmission method will be accepted. Please limit your capability statement to the space provided within the form. The Market Survey Form can be accessed at https://forms.osi.apps.mil/r/m7RM0xSKtG or via the QR Code provided in the attachments.
This is NOT a Request for Proposal and does not constitute any commitment by the Government. Responses to this sources sought notice will be used by the Government to make appropriate acquisition decisions. All interested sources must respond to future solicitation announcements separately for responses to this market survey.
NOTICE: The following information is provided for situational awareness and is not required to respond to this Sources Sought.
All contractors must be registered in the System for Award Management (www.SAM.gov) prior to award of a contract. All proposed contractors are highly encouraged to review FAR Clause 52.232-33 Payments by Electronic Funds Transfer – System for Award Management, which indicates “All payments by the Government under this contract shall be made by electronic funds transfer (EFT).” Those not currently registered can obtain registration by going to the website http://www.SAM.gov. The process can usually be completed from 24 to 48 hours after submission. Contractors will need to obtain a Unique Entity Identifier (formerly DUNS number) for processing their registration. If you do not already have a Unique Entity Identifier, one can be obtained from http://www.SAM.gov. Refer to www.SAM.gov for information formerly found in CCR, EPLS, ORCA and FedReg.
Please begin the registration process immediately in order to avoid delay of the contract award should your firm be selected.
ALERT: You must submit a notarized letter appointing the authorized Entity Administrator before your registration will be activated. This requirement now applies to both new and existing entities. Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required before the GSA Federal Service Desk (FSD) will activate the entity's registration.
Effective 29 June 2018, vendors creating or updating their registration can have their registration activated prior to the approval of the required notarized letter. However, the signed copy of the notarized letter must be sent to the GSA Federal Service Desk (FSD) within 30 days of activation or the vendor risks no longer being active in SAM. Vendors can check whether an account is active by performing a query by their CAGE or Unique Entity Identifier The new registration process may now take several weeks, so vendors are highly encouraged to begin registering as soon as possible to avoid any possible delays in future contract awards. Remember, there is no cost to use SAM. To find out additional information about the changes of the SAM registration process, contractors should visit the Frequently Asked Questions (FAQ) link located at the top of the SAM homepage (www.sam.gov).
Award Overview
No prior contract identified
No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.
Contacts
Contracting Officer
Primary Contact
Documents
Files (1)
- Download
QR Code.png
591 KBAdded in Sources Sought version 3Posted
Lifecycle
- 3Version 3Sources SoughtArchivedCurrent
Repair AMSA / ECS - Arden Hills Army Reserve Center, Minnesota
- 6Version 6PresolicitationArchived
Type changed from Sources Sought to Presolicitation
Presolicitation - Repair AMSA / ECS - Arden Hills Army Reserve Center, Minnesota
Similar Opportunities
Title | Match | Phase | Deadline |
|---|---|---|---|
***Amendment 0004 is issued to PHASE II SELECTED OFFERORS ONLY on 28 August 2026. The due date is extended to 4 September 2026 at 1:00 PM EDT***Amendment 0003 is issued to PHASE II SELECTED OFFERORS ONLY on 4 August 2026*** ***Amendment 0002 is issued to PHASE II SELECTED OFFERORS ONLY on 29 July 2026**** Request for Proposal (RFP), Solicitation No. W912QR26RA035 is issued for the Design-Build of the Maintenance Support Activity (AMSA) and Equipment Concentration Site (ECS) in Arden Hills, MN. All documents are available for download from the Procurement Integrated Enterprise Environment (PIEE) website. Go to the Attachments/Links section of the SAM notice and access the hyperlink titled PIEE Solicitation Module Link for W912QR26RA035. Once at the site, scroll down to the Attachments section of the PIEE Solicitation Module to locate the documents. | - | Solicitation | 09/04/2026 |
438-21-403, Renovate First Floor Kitchen | - | Solicitation | 11/13/2026 |
Amendment 0001 incorporates a copy of the ICRA, Site Visit attendance sheet, responses to the Site Visit questions and a revised DBA Wage Determination. This project includes all labor, management, and materials to replace the existing carpet and base with Luxury Vinyl Plank and new Rubber Cove Base in Building 1,on the 3rd and 2nd Floors. All measurements/dimensions existing blueprints are approximate. Contractor must verify all measurements/dimensions. The Contractor shall inspect the area under contract prior to commencing work and identify any pre-existing damage and provide an Existing Site Conditions report with related photos to the Contracting Officer for review and approval. The Contractor shall match existing conditions at each location. The contractor will be responsible for and shall repair any excessive damage caused by the removal/demolition of existing materials or the installation of new materials. | - | Solicitation | 09/02/2026 |
