Notice ID: 121e2a70312d4b4e96fbf6b4f6df7cd4Solicitation

WPAFB B71D Replace Cooled Waterlines

Archived on August 30, 2022. Original response deadline: . Full description on SAM.gov.

Overview

Response deadline
2:00 PM UTC−04:00
Posted
August 12, 2022
Notice type
Solicitation
NAICS
236220: Commercial and Institutional Building Construction
Agency
Department of WarDepartment of the Army

Notice details

Office
W072 ENDIST LOUISVILLE
Place of performance
Dayton, OH, 45324
Last updated
Dec 4, 2025

Identifiers

Solicitation number
W912QR22R0016
Notice ID
121e2a70312d4b4e96fbf6b4f6df7cd4

Description

The intent of this solicitation is to remove and replace deteriorated steel identified in the process cooling water pipe system (facilities 71A, 71D, 20, and 20A) and served by cooling towers at facility 21624 (building 71D) with new grooved stainless-steel pipe. Reroute path of piping from facility 21624 (71D) to 20020A from existing below ground to above ground, entering facility 20020A at the Southeast corner of the building and hanging from wall supports along South side of building until it reaches the original tie-in location for the existing auxiliary oil room. Steel piping is preferred in all mechanical room spaces and where sufficient space is available for maintenance access. Includes replacement of pumps; new Process Automation System controls, which including new control valves, new VFDs, process automation system programming, new Motor Control Center MCC-71D, and associated Automatic Transfer Switch (ATS); conduit; electrical wiring; communications cabling; control wiring; and miscellaneous control components. TYPE OF CONTRACT AND NAICS: This will be for one (1) Firm-Fixed-Price (FFP) contract. The North American Industrial Classification System Code (NAICS) for this effort is 236220 Commercial and Institutional Building Construction. TYPE OF SET-ASIDE: Full and Open Competition (Unrestricted) CONSTRUCTION MAGNITUDE: The magnitude of this construction project is anticipated to be between $5,000,000 and $10,000,000 in accordance with FAR 36.204. SELECTION PROCESS: This is a single-phase procurement. The proposals will be evaluated using a Best Value Tradeoff source selection process. The technical information contained in each offerors proposal will be reviewed, evaluated, and rated by the Government. DISCUSSIONS: The Government intends to award without discussions but reserves the right to conduct discussion should it be deemed in the Government's best interest. SOLICITATION WEBSITE: The official solicitation, when posted, will be available free of charge by electronic posting only and may be found at the Contracting Opportunities website, http://Sam.gov. Paper copies of the solicitation will not be issued. Telephone and Fax requests for this solicitation will not be honored. Project files are Portable Document Format (PDF) files and can be viewed, navigated, or printed using Adobe Acrobat Reader. To download the solicitation for this project, contractors are required to register at the Contracting Opportunities website at http://Sam.gov. Amendments, if/when issued, will be posted to the above referenced website for electronic downloading. This will be the only method of distributing amendments prior to closing; therefore, it is the Offerors responsibility to check the website periodically for any amendments to the solicitation. REGISTRATIONS: Offerors shall have and shall maintain an active registration in the following database: System for Award Management (SAM): Offerors shall have and shall maintain an active registration in the SAM database at http://Sam.gov to be eligible for a Government contract award. If the Offeror is a Joint Venture (JV), the JV entity shall have valid SAM registration in the SAM database representing the JV as one business/firm/entity. If at the time of award an Offeror is not actively and successfully registered in the SAM database, the Government reserves the right to award to the next prospective Offeror. POINT-OF-CONTACT: The point-of-contact for this procurement is Robert Glenn, Jr, Contract Specialist, at robert.glenn2@usace.army.mil

Full description on SAM.gov

Award Overview

No prior contract identified

No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.

Contacts

Documents

No documents available.

Lifecycle

Solicitation:W912QR22R0016
  1. Pre-Solicitation
  2. Solicitation

Award typically follows within 30–90 days after the response deadline. (estimate)

