GovChime
Notice ID: ab7473fa88854662a76f23ca7e816164Solicitation

Maintenance dredging for Kennebec River, Bath Maine

Archived on September 21, 2024. Original response deadline: . Full description on SAM.gov.

Overview

Response deadline
1:00 PM UTC−04:00
Posted
September 9, 2024
Notice type
Solicitation
NAICS
237990: Other Heavy and Civil Engineering Construction
Agency
Department of WarDepartment of the Army

Notice details

Office
W2SD ENDIST NEW ENGLAND
Place of performance
Phippsburg, ME, 04562
Last updated
Sep 25, 2026

Identifiers

Solicitation number
W912WJ24B0019
Notice ID
ab7473fa88854662a76f23ca7e816164

Description

The U.S. Army Corps of Engineers, New England District is issuing an Invitation for Bids on behalf of the United States Navy (USN) for maintenance dredging of two portions of the Federal Navigation Project (FNP) in the lower Kennebec River, Maine. This will be an unrestricted competitive IFB procurement requiring a hydraulic hopper dredge to perform the work. The NAICS code for the work is 237990 with a size standard of $37M. The construction will extend over a 3-4 week period. The estimated construction cost is $1,000,000 to $5,000,000. Any responsible source meeting this standard may submit a bid to be considered by the New England District. The work involves maintenance dredging for the USN of two portions of the authorized, 27-foot deep, 500-foot wide FNP in the lower Kennebec River. Dredging is required to meet the navigational requirements of newly constructed surface combatants being built and tested at Bath Iron Works. The work will restore the channel to its authorized dimensions and involves removal of a total of about 50,000 cubic yards (cy) of clean sand. Approximately 40,000 cy of material will be removed from the Doubling Point area (i.e., just below Bath) and approximately 10,000 cy of material will be removed from the Popham Beach area (at the river mouth). As part of this proposal, maintenance dredging will be performed to remove the sand-waves in the vicinity of Doubling Point to a maximum elevation of -34 feet MLLW to improve the chance that adequate depths will endure. The 40,000 cy to be removed from the channel at Doubling Point includes approximately 30,000 cy of advance maintenance dredging. Material dredged from the Doubling Point area will be placed in the previously used in-river disposal area north of Bluff Head in about 95-100 feet of water. Material dredged from the Popham Beach area will be placed at the previously used Jackknife Ledge placement site in about 40-50 feet of water. The dredging and dredged material placement work is expected to take 3-4 weeks to complete. The available work window for the dredging and placement of dredged material is from 1 December 2024 to 1 March 2025.

Full description on SAM.gov

Award Overview

No prior contract identified

No prior award matched this notice's agency, NAICS, place of performance and PSC within 18 months. It may be a new requirement.

Contacts

Contracting Officer

Primary Contact

Documents

No documents available.

Lifecycle

Solicitation:W912WJ24B0019
  1. Pre-Solicitation
  2. Solicitation

Award typically follows within 30–90 days after the response deadline. (estimate)

  1. Pre-SolicitationJul 8, 2024

    Maintenance Dredging for the United States Navy of the Federal Navigation Project (FNP) in the lower Kennebec River, Bath and Phippsburg, Maine.

