GovChime
Notice ID: 618f69310d714616bc60117499969be7Award NoticeAwardedArchived

Award W91QF4-26-B-A013 - Installation Lightning Protection (Insp-Test-Rpr)

Awarded on September 24, 2026. Full description on SAM.gov.

Awarded tounder W91QF4-26-C-A013 (source: SAM.gov award notice)• $359.2K

Overview

Posted
September 24, 2026
Notice type
Award Notice
Set-aside
Small Business Set Aside - Total
NAICS
238290: Other Building Equipment Contractors
Agency
Department of WarDepartment of the Army

Notice details

Office
AMC.ACC.MISSION INSTALLATION CONTRACTING COMMAND.FDO EUSTIS.W6QM MICC-FT LEAVENWORTH
Place of performance
Fort Leavenworth, Kansas, 66027
Last updated
Oct 28, 2026
First published
Last updated on SAM.gov
Award date
Sep 24, 2026
Award amount (SAM.gov award notice)
$359.2K

Identifiers

Solicitation number
W91QF4-26-C-A013
Notice ID
618f69310d714616bc60117499969be7
Award number (PIID)
W91QF4-26-C-A013

Description

Awarded in accordance FAR Part 14 Sealed Bidding Procedures in Section M.

Full description on SAM.gov

Award Overview

Award Number

W91QF4-26-C-A013

Award Amount (SAM.gov award notice)

$359.2K

Award Date

Sep 24, 2026

Awardee

Awardee UEI

ULBZXDY9GAB8

Awardee CAGE Code

9GVQ8

Awardee Address

Indianapolis, IN 46240, UNITED STATES

Line Item Number

0001-0002

Original Solicitation

Notice ID: 618f69310d714616bc60117499969be7

Posted Date: Sep 24, 2026

Original Response Deadline: Not specified

Contract Details

Contract data not yet available

Contract details typically appear within 2-4 weeks after award; DoD awards are published about 90 days after signature.

Contacts

Contracting Officer

Primary Contact

Secondary Contact

Documents

Files (16)

  • 3-SF30_Amednment-0002-All_CLINS_JOB_and_Add_Attch12_QandA.pdf

    3.9 MBAdded in Solicitation version 8Posted
    Download
  • 1-IFB-CONF_COPY-Amend-0001-W91QF426BA013_LPS.pdf

    6.3 MBAdded in Solicitation version 3Posted
    Download
  • 2-SF30_Amendment-0001-Add_52.217-9_Update_CLIN_0001_and_1001.pdf

    3.8 MBAdded in Solicitation version 3Posted
    Download
  • 0-IFB-W91QF426BA013_Lightning_Protection_System.pdf

    7.2 MBAdded in Solicitation version 2Posted
    Download
  • Attch-1-Facilities_List-TE-A.pdf

    91 KBAdded in Solicitation version 2Posted
    Download
  • Attch-2-Facilities_POC_List-TE-A1.pdf

    145 KBAdded in Solicitation version 2Posted
    Download
  • Attch-3-Drawings_and_Test_Results-TE-B.pdf.pdf

    27 MBAdded in Solicitation version 2Posted
    Download
  • Attch-4-SOW_LPS-TE-C-REV-1.pdf

    845 KBAdded in Solicitation version 2Posted
    Download
  • Attch-5-Previous_Completed_Finalized_Building_Reports-TE-D.pdf

    5.5 MBAdded in Solicitation version 2Posted
    Download
  • Attch-6-ufc_3_575_01_2012_c1-TE-E.pdf

    1.0 MBAdded in Solicitation version 2Posted
    Download
  • Attch-7-UL_Lightning_Protection-TE-F.pdf

    653 KBAdded in Solicitation version 2Posted
    Download
  • Attch-8-Sample LV-DES-LAC-APPLICATION-TE-G.pdf

    419 KBAdded in Solicitation version 2Posted
    Download
  • Attch-9-Sample_Key_Personnel_Roster-TE-H.pdf

    663 KBAdded in Solicitation version 2Posted
    Download
  • z-Attch-10-iWATCH_Army_Training_for_Contractors-TE-I.pdf

    1.6 MBAdded in Solicitation version 2Posted
    Download
  • z-Attch-12-QandA_Lightning_Protection.pdf

    56 KBAdded in Solicitation version 8Posted
    Download
  • z-Attch-11-CONST_WD-KS20260053_dtd-18May2026-TE-J.pdf

    1.9 MBAdded in Solicitation version 2Posted
    Download

Lifecycle

  1. 3
    Version 3SolicitationArchived

    W91QF4-26-B-A013 - Installation Lightning Protection (Insp-Test-Rpr)