  1. Pre-SolicitationMay 2, 2022

    WPAFB B71D Replace Cooled Waterlines

    Notice 36057ee9388c46459187357afb85edfa on SAM.gov

  2. 5×
    SolicitationCurrentMay 31, 2022

    WPAFB B71D Replace Cooled Waterlines

    Notice 121e2a70312d4b4e96fbf6b4f6df7cd4 on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline
SPECIAL NOTICE The U.S. Army Corps of Engineers (USACE) is issuing this special notice to announce an upcoming competition for a design and construction solicitation for the US Space Force Integration Facility, F/10852 using Progressive Design-Build under 10 USC §2808a Other Transaction Authority for Construction. This notice is for informational and planning purposes to allow interested parties to prepare for and provide feedback prior to the official solicitation release. I. INDUSTRY DAY USACE intends to conduct an Industry Day on 03 December 2026 at 0900 Eastern Time to provide an overview of the project, acquisition strategy, and anticipated requirements. This event will provide interested parties with an opportunity to gain additional insight into the project and proposed PDB under an OT (non-FAR-based) framework. A notional acquisition schedule will be shared. Interested parties are encouraged to ask questions and provide input. General questions will be permitted during the Industry Day; however, all discussions and responses provided during the event are considered unofficial and are for informational purposes only. Statements made during the Industry Day do not constitute commitment, authorization, or binding guidance related to the future RFQ. Official Questions and Answers (Q&A) will be accepted and addressed following the release of RFQ. II. LOCATION Industry Day Presentation location: Hope Hotel, 10823 Chidlaw Rd # A, Dayton, OH 45433 III. PROJECT OVERVIEW Project Title: US Space Force Integration Facility, F/10852 Location: Wright-Patterson Air Force Base (WPAFB), OH NAICS Code: 236220 Total Program Funding: $394,000,000.00 IV. PROJECT DESCRIPTION The USSF Integration Facility is a newly programmed mission at Wright-Patterson Air Force WPAFB, Ohio. It serves as a highly classified and secured contiguous operations area to enable Director for National Intelligence (DNI) and United States Space Force (USSF) directed and endorsed missions in areas of the highest national security, housing intelligence analysis and production for new and expanded all-source means that enable near-real-time capabilities. The facility supports the intelligence needs of the Defense Intelligence Enterprise, USSF, joint warfighters, policymakers, and acquisition professionals, driving intelligence, surveillance, and reconnaissance (ISR) for space domain operations including detection, characterization, and targeting of adversary space capabilities. The adjacent existing facility, Building F/10854, will remain fully occupied and uninterrupted, maintaining 24/7 business operations and ICD 705 security accreditation throughout construction, requiring strict utility, access, physical security, and logistical phasing constraints. Construction is broken into distinct agreement phases under the Progressive Design-Build (PDB) framework. Phase 1 (Design & Pre-Construction): This Phase is structured to collaboratively advance the facility design from initial concepts to 65% design maturity, perform detailed constructability reviews, conduct transparent open-book cost estimating, identify and mitigate complex interface risks, and validate the overall space programming. Pre-construction services will establish a baseline cost and allow for early design and potential separate authorization of long-lead procurement items. Phase 2 (Final Design and Construction): This Phase will include the completion of final design documents (95% and 100% Certified Final), fast-tracking capabilities, and all physical construction activities, including structural, interior finishes, specialized secure Sensitive Compartmented Information Facility (SCIF) fit-out, redundant systems commissioning, and final security accreditation. Phase 2 will also include comprehensive site work, utility distribution integration, and connection into the active Building F/10854. Phase 2 covers construction of the multi-floor, approximately 333,700 SF secure USSF Integration Facility, including the physical connection to active Building F/10854, the integration of high-efficiency HVAC networks, a backup generator facility, high-security electrical switchgear, and the buildout of specialized SCIF and SAP compartments. The Government will use available concept design information, programmed requirements, and initial planning data as the initial technical baseline. During Phase 1, the selected Design-Builder will validate the baseline and may recommend refinements; any material deviation from the Government’s baseline will require Government review and approval. The scope generally encompasses the following critical lines of effort: Critical Infrastructure and Utilities: Installation of high-efficiency mechanical, electrical, plumbing (MEP), heating, ventilation, and air conditioning (HVAC) systems designed for 24/7 continuous operation, electrical tie-ins to centralized utilities, backup generator integration (7,500 KW), Lightning Protection Systems (LPS), and addressable fire protection networks. Secure Facilities: Turnkey design, construction, and Defense Intelligence Agency (DIA) accreditation of highly classified Special Access Program (SAP) SCIF spaces built to stringent ICD 705, IC Tech Spec, and Telecommunictaions Electronics Material Protected from Emanating Spurious Tranmission (TEMPEST) shielding standards to ensure complete physical, visual, and acoustic isolation. New Construction, Envelope, and Physical Connection: Construction of a new structural frame with metal panels and pre-cast exterior walls, establishing a secure thermal wall envelope, executing the physical and utility connection to adjacent operational Building F/10854, and conducting all associated site work, paving, and access control infrastructure. V. ACQUISITION STRATEGY - PRE-AWARD The USACE will use a streamlined competitive selection process: Step 1 –RFQ: Interested parties will submit a Statement of Qualifications (SOQ). Following evaluation of the qualification packages, the Government intends to short-list a target of three (3) of the highest qualified Design-Builders to proceed to Step 2. Step 2 – Pitches: Selected Companies will participate in pitch presentations. One company will be selected as the Design-Build team for award of the initial design and preconstruction services with a modification for design completion and construction award. Step 3 – Exclusive Negotiation: Based on pitch evaluations, the Government will select one Design-Builder to enter exclusive negotiations. VI. ACQUSITION STRATEGY – AWARD The agreement will be awarded to the most qualified Progressive Design-Build Entity (PDBE) to provide design development, preconstruction services, and construction. Post-award Phase 1 of PDB includes Design and Pre-construction services and Post-award Phase 2 includes the final design and construction. The agreement will be Firm-Fixed-Price (FFP). The FFP for successive design and construction milestones will be agreed to as the design progresses and funds are available. VII. VIRTUAL PARTICIPATION OPPORTUNITY: For those who are unable to attend the Industry Day event in person, the Louisville District will also make the event available via Microsoft Teams. The details related to the MS Teams event are provided below: Microsoft Teams Meeting Join: https://dod.teams.microsoft.us/meet/993610255621?p=yaQ28DL3lmCC9Nap5C Meeting ID: 993 610 255 621 Passcode: Y6sB764r VIII. KEY SECURITY REQUIREMENTS This project will require the selected contractor and its subcontractor(s) to process, store, or transmit CUI and Federal Contract Information (FCI). In accordance with the CMMC program (32 CFR part 170) and USACE policy (including Alert 26-HQ-010, Rev1), CMMC Level 2 (Self) will be a mandatory prerequisite prior to award. Offerors must have an active SAM registration and a current, verified BASIC confidence level assessment (or higher) posted in the Supplier Performance Risk System (SPRS) in accordance with NIST SP 800-171. NOTE: An offeror will not be eligible for award if they do not possess the required CMMC status posted in SPRS prior to award. IX. CLOSING STATEMENT All interested parties should monitor the official solicitation announcement, which will provide complete details and submission instructions. Draft documents may be provided at a future date for feedback and informational purposes only and are subject to change upon issuance of the formal solicitation. NOTE: This will be a combined Industry for both the US Space Force Integration Facility (USSF) and the Air Force Material Command (AFMC) Headquarters Renovation projects, both located at Wright Patterson Air Force Base, Ohio.