    Notice 5ccbfbb7f68c4bb7ae62d4efbf4a0234 on SAM.gov

  2. 7×
    SolicitationCurrentAug 6, 2024

    Maintenance dredging for Kennebec River, Bath Maine

    Notice ab7473fa88854662a76f23ca7e816164 on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline
The Isle au Haut Thoroughfare Federal Navigation Project, located between Isle au Haut, Maine and Kimball Island, Maine on the outskirts of Penobscot Bay, about six miles southeast of Stonington and 25 miles east of Rockland. The Federal Navigation Project consists of a -6-foot Mean Lower Low Water (MLLW) deep by 75-foot wide extending 1,200-foot in length through the shoal in the thoroughfare.The proposed work consists of mechanically dredging approximately 3,355 cubic yards (cy) (1,183 cy required, plus 2,172 cy overdepth) of shoaled material consisting of highly compacted coarse sand and gravel, with areas of cobbles and isolated small boulders from the channel. Due to the material type, a mechanical dredge with the ability to dig highly compacted coarse sand and gravel will be required. The proposed action is to dredge to the authorized depth of -6-foot MLLW plus an additional 1-foot of required advance maintenance with an additional allowable 1-foot of overdepth (e.g. -7-foot MLLW required + 1-foot allowable OD). One-time, advanced maintenance is approved for the entirety of the 1200-foot long authorized channel. The dredged material will be placed at the Flake Island Disposal Site (FIDS) which is approximately 1 nautical mile northwest of the FNP. Placement of the dredged material (sand, gravel and cobble) at Flake Island Disposal Site will benefit both juvenile lobster habitat and juvenile cod by increasing the areas habitat complexity.The anticipated allowable dredging window is between September 15 and April 1 to avoid impacts to spawning shellfish, benthic resources, Essential Fish Habitat (EFH) of federally managed species, threatened and endangered species and interactions with mobile fishing gear.
-Solicitation11/10/2026
Removal of Navigation Obstruction, Portland Harbor, Portland, ME
-Solicitation06/12/2026
Maintenance Dredging, Wareham Harbor, Wareham, MA
-Solicitation01/21/2026
The U.S. Army Corps of Engineers, New England District will be issuing an Invitation for Bids on for the Bar Harbor Breakwater Repair Project, Bar Harbor, Maine. This will be an unrestricted Invitation for Bid. The NAICS code for this procurement is 237990 with a size standard of $45M. The solicitation requirements and contract documents to include instructions for submission and the response date will be available on or about October 2025 with construction to begin in the spring of 2026. The anticipated period of performance is 14 months. The estimated construction cost is expected to range from $10,000,000 to $25,000,000.The Bar Harbor Breakwater extends approximately 2,500 linear feet southwest from Bald Porcupine Island and was constructed between 1889 and 1916. The final design of the breakwater consisted of a 20-ft crest at 11 ft MLLW with 1H:1V side slopes, although the crest width was only constructed to 10-ft wide. The proposed work consists of repairing two large portions and a few small areas of a rubble mound breakwater structure that has been damaged from storms since its completion in 1916.There are two (2) repairs areas plus multiple small minor repair areas. Repair Area 1 is approximately 800 feet long and Repair Area 2 is approximately 850 feet long. Repair Area 2 and the minor repair zones are optional items. Anticipated stone required for Repair Area 1 includes approximately 8,800 tons of 6-10 ton armor stone and for Repair Area 2, includes approximately 5,900 tons of 6-10 ton armor stone. The minor repair areas are isolated locations of damage that are estimated to need 2-3 new armor stones to restore the structure. The repair areas will be constructed with 1.5H:1V side slopes.The work includes mobilization and demobilization, the furnishment and delivery of stones, removal/rehandling/resetting of existing stones, and placement of armor stone for tie-in between the repair area and the existing structure. The reinforcement work will require substantial moving and rehandling of existing stones to obtain the required interlocking placement and construction tolerances.Construction, stone delivery, and access will be by water. Access to the breakwater by land is unavailable and no work should be completed from the crest of the breakwater. There are no time of year restrictions. Environmental coordination and permitting has been completed by the U.S. Army of Engineers, New England District. Low tide water depths in the vicinity of Repair Area 1 are approximately 10 feet and Repair Area 2 are approximately 50 feet, and the average tidal range is approximately 11 feet. The area is subject to wave action. No spudding or anchoring into the existing structure is permitted.
-Solicitation12/16/2025