This is a Pre-Solicitation Notice regarding project: 438-21-403, Renovate First Floor Kitchen at the Sioux Falls VA Health Care System, Sioux Falls, South Dakota. The Department of Veterans Affairs, Network Contracting Office 23 (NCO 23), is preparing to issue a solicitation for a Firm-Fixed-Price contract for this project. Note: This is a Pre-Solicitation Notice only, the Solicitation will not be posted for at least 15 days from the date of this notice. This is NOT a request for proposal. Estimated SOLICITATION DATE: on or about 08/20/2026 Estimated AWARD DATE: 10/31/2026 SET-ASIDE: 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) NAICS: 236220, Commercial and Institutional Building Construction $45.0 Million PROJECT MAGNITUDE: Between $10,000,000 and $20,000,000. THIS IS A TOTAL 100% SERVICE-DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE. In accordance with Public Law 109-461 and VAAR 819.7003 (b), bidders must be registered, certified, and listed in the SBA certification database at  https://veterans.certify.sba.gov/ as a SDVOSB/VOSB. Only bids from verified SDVOSB s at SBA certification database at the time of proposal submission shall be deemed responsive. All non-responsive bids shall be rejected and ineligible for award. SCOPE OF WORK 438-21-403, Renovate First Floor for New Kitchen Sioux Falls VA Healthcare System GENERAL INFORMATION Base Bid: The Contractor must provide all supervision, tools, labor, materials, equipment, services, and testing necessary to accomplish the Renovate First Floor for New Kitchen project per the construction drawings and specifications. The project must be accomplished by the contract drawings and specifications for the project 438-21-403. Follow OSHA and all VA regulations as outlined in specifications 01 00 00. This work includes but is limited to: Demolition as described on the design plans and specifications. The contractor is responsible for locating all the existing utilities within the project site before any excavation or site work begins. Contractor shall remove from the VA site and dispose of all equipment and materials not scheduled to be reused. Construction consists of, but is limited to: Site work includes fencing, excavation, grading, paving, and protection of existing utilities. Demolition of walls, floors, ceilings, equipment, heating/cooling ventilation, and electrical. Construction consists of architectural, structural, mechanical and electrical improvements. Installation of owner furnished equipment The existing kitchen is located on the 2nd floor of building 5. The project consists of renovating first floor of building 5. There are phases to ensure the kitchen and VA staff provide meals for the impatient staff during the construction. Phasing is required to keep the existing kitchen operational. Additional construction projects will be occurring at the same time and near the kitchen renovation space. Contractors are expected to coordinate with the other contractors to minimize the disruption to the hospital. Owner furnished equipment will be provided for contractor installation. Once the equipment is received the contractor must store the equipment on site in a humidity and temperature-controlled storage unit. Maintain 50% relative humidity and a temperature of 60 - 70 degrees Fahrenheit. VA will be badging all construction employees. Badging requires background checks and personal information on each contract employee that will be on site. Forms to be filled out by the contractors and submitted for the badging process. Submittal exchange shall be procured and managed by the contractor for all submittals; Phasing is required to ensure the hospital is functional throughout the request for information (RFI), architectural supplemental information (ASI), VA purchased contractor installed equipment, shop drawings, and other project tracking needs for the duration of the project. Specification section 11 40 00 and plan sheet FS101 and plan sheet FS103 include the owner furnished kitchen equipment for a line item to be included in submittal exchange for review and acceptance. Night and weekend work will be expected to keep the campus fully functional during the construction activities that cannot be accomplished during business hours. After-hours are typically 5:00pm and before 6:00am. A dedicated site superintendent managing the construction effort and a site safety health officer shall be present during all construction activities. A dedicated quality control manager for the quality of the construction effort must be provided by the contractor per specification 01 45 00. Other construction will be occurring during the project. Coordination with other contractors is expected to ensure no disruption to the hospital s daily functions. Accuracy of the Planned Information: Bidders are highly encouraged to conduct a thorough site visit to investigate all as-built conditions of the project area in this SOW. Discrepancies in Planning Information: The prime contractor must promptly report to the Contracting Officer in writing any discrepancies between plans and specifications and as-built conditions. The Prime Contractor shall make no adjustments to their work due to discrepancies prior to review by the Contracting Officer. Ownership of Drawings: All designs, drawings, specifications, notes, and other work developed in the performance of this contract shall be the sole property of the US Government. The Prime Contractor shall provide a list of all items specified for which no substitutions will be accepted. This list shall identify each item with the specification section in which the item is defined. Performance Period:  The contractor shall complete the work required under this SOW, Monday through Friday in 550 calendar days or less from Notice to Proceed, unless otherwise directed by the Contracting Officer (CO). Construction at the Government site shall not take place on Federal holidays or weekends unless approved by the project engineer. Tentative Schedule:  Contract Award A Pre-construction Conference A+7 Notice to Proceed D (A+12) Construction Start D+22 Construction Completion D+550 | - | Pre-Solicitation | 09/01/2026 |
Amendment 2 for additional questions received | - | Solicitation | 08/03/2026 |
Additional Details
Solicitation Number
W912QR-26-AHARC
Archive Date
Dec 31, 2025
Office Address
LOUISVILLE, KY, 40202-2230