-Special Notice11/30/2026
The U.S. Army Corps of Engineers (USACE) is issuing this special notice to announce an upcoming competition for a construction solicitation for the Air Force Materiel Command (AFMC) Headquarters (HQ) Renovation, Building 10262, utilizing an Other Transaction (OT) Agreement under 10 U.S.C. § 2808a. The anticipated delivery method is Progressive Design-Build (PDB). This notice is for informational and planning purposes. INDUSTRY DAY USACE intends to conduct an Industry Day on 03 December 2026 at 0900 Eastern Time to provide an overview of the project, acquisition strategy, and anticipated requirements. This event will provide interested parties with an opportunity to gain additional insight into the project and proposed PDB under an OT (non-FAR-based) framework. A notional acquisition schedule will be shared. Interested parties are encouraged to ask questions and provide input in advance of the official Request for Qualifications (RFQ) release. General questions will be permitted during the Industry Day; however, all discussions and responses provided during the event are considered unofficial and are for informational purposes only. Statements made during the Industry Day do not constitute commitment, authorization, or binding guidance related to the future RFQ. Official Questions and Answers (Q&A) will be accepted and addressed following the release of RFQ. LOCATION Industry Day Presentation location: Hope Hotel, 10823 Chidlaw Rd # A, Dayton, OH 45433 PROJECT OVERVIEW Project Title: Renovate Headquarters (HQ) Air Force Materiel Command (AFMC), Building 10262, Phase 2 Construction Location: Wright-Patterson Air Force Base (WPAFB), OH Agency: U.S. Army Corps of Engineers, Louisville District NAICS Code: 236220 PROJECT DESCRIPTION This acquisition will deliver the design and construction for the progressive design-build phased renovation of Building 10262, AFMC HQ, at WPAFB, OH. The scope of work consists of furnishing all necessary equipment, materials, labor, supervision, quality control, and supplies to deliver a fully functional, modernized headquarters facility while supporting ongoing occupied command operations. Key features of the project may include: Facility Renewal, Envelope, and Interior Renovation: Replacement of the Building 10262 roof and related envelope work, comprehensive interior renovation and finishes of the entire second floor, designated basement areas, required building repairs, and hazardous-material abatement. Critical Infrastructure Overhaul: Modernization and replacement of affected mechanical, electrical, plumbing (MEP), heating, ventilation, and air conditioning (HVAC), electric-power, telecommunications, fire-protection, fire-alarm, and life-safety systems necessary to support the renovated areas. Secure Facilities & Specialized Spaces: Turnkey design, construction, and Defense Intelligence Agency (DIA) accreditation of Special Access Program (SAP) and Sensitive Compartmented Information Facility (SCIF) spaces compliant with ICD 705 / IC Tech Spec and DoDM 5205.07 Vol 3 standards (including designated basement areas). Occupied Facility Logistics & Continuity: Construction sequencing, utility/system outage planning, temporary bypass systems, controlled access, and strict coordination to maintain uninterrupted global command operations supporting approximately 4,000 personnel. ACQUISITION STRATEGY – PRE-AWARD USACE – Louisville District will use a streamlined competitive selection process: Step 1 – RFQ: Interested parties will submit a Statement of Qualifications (SOQ). Following evaluation of the qualification packages, the Government intends to short-list a target of three (3) of the highest qualified Design-Builders to proceed to Step 2. Step 2 – Pitch Presentations: Short-listed firms must attend a mandatory site visit at WPAFB, OH during pitch preparation, followed by live, interactive presentations. Problem-solving, technical approach, risk management, and team chemistry will be evaluated by the Government. Step 3 – Exclusive Negotiation: Based on pitch evaluations, the Government will select one Design-Builder to enter exclusive negotiations. All interested parties should monitor the official solicitation announcement, which will provide complete details and submission instructions. Draft documents may be provided at a future date for feedback and informational purposes only and are subject to change upon issuance of the formal project RFQ. Virtual Participation Opportunity: For those who are unable to attend the Industry Day event in person, the Louisville District will also make the event available via Microsoft Teams. The details related to the MS Teams event are provided below: Microsoft Teams Meeting Join: https://dod.teams.microsoft.us/meet/993610255621?p=yaQ28DL3lmCC9Nap5C Meeting ID: 993 610 255 621 Passcode: Y6sB764r This is a combined Industry Day for AFMC and United States Space Force (USSF).
-Special Notice11/30/2026
UPDATE 01 - Solicitation amendment 01 (updates solicitation closing date, and period of performance) - Contractor Access Form is attached - Note that CLIN 0003 work is an option END OF UPDATE 01 ***************************** The 179th Cyberspace Wing, Mansfield Ohio ANG Contracting Office is issuing this Solicitation notice for Project No's: PBXP 272018 – B422 Breakroom, and PBXP 272019 - B300 BDOC. Bids will be evaluated in accordance with RFO FAR 14.306. Bids will be evaluated without discussions. Award will be made in accordance with RFO FAR 14.307(b). This project is solicited as SET ASIDE FOR SMALL BUSINESSES, 100%. All responsible bidders are encouraged to participate. The North American Industry Classification (NAICS) Code is 236220, with a size standard of $45,000,000 average annual revenue for the previous three (3) years. The magnitude is between $0.00 and $150,000.00. See Sec 00 21 00 - Instructions, for pertinent details and instructions related to site visit. Interested contractors are highly encouraged to attend and shall follow conference registration and base access requirements shown in the solicitation. The bid opening date is currently scheduled for 10 December 2026, at 1:00pm (EST). Please ensure Request for Information template/outline is utitilized for all questions related to this project; template is located within Section 00 21 00 - Instructions. Interested bidders shall be registered in System for Award Management (SAM). To register go to: https://www.sam.gov. Instructions for registering are on the web page. The solicitation and associated information and the plans and specifications will be available only through Contract Opportunities located within SAM.gov website online at https://www.sam.gov. SAM.gov is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. The project site is located at the 179th Cyberspace Wing,Mansfield, Ohio 44903. Any questions should be emailed to the following:Gordon Strom, gordon.strom.1@us.af.mil. DISCLAIMER: The official plans and specifications are located on the official government web page and the Government is not liable for information furnished by any other source. Amendments, if/when issued will be posted to https://www.beta.sam.gov for electronic downloading. This will normally be theonly method of distributing amendments prior to closing; therefore, it is the bidder’s responsibility to check the website periodically for any amendments to the solicitation. Websites are occasionally inaccessible, due to various reasons.The Government is not responsible for any loss of Internet connectivity or for a bidders’ inability to access the documents posted on the referenced web pages.The Government will not issue paper copies.
-Solicitation12/10/2026