The U.S. Army Corps of Engineers, New England District will be issuing Invitation for Bids for the Wareham Harbor Federal Navigation Project, located in Wareham, Massachusetts. This procurement is a Small Business Set Aside Invitation for Bid (IFB). The NAICS code for the work is 237990 with a size standard of $37M. Construction is expected to take about five months to complete. The estimated construction cost is $1,000,000 to $5,000,000. Any responsible source meeting this standard may submit a bid to be considered by the New England District. The Wareham Harbor FNP consists of a 2.4 mile long, 9-foot deep Mean Lower Low Water (MLLW) channel. The channel is comprised of several reaches of varying widths (100-ft to 250-ft widths) to include the entrance channel through Cromeset Neck Reach, Quahaug Bar Reach, Parkwood Beach Reach, and the Inner Harbor Reach. The proposed work consists of mechanically dredging up to appropriately 52,000 cubic yards (CY) of shoaled material over a 10.2-acre area. Most of the material is fine-grained/silt and will be transported by scow and placed at Cape Cod Bay Disposal Site (CCBDS), approximately 35 miles away. Transit from Wareham to CCBDS will occur through the Cape Cod Canal. A smaller portion of the material is sand (approx. 1,000 CY) and will be placed beneficially at a nearshore site off of Church's Beach in Cuttyhunk, Massachusetts (approximately 28 miles away). Dredging operations can start on July 1, 2026 for maintenance dredging using a mechanical dredge and placement in open water at CCBDS and Church’s Beach Nearshore Placement Site. All work must be complete by December 31, 2026. In order to accomplish all dredging requirements within the specified dredging window the Contractor will need to meet a production rate of at least 28,500 CY per 30 consecutive calendar day period. This is not an invitation for bids at this time. The solicitation requirements and contract documents to include instructions for submission and the response date will be available on or about mid-November 2025. Neither telephonic, mailed nor faxed requests for hard copies of this solicitation will be accepted. The solicitation will only be available online; in order to download the solicitation offerors must access the System of Award Management website (https://www.sam.gov/) and the Procurement Integrated Enterprise Environment (https://piee.eb.mil/). All responsible sources may submit a bid which shall be considered by the New England District. Additional questions may be emailed to the Contract Specialist at heather.m.skorik@usace.army.mil. The U.S. Army Corps of Engineers, New England District will be issuing Invitation for Bids for the Wareham Harbor Federal Navigation Project, located in Wareham, Massachusetts. This procurement is a Small Business Set Aside Invitation for Bid (IFB). The NAICS code for the work is 237990 with a size standard of $37M. Construction is expected to take about five months to complete. The estimated construction cost is $1,000,000 to $5,000,000. Any responsible source meeting this standard may submit a bid to be considered by the New England District. The Wareham Harbor FNP consists of a 2.4 mile long, 9-foot deep Mean Lower Low Water (MLLW) channel. The channel is comprised of several reaches of varying widths (100-ft to 250-ft widths) to include the entrance channel through Cromeset Neck Reach, Quahaug Bar Reach, Parkwood Beach Reach, and the Inner Harbor Reach. The proposed work consists of mechanically dredging up to appropriately 52,000 cubic yards (CY) of shoaled material over a 10.2-acre area. Most of the material is fine-grained/silt and will be transported by scow and placed at Cape Cod Bay Disposal Site (CCBDS), approximately 35 miles away. Transit from Wareham to CCBDS will occur through the Cape Cod Canal. A smaller portion of the material is sand (approx. 1,000 CY) and will be placed beneficially at a nearshore site off of Church's Beach in Cuttyhunk, Massachusetts (approximately 28 miles away). Dredging operations can start on July 1, 2026 for maintenance dredging using a mechanical dredge and placement in open water at CCBDS and Church’s Beach Nearshore Placement Site. All work must be complete by December 31, 2026. In order to accomplish all dredging requirements within the specified dredging window the Contractor will need to meet a production rate of at least 28,500 CY per 30 consecutive calendar day period. This is not an invitation for bids at this time. The solicitation requirements and contract documents to include instructions for submission and the response date will be available on or about mid-November 2025. Neither telephonic, mailed nor faxed requests for hard copies of this solicitation will be accepted. The solicitation will only be available online; in order to download the solicitation offerors must access the System of Award Management website (https://www.sam.gov/) and the Procurement Integrated Enterprise Environment (https://piee.eb.mil/). All responsible sources may submit a bid which shall be considered by the New England District. Additional questions may be emailed to the Contract Specialist at heather.m.skorik@usace.army.mil.
-Pre-SolicitationOpen