    Notice 8a4193e6225a4231826bd6d9f23e9915 on SAM.gov

  2. 5
    Version 5Award NoticeArchivedCurrent

    Type changed from Solicitation to Award Notice

    Award W91QF4-26-B-A013 - Installation Lightning Protection (Insp-Test-Rpr)

    Notice 618f69310d714616bc60117499969be7 on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline
The U.S. Army Corps of Engineers - New England District is issuing a Solicitation Notice for Dike B Generator Installation, Mansfield Hollow Dam, Mansfield Center, CT. THE WORK CONSISTS OF: The Contractor shall furnish all necessary materials, equipment, and labor required to construct and commission a new power system for the Dike B Operator unit. The scope of work involves comprehensive site preparation to support the construction of a reinforced concrete generator pad and the installation of secure perimeter fencing. The Contractor is responsible for the procurement and installation of a standalone, propane-powered generator and a corresponding propane fuel storage tanks. Following the physical installation, the Contractor shall execute all final electrical connections and integration into the existing sluice gate operator unit and control panel. All work shall comply with all applicable federal laws and codes, and shall be completed in accordance with the Statement of Work. This procurement is set-aside for small business vendors. The applicable NAICS code is 238290 with a Small Business Size Standard of $22 Million. ALL VENDORS MUST HAVE AN ACTIVE REGISTRATION IN SAM.GOV AT THE TIME OF SUBMISSION IN ORDER TO BE CONSIDERED. ANY VENDOR THAT DOES NOT HAVE AN ACTIVE SAM.GOV REGISTRATION WILL BE REJECTED AS NON RESPONSIVE.
-Solicitation11/18/2026
US Goverment is posting for Pre-Solicitaion for Exterior Cipher Locks & Exit Hardware Retrofit, Schofield Barracks, HI. This is Pre-Solicitation notice only. Please don't send us quote for this time. Please see attached for more detail with SALIENT CHARACTERISTICS.
-Pre-Solicitation11/20/2026
This acquisition is for a a non-personal services contract to provide facility maintenance services and certain related facility management services at Fort Hood to include operation, preventative maintenance (PM) and corrective maintenance (CM) service (M and S) for approximately 136 automatic doors, 3,375 overhead doors (some hangers), and commercial doors for preventative and corrective (on demand) maintenance at the Fort Hood Army Installation, Fort Hood, Texas. This requirement also includes certain facility management and support services, as defined in this PWS, at US Army Garrison Fort Hood. The Contractor shall provide required PM and (CM) services in compliance with all code; criteria; regulations; and Federal, State, and local laws. All work shall be performed at Fort Hood, Texas, which consists of the Main Cantonment, West Fort Hood, and all areas under the control of Fort Hoods Installation or Installation considered Real Property. AMENDMENT 1: The purpose of amendment 1 is to incorporate site visit information detail. Location: FT Hood, TX. Date: 6 August 2026 Time: 1:30 PM CST. Attachments enclosed. AMENDMENT 2: Extend proposal due date to 14 August 2026, 1:00 PM CST (Posted to GPE/Sam.gov on 7 Aug 2026). AMENDMENT 3: The purpose of amendment 3 is to incorporate revised documents. Please see the updated Solicitation Amendment 3 for details. AMENDMENT 4: The purpose of amendment 4 is to communicate revisions to the evaluation factors detailed in RFO 52.212-2, Evaluation-Commercial Products and Commercial Services. (Deviation 2026-O0038). Please see updated solicitation attachment: Solicitation Amendment 4_W912DY26RA0760001_12 Aug.
-AwardedOpen
CSS Project #99178 - Install Facility Lightning Protection System in Morgantown, WV (WV029)
-Solicitation09/23/2026
As of 18 August 2026: Amendment 0001 posted to respond to contractor RFis. The New York District Army Corps of Engineers intends to award a contract for a Request for Proposal for the Design and Installation of 3M Fall Protection Systems Davit Arm and Detent Anchors at AFO. The Project has four main requirements:(a) Engineering Assessment and Design The contractor will be required to evaluate the required installation sites for fall protection equipment and develop a Design Document to appropriately install the equipment.(b) Install Government Furnished Equipment (GFE) The Government will provide the fall protection equipment to be installed. The contractor will provide 3M certified installers and install the equipment per the design.(c) Testing and Inspection The contractor will test and inspect all installed equipment to ensure it will function as intended.(d) End User Training The contractor will provide a training session for AFO employees that will use and maintain the equipment. Offerors should be regularly engaged in the business of installing fall protection systems and be able to provide 3M Certified Installers.
-Solicitation08/31/2026

Additional Details

Solicitation Number

W91QF4-26-C-A013

Archive Date

Oct 9, 2026

Office Address

FORT LEAVENWORTH, KS, 66027-0000