The Ohio Air National Guard intends to issue an Invitation for Bids to award a single firm fixed-price contract for construction services, to provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary for B422 Breakroom and B300 BDOC projects, at 179th Cyberspace Wing, 1947 Harrington Memorial Rd., Mansfield, Ohio ANG. The contract duration is currently estimated to be 120 calendar days after notice to proceed to include inspection and punch list. This project is set aside 100% for Small Businesses. The North American Industry Classification System (NAICS) Code is 236220, with a small business size standard of $45,000,000. The magnitude of construction is between $0.00 and $150,000. The tentative date for issuing the solicitation is on-or-about 10 November 2026. The tentative date for the pre-bid conference is on-or-about 16 November 2026, 10:00am local time, location to be provided in the solicitation. Interested contractors are encouraged to attend and shall follow conference registration and base access requirements shown in the solicitation. A site visit will follow the pre-bid conference. All questions for the pre-bid conference must be submitted by 09 November 2026, via email to: gordon.strom.1@us.af.mil . The bid opening date is tentatively planned for on-or-about 08 December 2026. Actual dates and times will be identified in the solicitation. Interested offerors must be registered in the System for Award Management (SAM). To register go to www.SAM.gov. Instructions for registering are on the web page (there is no fee for registration). The solicitation and associated information will be available only from the Contract Opportunities page at SAM.gov. Your attention is directed to FAR clause 52.219-14(e)(3) (DEVIATION 2021-O0008), LIMITATIONS ON SUBCONTRACTING, which states “By submission of an offer and execution of a contract, the Offeror/Contractor agrees in performance of the contract for General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 85 percent subcontract amount that cannot be exceeded”. In accordance with FAR 36.211(b), the following information is provided: The National Guard has no agency-specific policies or procedures applicable to definitization of equitable adjustments for change orders under construction contracts other than those described at FAR 43.204, DFARS 243.204 and AFARS 5143.204. Data for the prior 3 fiscal years regarding the time required to definitize equitable adjustments for change orders under construction contracts for the National Guard is currently not available but will be compiled and provided in future announcements. DISCLAIMER: The official plans and specifications are located on the official government webpage and the Government is not liable for information furnished by any other source. Amendments, if/when issued will be posted to Contract Opportunities for electronic downloading. This will normally be the only method of distributing amendments prior to closing; therefore, it is the offeror’s responsibility to check the website periodically for any amendments to the solicitation. Websites are occasionally inaccessible for various reasons. The Government is not responsible for any loss of Internet connectivity or for an offeror’s inability to access the documents posted on the referenced web pages. The Government will not issue paper copies.
-Pre-Solicitation12/08/2026
***21 October 2026 Update: The responses due date is being revised to 02 Novemeber at 12:00 P.M. Eastern Time. REQUEST FOR INFORMATION (RFI) / MARKET RESEARCH NOTICE RELATED TO SEVERAL UPCOMING PROJECTS at WPAFB, OHIO Notice: This is a Request for Information (RFI) for market research and informational purposes only. This announcement does not constitute a Solicitation or a Request for Proposal (RFP), and no solicitation is currently available. Participation in this RFI is strictly voluntary. The Government will not be obligated to award any agreement or contract because of this RFI, nor will it reimburse respondents for any costs associated with the preparation or submission of information. Submitting a response will not affect a firm’s ability to submit a proposal should a formal solicitation be issued in the future. NAICS Code: 236220 – Commercial and Institutional Building Construction (Note: While Other Transaction Authority is not subject to FAR-based small business regulations, this NAICS code is provided for market research to help the Government understand the size and demographics of the interested industrial base.) 1. PROJECT OVERVIEWS The U.S. Army Corps of Engineers (USACE), in support of the United States Air Force (USAF), is conducting market research to identify interested and qualified industry partners for the design and construction of several upcoming construction projects at Wright-Patterson Air Force Base (WPAFB), Ohio. PROJECT 1: RENOVATE NASIC MAIN CAMPUS, PHASE 1, F/10853 - This project is renovation of 170,000 SF of Sensitive and/or Special Access Program spaces. The work consists of the full renovation of F/10853 through reconfiguration and interior renovation to create a network of administrative functions. The work shall be done in accordance with Intelligence Community Directive 705 (ICD 705) criteria and standards. The interior demolition consists of removal of all architectural and mechanical, electrical, and plumbing (MEP) elements including floor, wall, and ceiling finishes. Work includes replacement of building systems, reconfiguration of interior partitions, life safety systems, roof replacement, and envelope modification. The roofing system will be replaced with an energy-compliant system. Penetrations will be added to the building for daylighting, and the exterior envelope will be modified on first floor locations for mechanical rooms. All piping and sprinklers that are part of the current fire protection system are to be replaced. All domestic water, storm, and sanitary piping will be replaced. Additionally, this project includes cybersecurity measures. A corridor bridge connecting F/10828 and F/10856 over an existing loading dock is to be constructed. Personnel will require swing space during the renovation of F/10853. Swing space will be provided through existing available spaces throughout the NASIC IPC campus or via a temporary facility. It is critical that the sequencing of repair work be considered so that available spaces are not overwhelmed. Estimated Acquisition Magnitude: Approximately $160,000,000 PROJECT 2: Advanced Materials Research Laboratory – C2A - Construction of an approximately ~90,000 SF three-story laboratory and research facility, as well as the potential construction of a central utility plant for the Air Force Reach Labor Material and Manufacturing Directorate. New facility will consist of concrete, foundation, structural steel frame, masonry etc. Onsite gas boilers for heat and chilled water generation for cooling and lab processes. The interior shall consist of open inter-disciplinary collaboration labs with clean utilities, vibration isolation, precision HVAC and humidity controls, as well as fire protection/suppression, intrusion detections systems and medium voltage switchgear (i.e. 12,470 volts). Site work consists of utilities, sidewalks, parking, communications The new facility shall connect to existing facilities and demolitions of facility 20654. is part of this project. Estimated Acquisition Magnitude: Approximately $122,000,000 PROJECT 3: Compressor Research Facility Systems Modernization This project will modernize the Air Force Research Lab’s (AFRL) Compressor Research Facility (CRF) by replacing legacy drive and power equipment with a new 30,000-horsepower Variable Frequency Drive system to support engine component testing. The effort will deliver a fully integrated system that improves reliability, control, maintainability, and long-term test capability. Work includes replacement of the existing drive system with a new 30,000-horsepower VFD with active front end, a new 30,000-horsepower brushless synchronous motor, a new primary transformer, medium-voltage switchgear, protective relaying, and all associated interconnecting cables, bus work, grounding, and terminations. The project also includes the demolition and removal of legacy electrical and mechanical equipment; upgrades to controls, monitoring interfaces, cooling and ventilation systems, and supporting electrical infrastructure; and any required structural, foundation, enclosure, or fire/life-safety modifications needed to install and operate the new equipment. Additional work will include system integration, testing, commissioning, performance verification, operator and maintainer training, and delivery of technical data, recommended spare parts, and warranty support. Estimated Acquisition Magnitude: $25,000,000 PROJECT 4: Consolidate/Demo F/31240 This project will decentralize Area A heating by replacing the aging high-temperature hot water (HTHW) system fed from Building F/31240, Line A, and Line D with standalone boiler plants serving 49 facilities. The project supports administrative, warehouse, laboratory, hangar, and dormitory buildings that require year-round hot water for heating, reheating, humidity control, and climate management. Work includes facility surveys, evaluation of mechanical room capacity and code compliance, and determination of any needed interior renovations or limited additions to support the new equipment. The project also includes demolition of Building F/31240 and its boiler equipment, removal of above-ground HTHW piping and supports, and capping and abandonment of below-grade piping in place. New high-efficiency boiler systems, pumps, controls, and related accessories will be installed at affected facilities, with evaluation of both natural gas-fired and electric options. Additional work includes mechanical room modifications, make-up water assemblies where needed, upgrades to electrical, fire alarm, fire suppression, and direct digital control systems, and site restoration including pavement repair, grass restoration, and backfill and seeding at the demolished plant site. Estimated Acquisition Magnitude: $66,500,000 PROJECT 5: Consolidate/Demo West Ramp This project will decentralize heating for the West Ramp area at Wright-Patterson Air Force Base by replacing the existing high-temperature hot water (HTHW) system from Building F/34019 with standalone boiler plants serving 15 surrounding facilities. The effort addresses aging and degraded infrastructure supporting administrative, laboratory, and active hangar facilities that require year-round hot water for comfort heating, reheating, humidity control, and climate management. The project includes surveying each facility to determine boiler locations, evaluating mechanical room walls for code compliance, and assessing whether mechanical room expansions, electrical upgrades, or system improvements are needed to support the new equipment. Work includes demolition and removal of Building F/34019 and its internal boiler equipment, along with demolition of the exterior emergency generator, tank, piping, and all above-ground HTHW piping, supports, and foundations. Below-grade piping will be capped and abandoned in place. Each affected facility will receive new high-efficiency boiler systems, distribution pumps, controls, and related accessories, with evaluation of both natural gas-fired and electric boiler options. The project also includes interior renovations to create or enclose mechanical room space in select buildings, installation of new gas mains and make-up water assemblies where required, upgrades to fire alarm, fire suppression, and direct digital control systems as needed, and site restoration including pavement patching and sod replacement at disturbed areas. Estimated Acquisition Magnitude: $14,000,000 PROJECT 6: Repair Dormitory Multi-Facility F/31212 & F/31213 This project repairs and modernizes Dormitories F/31212 and F/31213 at Wright-Patterson Air Force Base to improve living conditions, address aging building systems, and extend the service life of the facilities. Each three-story dormitory includes 76 dorm rooms and common living spaces, and both require comprehensive renovation because many systems and materials are at or near the end of their useful life. The effort focuses on sustainment repairs and restoration/modernization of the existing facilities rather than expansion. Work includes interior, exterior, and site repairs; evaluation and upgrade of mechanical, plumbing, and electrical infrastructure; replacement of domestic water, sanitary, and vent piping as needed; installation of a new water softening system and recommended booster pumping improvements; replacement of nuisance-tripping AFCI receptacles; new LED lighting, controls, and receptacles; and fire protection and fire separation corrections to meet code. The project also includes repairs for drainage and runoff issues, structural validation and repair of exterior walls, walkways, and stairwells, repair or replacement of damaged perimeter concrete walkways, and potential reconfiguration of shared restrooms into private restrooms at existing locations. Hazardous material and mold remediation will be needed. Estimated Acquisition Magnitude: $25,000,000 (total for both buildings) PROJECT 7: Renovate Research Facility – F/20490 This project renovates the North and South Wings of Research Facility F/20490 at Wright-Patterson Air Force Base. The facility is a two-story Aerospace Research building consisting of over 60,000 SF that was built in 1980. The interior requires renovations, repairs, and system upgrades to support consistent and reliable lab research operations. The purpose of the overall renovation is to improve functionality, reliability, and code compliance for current laboratory and office operations. The primary objective is to fully renovate the north and south wings to better separate office and laboratory functions, increase office space, and provide a more modern, efficient, and usable research environment that meets current Department of Defense, federal, and base standards. Work includes interior demolition and reconfiguration; renovation of office, laboratory, restroom, and breakroom spaces; installation of new low-flow plumbing fixtures, new lab fixtures, and associated lab utilities; replacement or upgrade of leaking plumbing, air handlers, portions of the roof, ceiling tiles, lighting, and electrical distribution components; and provision of new LED lighting, panels, feeders, receptacles, and toxic gas detection and alarm systems. The project also includes new partitions, doors, finishes, flooring, stairs, HVAC, chilled water distribution, sanitary and vent improvements, and code-related fire protection, egress corrections and medium voltage switchgear (i.e. 12,470 volts). The project may require temporary facilities (i.e. ~10,000 SF of swing space, temporary electrical utilities connection for the swing spaces, pad mounted transformers). Environmental coordination and hazardous material handling will be required, as the report identifies asbestos-containing materials within portions of the renovation scope that may be disturbed during construction. Estimated Acquisition Magnitude: Approximately $22,000,000 2. PLANNED ACQUISITION STRATEGY The Government is considering utilizing an Other Transaction (OT) Agreement for each of these projects under the authority of 10 U.S.C. § 2808a. This authority is intended for military construction projects that involve testing and experimentation associated with new and emergent construction technologies or delivery methodologies to achieve benefits such as enhanced mission resilience, improved installation support, or cost and schedule reduction. The baseline delivery method under consideration is Progressive Design-Build (PDB). Phase 1 (Design & Pre-Construction): The Government and the OT Awardee will work collaboratively to advance the design, perform constructability reviews, conduct open-book cost estimating, and mitigate project risks. Phase 2 (Construction): Upon reaching an agreed-upon level of design (e.g., 60% to 90%), the Awardee will propose a Guaranteed Maximum Price (GMP). If accepted, the Government will exercise Phase 2 for construction execution. If a GMP cannot be agreed upon, the Government retains an "off-ramp" to complete the design and construct the facility via alternative methods. 3. INFORMATION REQUESTED Section 1: Company Profile Firm Name, Address, and Point of Contact (Name, Title, Phone, Email). Unique Entity ID (UEI). Socioeconomic Status (Other Than Small, Small, 8(a), SDVOSB, WOSB, HUBZone, etc.). Participating Role (Prime Contractor, Subcontractor, Design Firm, Other) Controlled Unclassified Information (CUI) & Cybersecurity Maturity Model Certification (CMMC) – Some of the projects listed above may involve CMMC requirements prior to award of any agreement. These projects may require the selected prime contractor and its subcontractor(s) to process, store, or transmit CUI and Federal Contract Information (FCI). In accordance with the CMMC program (32 CFR part 170) and USACE policy (including Alert 26-HQ-010, Rev1), CMMC may be a mandatory prerequisite prior to award. An offeror will not be eligible for award if they do not possess the required current CMMC status posted in SPRS prior to award of any agreement. Briefly describe your firm's strategy for ensuring your information systems (and those of your subcontractors) are fully compliant. Briefly detail your experience in safeguarding Controlled Unclassified Information (CUI) and managing secure communications on previous federal/military design-build projects. How do you plan to handle the exchange of CUI design packages, specifications, and drawings with subcontractors who may have varying levels of cybersecurity maturity? Briefly describe how your firm plans to process, store, or transmit CUI and Federal Contract Information (FCI). Offerors must have an active SAM registration and a current, verified BASIC confidence level assessment (or higher) posted in the Supplier Performance Risk System (SPRS) in accordance with NIST SP 800-171. Section 2: Other Transaction Authority (OTA) & Statutory Compliance For each project listed above, that you are interested in submitting a proposal, please provide separate responses to the following: Innovative Technologies & Practices: 10 U.S.C. 2808(a) authorizes transactions other than standard contracts to carry out facility repair and construction projects—including the planning, design, engineering, prototyping, piloting, and execution —enabling early contractor involvement, commercial pricing transparency, and schedule and cost efficiencies. Describe any innovative materials, sustainable building technologies, or modern construction processes (e.g., prefabrication, modular MEP systems) your firm could utilize to accelerate the schedule, reduce costs, or increase the building's life expectancy. OTA Experience: Describe your firm’s experience (if any) executing projects under an Other Transaction Agreement (OTA). Overcoming Traditional Barriers: What commercial or Government-imposed barriers (e.g., traditional FAR-based procurement limitations) make it difficult to implement innovative methods on complex military construction/renovations? How can the flexibility of an OTA help overcome these barriers? Custom Commercial Terms & Dispute Resolution: To optimize the flexibilities of the OTA framework, what specific commercial terms (e.g. tailored dispute resolution/rapid escalation mechanisms, commercial milestone payment structures, or shared intellectual property rights for innovative method) would your firm recommend the Government adopt to minimize risk or incentivize your participation? Section 3: Progressive Design-Build (PDB) / Early Contractor Involvement Information Baseline: What minimum level of detail (e.g., DD Form 1391, conceptual design, spatial programming documents) does your firm require prior to entering Phase 1 (Design & Pre-construction) to feel confident in the project's baseline viability and target budget? Collaborative Framework: What collaborative mechanisms (such as joint design charrettes, target-value design workshops, or phased scoping approvals) do you recommend the Government implement in the first 30-90 days of Phase 1 to rapidly transition from a planning document to an agreed-upon technical baseline? Open-Book Pricing: Describe your experience with "open-book" pricing and transparency during pre-construction. How do you assure the Government that subcontractor and material pricing represent fair market value? Section 4: Guaranteed Maximum Price (GMP), Risk Allocation & Compensation Off-Ramp Risk & Design Rights: If the Government and the contractor cannot reach an agreement on the GMP (the "off-ramp"), what specific compensation structures (e.g., design fees, stipends, time-and-materials) would adequately compensate your firm for Phase 1 efforts? Who should retain ownership of the design deliverables in this scenario? GMP Lock-In Milestone: In your experience with highly complex, secure administrative renovations, at what design milestone (e.g., 35%, 65%, 95%) is it most advantageous to lock in the GMP, and why? Long-Lead Procurement: How do you handle the procurement of critical, long-lead items (such as backup generators, customized HVAC chiller components, and high-security electrical switchgear) prior to establishing the final construction GMP? Section 5: Specialized Experience Secure Spaces (ICD 705): Briefly describe your firm's specific experience in constructing and accrediting Special Access Program (SAP) spaces complying with ICD 705 standards. What are the primary risk factors in delivering these facilities on time? Complex MEP Infrastructure: Briefly detail your firm’s experience in designing and constructing central energy/chiller plants, complex electrical distribution, and backup power generator facilities. Adjoining Occupied Renovation: Briefly describe your firm’s approach to planning and executing construction phases in a fully operational, high-security 24/7 headquarters environment. How do you manage noise, dust, vibration, and security sweeps to prevent mission disruption? Communication Systems: Briefly describe your firm’s experience with the integration of robust communications infrastructure, including both Contractor-Furnished/Contractor-Installed (CFCI) and Government-Furnished/Contractor-Installed (GFCI) assets. Laboratory Equipment Procurement/Coordination: Briefly describe your firm’s experience with spatial planning, detailed design, utility integration, and installation of complex laboratory environments, encompassing both Contractor-Furnished/Contractor-Installed (CFCI) and Government-Furnished/Contractor-Installed (GFCI) equipment. Section 6: Teaming & Subcontractor Integration Subcontractor Onboarding: Under a collaborative (PDB) model, how and when do you plan to onboard critical specialty subcontractors (e.g., ICD 705 security, MEP, fire protection, hazardous abatement)? Competition: Will you compete these subcontracts openly during Phase 1 pre-construction, or do you prefer bringing in established, pre-selected trade partners from day one? Section 7: Bonding & Financial Capability Surety Timelines: If construction bonds are deferred until Phase 2, what is the maximum duration your surety would hold a commitment open between the finalization of the GMP and the Notice to Proceed for construction? Funding Gap Mitigations: If funding or execution authority for Phase 2 construction is delayed (e.g., 90–180 days post-design completion due to O&M/fiscal year cycles), what contractual mechanisms (e.g., escalation clauses, right to off-ramp) would your firm require to maintain the agreement? Bonding Limits: Specify your maximum bonding limits (Single and Aggregate) as a Sole Prime Contractor and/or as a Joint Venture. Phased bonding approach: Would a phased bonding structure - where the contractor is only required to bond the value of the phase 1 effort initially, and construction bonds are deferred until the execution of phase 2 - effectively mitigate risk for your firm? 4. SUBMISSION INSTRUCTIONS Interested firms are invited to submit their responses to this RFI no later than 22 October 2026 at 1600ET. Submissions should be sent via email to Mr. Jacob Pridemore at Jacob.S.Pridemore@usace.army.mil in PDF format, not exceeding 15 pages (excluding company brochures or standard profiles). Please direct all questions regarding this market research notice to the primary Point of Contact listed above. REQUEST FOR INFORMATION (RFI) / MARKET RESEARCH NOTICE RELATED TO SEVERAL UPCOMING PROJECTS at WPAFB, OHIO Notice: This is a Request for Information (RFI) for market research and informational purposes only. This announcement does not constitute a Solicitation or a Request for Proposal (RFP), and no solicitation is currently available. Participation in this RFI is strictly voluntary. The Government will not be obligated to award any agreement or contract because of this RFI, nor will it reimburse respondents for any costs associated with the preparation or submission of information. Submitting a response will not affect a firm’s ability to submit a proposal should a formal solicitation be issued in the future. NAICS Code: 236220 – Commercial and Institutional Building Construction (Note: While Other Transaction Authority is not subject to FAR-based small business regulations, this NAICS code is provided for market research to help the Government understand the size and demographics of the interested industrial base.) 1. PROJECT OVERVIEWS The U.S. Army Corps of Engineers (USACE), in support of the United States Air Force (USAF), is conducting market research to identify interested and qualified industry partners for the design and construction of several upcoming construction projects at Wright-Patterson Air Force Base (WPAFB), Ohio. PROJECT 1: RENOVATE NASIC MAIN CAMPUS, PHASE 1, F/10853 - This project is renovation of 170,000 SF of Sensitive and/or Special Access Program spaces. The work consists of the full renovation of F/10853 through reconfiguration and interior renovation to create a network of administrative functions. The work shall be done in accordance with Intelligence Community Directive 705 (ICD 705) criteria and standards. The interior demolition consists of removal of all architectural and mechanical, electrical, and plumbing (MEP) elements including floor, wall, and ceiling finishes. Work includes replacement of building systems, reconfiguration of interior partitions, life safety systems, roof replacement, and envelope modification. The roofing system will be replaced with an energy-compliant system. Penetrations will be added to the building for daylighting, and the exterior envelope will be modified on first floor locations for mechanical rooms. All piping and sprinklers that are part of the current fire protection system are to be replaced. All domestic water, storm, and sanitary piping will be replaced. Additionally, this project includes cybersecurity measures. A corridor bridge connecting F/10828 and F/10856 over an existing loading dock is to be constructed. Personnel will require swing space during the renovation of F/10853. Swing space will be provided through existing available spaces throughout the NASIC IPC campus and not via a temporary facility. It is critical that the sequencing of repair work be considered so that available spaces are not overwhelmed. Estimated Acquisition Magnitude: Approximately $160,000,000 PROJECT 2: Advanced Materials Research Laboratory – C2A - Construction of an approximately ~90,000 SF three-story laboratory and research facility, as well as the potential construction of a central utility plant for the Air Force Reach Labor Material and Manufacturing Directorate. New facility will consist of concrete, foundation, structural steel frame, masonry etc. Onsite gas boilers for heat and chilled water generation for cooling and lab processes. The interior shall consist of open inter-disciplinary collaboration labs with clean utilities, vibration isolation, precision HVAC and humidity controls, as well as fire protection/suppression, intrusion detections systems and medium voltage switchgear (i.e. 12,470 volts). Site work consists of utilities, sidewalks, parking, communications The new facility shall connect to existing facilities and demolitions of facility 20654. is part of this project. Estimated Acquisition Magnitude: Approximately $122,000,000 PROJECT 3: Compressor Research Facility Systems Modernization This project will modernize the Air Force Research Lab’s (AFRL) Compressor Research Facility (CRF) by replacing legacy drive and power equipment with a new 30,000-horsepower Variable Frequency Drive system to support engine component testing. The effort will deliver a fully integrated system that improves reliability, control, maintainability, and long-term test capability. Work includes replacement of the existing drive system with a new 30,000-horsepower VFD with active front end, a new 30,000-horsepower brushless synchronous motor, a new primary transformer, medium-voltage switchgear, protective relaying, and all associated interconnecting cables, bus work, grounding, and terminations. The project also includes the demolition and removal of legacy electrical and mechanical equipment; upgrades to controls, monitoring interfaces, cooling and ventilation systems, and supporting electrical infrastructure; and any required structural, foundation, enclosure, or fire/life-safety modifications needed to install and operate the new equipment. Additional work will include system integration, testing, commissioning, performance verification, operator and maintainer training, and delivery of technical data, recommended spare parts, and warranty support. Estimated Acquisition Magnitude: $25,000,000 PROJECT 4: Consolidate/Demo F/31240 This project will decentralize Area A heating by replacing the aging high-temperature hot water (HTHW) system fed from Building F/31240, Line A, and Line D with standalone boiler plants serving 49 facilities. The project supports administrative, warehouse, laboratory, hangar, and dormitory buildings that require year-round hot water for heating, reheating, humidity control, and climate management. Work includes facility surveys, evaluation of mechanical room capacity and code compliance, and determination of any needed interior renovations or limited additions to support the new equipment. The project also includes demolition of Building F/31240 and its boiler equipment, removal of above-ground HTHW piping and supports, and capping and abandonment of below-grade piping in place. New high-efficiency boiler systems, pumps, controls, and related accessories will be installed at affected facilities, with evaluation of both natural gas-fired and electric options. Additional work includes mechanical room modifications, make-up water assemblies where needed, upgrades to electrical, fire alarm, fire suppression, and direct digital control systems, and site restoration including pavement repair, grass restoration, and backfill and seeding at the demolished plant site. Estimated Acquisition Magnitude: $66,500,000 PROJECT 5: Consolidate/Demo West Ramp This project will decentralize heating for the West Ramp area at Wright-Patterson Air Force Base by replacing the existing high-temperature hot water (HTHW) system from Building F/34019 with standalone boiler plants serving 15 surrounding facilities. The effort addresses aging and degraded infrastructure supporting administrative, laboratory, and active hangar facilities that require year-round hot water for comfort heating, reheating, humidity control, and climate management. The project includes surveying each facility to determine boiler locations, evaluating mechanical room walls for code compliance, and assessing whether mechanical room expansions, electrical upgrades, or system improvements are needed to support the new equipment. Work includes demolition and removal of Building F/34019 and its internal boiler equipment, along with demolition of the exterior emergency generator, tank, piping, and all above-ground HTHW piping, supports, and foundations. Below-grade piping will be capped and abandoned in place. Each affected facility will receive new high-efficiency boiler systems, distribution pumps, controls, and related accessories, with evaluation of both natural gas-fired and electric boiler options. The project also includes interior renovations to create or enclose mechanical room space in select buildings, installation of new gas mains and make-up water assemblies where required, upgrades to fire alarm, fire suppression, and direct digital control systems as needed, and site restoration including pavement patching and sod replacement at disturbed areas. Estimated Acquisition Magnitude: $14,000,000 PROJECT 6: Repair Dormitory Multi-Facility F/31212 & F/31213 This project repairs and modernizes Dormitories F/31212 and F/31213 at Wright-Patterson Air Force Base to improve living conditions, address aging building systems, and extend the service life of the facilities. Each three-story dormitory includes 76 dorm rooms and common living spaces, and both require comprehensive renovation because many systems and materials are at or near the end of their useful life. The effort focuses on sustainment repairs and restoration/modernization of the existing facilities rather than expansion. Work includes interior, exterior, and site repairs; evaluation and upgrade of mechanical, plumbing, and electrical infrastructure; replacement of domestic water, sanitary, and vent piping as needed; installation of a new water softening system and recommended booster pumping improvements; replacement of nuisance-tripping AFCI receptacles; new LED lighting, controls, and receptacles; and fire protection and fire separation corrections to meet code. The project also includes repairs for drainage and runoff issues, structural validation and repair of exterior walls, walkways, and stairwells, repair or replacement of damaged perimeter concrete walkways, and potential reconfiguration of shared restrooms into private restrooms at existing locations. Hazardous material and mold remediation will be needed. Estimated Acquisition Magnitude: $25,000,000 (total for both buildings) PROJECT 7: Renovate Research Facility – F/20490 This project renovates the North and South Wings of Research Facility F/20490 at Wright-Patterson Air Force Base. The facility is a two-story Aerospace Research building consisting of over 60,000 SF that was built in 1980. The interior requires renovations, repairs, and system upgrades to support consistent and reliable lab research operations. The purpose of the overall renovation is to improve functionality, reliability, and code compliance for current laboratory and office operations. The primary objective is to fully renovate the north and south wings to better separate office and laboratory functions, increase office space, and provide a more modern, efficient, and usable research environment that meets current Department of Defense, federal, and base standards. Work includes interior demolition and reconfiguration; renovation of office, laboratory, restroom, and breakroom spaces; installation of new low-flow plumbing fixtures, new lab fixtures, and associated lab utilities; replacement or upgrade of leaking plumbing, air handlers, portions of the roof, ceiling tiles, lighting, and electrical distribution components; and provision of new LED lighting, panels, feeders, receptacles, and toxic gas detection and alarm systems. The project also includes new partitions, doors, finishes, flooring, stairs, HVAC, chilled water distribution, sanitary and vent improvements, and code-related fire protection, egress corrections and medium voltage switchgear (i.e. 12,470 volts). The project may require temporary facilities (i.e. ~10,000 SF of swing space, temporary electrical utilities connection for the swing spaces, pad mounted transformers). Environmental coordination and hazardous material handling will be required, as the report identifies asbestos-containing materials within portions of the renovation scope that may be disturbed during construction. Estimated Acquisition Magnitude: Approximately $22,000,000 2. PLANNED ACQUISITION STRATEGY The Government is considering utilizing an Other Transaction (OT) Agreement for each of these projects under the authority of 10 U.S.C. § 2808a. This authority is intended for military construction projects that involve testing and experimentation associated with new and emergent construction technologies or delivery methodologies to achieve benefits such as enhanced mission resilience, improved installation support, or cost and schedule reduction. The baseline delivery method under consideration is Progressive Design-Build (PDB). Phase 1 (Design & Pre-Construction): The Government and the OT Awardee will work collaboratively to advance the design, perform constructability reviews, conduct open-book cost estimating, and mitigate project risks. Phase 2 (Construction): Upon reaching an agreed-upon level of design (e.g., 60% to 90%), the Awardee will propose a Guaranteed Maximum Price (GMP). If accepted, the Government will exercise Phase 2 for construction execution. If a GMP cannot be agreed upon, the Government retains an "off-ramp" to complete the design and construct the facility via alternative methods. 3. INFORMATION REQUESTED Section 1: Company Profile Firm Name, Address, and Point of Contact (Name, Title, Phone, Email). Unique Entity ID (UEI). Socioeconomic Status (Other Than Small, Small, 8(a), SDVOSB, WOSB, HUBZone, etc.). Participating Role (Prime Contractor, Subcontractor, Design Firm, Other) Controlled Unclassified Information (CUI) & Cybersecurity Maturity Model Certification (CMMC) – Some of the projects listed above may involve CMMC requirements prior to award of any agreement. These projects may require the selected prime contractor and its subcontractor(s) to process, store, or transmit CUI and Federal Contract Information (FCI). In accordance with the CMMC program (32 CFR part 170) and USACE policy (including Alert 26-HQ-010, Rev1), CMMC may be a mandatory prerequisite prior to award. An offeror will not be eligible for award if they do not possess the required current CMMC status posted in SPRS prior to award of any agreement. Briefly describe your firm's strategy for ensuring your information systems (and those of your subcontractors) are fully compliant. Briefly detail your experience in safeguarding Controlled Unclassified Information (CUI) and managing secure communications on previous federal/military design-build projects. How do you plan to handle the exchange of CUI design packages, specifications, and drawings with subcontractors who may have varying levels of cybersecurity maturity? Briefly describe how your firm plans to process, store, or transmit CUI and Federal Contract Information (FCI). Offerors must have an active SAM registration and a current, verified BASIC confidence level assessment (or higher) posted in the Supplier Performance Risk System (SPRS) in accordance with NIST SP 800-171. Section 2: Other Transaction Authority (OTA) & Statutory Compliance For each project listed above, that you are interested in submitting a proposal, please provide separate responses to the following: Innovative Technologies & Practices: 10 U.S.C. 2808(a) authorizes transactions other than standard contracts to carry out facility repair and construction projects—including the planning, design, engineering, prototyping, piloting, and execution —enabling early contractor involvement, commercial pricing transparency, and schedule and cost efficiencies. Describe any innovative materials, sustainable building technologies, or modern construction processes (e.g., prefabrication, modular MEP systems) your firm could utilize to accelerate the schedule, reduce costs, or increase the building's life expectancy. OTA Experience: Describe your firm’s experience (if any) executing projects under an Other Transaction Agreement (OTA). Overcoming Traditional Barriers: What commercial or Government-imposed barriers (e.g., traditional FAR-based procurement limitations) make it difficult to implement innovative methods on complex military construction/renovations? How can the flexibility of an OTA help overcome these barriers? Custom Commercial Terms & Dispute Resolution: To optimize the flexibilities of the OTA framework, what specific commercial terms (e.g. tailored dispute resolution/rapid escalation mechanisms, commercial milestone payment structures, or shared intellectual property rights for innovative method) would your firm recommend the Government adopt to minimize risk or incentivize your participation? Section 3: Progressive Design-Build (PDB) / Early Contractor Involvement Information Baseline: What minimum level of detail (e.g., DD Form 1391, conceptual design, spatial programming documents) does your firm require prior to entering Phase 1 (Design & Pre-construction) to feel confident in the project's baseline viability and target budget? Collaborative Framework: What collaborative mechanisms (such as joint design charrettes, target-value design workshops, or phased scoping approvals) do you recommend the Government implement in the first 30-90 days of Phase 1 to rapidly transition from a planning document to an agreed-upon technical baseline? Open-Book Pricing: Describe your experience with "open-book" pricing and transparency during pre-construction. How do you assure the Government that subcontractor and material pricing represent fair market value? Section 4: Guaranteed Maximum Price (GMP), Risk Allocation & Compensation Off-Ramp Risk & Design Rights: If the Government and the contractor cannot reach an agreement on the GMP (the "off-ramp"), what specific compensation structures (e.g., design fees, stipends, time-and-materials) would adequately compensate your firm for Phase 1 efforts? Who should retain ownership of the design deliverables in this scenario? GMP Lock-In Milestone: In your experience with highly complex, secure administrative renovations, at what design milestone (e.g., 35%, 65%, 95%) is it most advantageous to lock in the GMP, and why? Long-Lead Procurement: How do you handle the procurement of critical, long-lead items (such as backup generators, customized HVAC chiller components, and high-security electrical switchgear) prior to establishing the final construction GMP? Section 5: Specialized Experience Secure Spaces (ICD 705): Briefly describe your firm's specific experience in constructing and accrediting Special Access Program (SAP) spaces complying with ICD 705 standards. What are the primary risk factors in delivering these facilities on time? Complex MEP Infrastructure: Briefly detail your firm’s experience in designing and constructing central energy/chiller plants, complex electrical distribution, and backup power generator facilities. Adjoining Occupied Renovation: Briefly describe your firm’s approach to planning and executing construction phases in a fully operational, high-security 24/7 headquarters environment. How do you manage noise, dust, vibration, and security sweeps to prevent mission disruption? Communication Systems: Briefly describe your firm’s experience with the integration of robust communications infrastructure, including both Contractor-Furnished/Contractor-Installed (CFCI) and Government-Furnished/Contractor-Installed (GFCI) assets. Laboratory Equipment Procurement/Coordination: Briefly describe your firm’s experience with spatial planning, detailed design, utility integration, and installation of complex laboratory environments, encompassing both Contractor-Furnished/Contractor-Installed (CFCI) and Government-Furnished/Contractor-Installed (GFCI) equipment. Section 6: Teaming & Subcontractor Integration Subcontractor Onboarding: Under a collaborative (PDB) model, how and when do you plan to onboard critical specialty subcontractors (e.g., ICD 705 security, MEP, fire protection, hazardous abatement)? Competition: Will you compete these subcontracts openly during Phase 1 pre-construction, or do you prefer bringing in established, pre-selected trade partners from day one? Section 7: Bonding & Financial Capability Surety Timelines: If construction bonds are deferred until Phase 2, what is the maximum duration your surety would hold a commitment open between the finalization of the GMP and the Notice to Proceed for construction? Funding Gap Mitigations: If funding or execution authority for Phase 2 construction is delayed (e.g., 90–180 days post-design completion due to O&M/fiscal year cycles), what contractual mechanisms (e.g., escalation clauses, right to off-ramp) would your firm require to maintain the agreement? Bonding Limits: Specify your maximum bonding limits (Single and Aggregate) as a Sole Prime Contractor and/or as a Joint Venture. Phased bonding approach: Would a phased bonding structure - where the contractor is only required to bond the value of the phase 1 effort initially, and construction bonds are deferred until the execution of phase 2 - effectively mitigate risk for your firm? 4. SUBMISSION INSTRUCTIONS Interested firms are invited to submit their responses to this RFI no later than 02 Novemeber at 12:00 P.M. Eastern Time. Submissions should be sent via email to Mr. Jacob Pridemore at Jacob.S.Pridemore@usace.army.mil in PDF format, not exceeding 15 pages (excluding company brochures or standard profiles). Please direct all questions regarding this market research notice to the primary Point of Contact listed above.
-Market Research11/02/2026

Additional Details

Solicitation Number

W912QR22R0016

Archive Date

Aug 30, 2022

Office Address

LOUISVILLE, KY, 40202-2230