Y--SODA MTN AGGREGATE

Awarded on August 28, 2020. Full description on SAM.gov.

Awarded tounder 140L0620C0041 (source: SAM.gov award notice)• $622.2K

Overview

Posted
August 28, 2020
Notice type
Award Notice
NAICS
237310: Highway, Street, and Bridge Construction
Agency
Department of the Interior

Notice details

Place of performance
OR
Last updated
Apr 29, 2026
Award date
Aug 28, 2020
Award amount (SAM.gov award notice)
$622.2K

Identifiers

Solicitation number
140L0620R0046
Notice ID
daba619d39f5476ea44ecc7c2b09615f
Award number (PIID)
140L0620C0041

Description

SODA MTN AGGREGATE

Full description on SAM.gov

Award Overview

Award Number

140L0620C0041

Award Amount (SAM.gov award notice)

$622.2K

Award Date

Aug 28, 2020

Awardee

Awardee UEI

CJRUTQ4HQJL9

Original Solicitation

Notice ID: daba619d39f5476ea44ecc7c2b09615f

Posted Date: Aug 28, 2020

Original Response Deadline: Not specified

Contacts

Documents

No documents available.

Lifecycle

Solicitation:140L0620R0046
  1. Market Research
  2. Pre-Solicitation
  3. Solicitation
  4. Awarded

This opportunity has been awarded.

  1. Market ResearchJun 8, 2020

    Y--SODA MTN AGGREGATE

    Notice 36a3d3bec9c94e14a53008e8b8b07aeb on SAM.gov

  2. Pre-SolicitationJun 18, 2020

    Y--SODA MTN AGGREGATE

    Notice 37cb7caa24e74bcfac8765474e01fc6e on SAM.gov

  3. 2×
    SolicitationJul 6, 2020

    Y--SODA MTN AGGREGATE

    Notice d26a30fd4f9c46d49a4937585ff6b863 on SAM.gov

  4. AwardedCurrentAug 28, 2020

    Y--SODA MTN AGGREGATE

    Notice daba619d39f5476ea44ecc7c2b09615f on SAM.gov

Similar Opportunities

Title
Match
Phase
Deadline
Date: October 28, 2026 To: SAM Federal Business Opportunities From: Rachel Dyer, Contracting Officer, National Park Service, Denver Service Center Subject: Sources Sought Notice Reference: GRSM 321788 - Oconaluftee River Trail This is a Sources Sought Notice (SSN) for the purpose of conducting market research. Proposals are NOT being requested, nor accepted at this time. Responses are being requested from both large and small businesses. Purpose: The purpose of this notice is to gain knowledge regarding the type of interested businesses and their qualifications. The National Park Service (NPS) will use information obtained through this notice to develop an acquisition strategy. The Government anticipates conducting a competitive acquisition for this requirement. The amount of interest or lack thereof will determine the possibility of a small business or other socio-economical small business set-aside for the solicitation. Analysis of the quality of responses to this source sought announcement will be considered in the market research being conducted, and in the making of any small business set-aside determination for this requirement. Additional Information: No proposal package, solicitation, specification or drawings are available with this notice. Cost Reimbursement: Response to this announcement is strictly voluntary; no reimbursement will be made for any costs associated with providing information in response to this sources sought announcement or any follow-up information requests. North American Industry Classification System (NAICS) code: 237310 Small Business Size Standard: $45,000,000.00 Solicitation: The NPS anticipates issuing a request for proposals in the Spring 2027. Bonding: The NPS anticipates bid, performance and payment bonds will be required. Project Description: The National Park Service (NPS) proposes to improve the multi-use Oconaluftee River Trail, that links the gateway community of Cherokee to Great Smoky Mountains National Park. The Oconaluftee River Trail is approximately 8,400 feet, or 1.6 miles, in length and extends from the Oconaluftee Visitor Center to the park boundary with Cherokee, North Carolina. The project corridor is within and/or adjacent to sensitive natural and cultural resources. Preventing or limiting disturbance to and respecting these resources is of high importance to the park. The scope of the work includes, but is not limited to, the following: ¿ Cutting and removal of between 250 to 300 hundred mixed hardwood trees of varying size. Trees can only be felled between November 16 through March 31 of any calendar year. ¿ Widening the trail to approximately 8¿ in width, adding new aggregate subgrade and paving approximately 8,200 feet of trail with bituminous concrete pavement. ¿ Construction of a new single span steel pedestrian bridge approximately 60 feet in length and 10 feet in clear width, including new stone-faced abutments. ¿ Construction of a new integrally colored concrete multi-use recreational plaza approximately 2800 SF in area, including the construction of stone seating walls and wooden benches. ¿ Construction of approximately 200 linear feet of riverbank erosion utilizing locally harvested vegetation to create a bioengineered fill structure. ¿ Construction of a new "spur" trail to connect the Oconaluftee River Trail to the Saunooke Bridge located on the Big Cove Connector Road. This trail consists primarily of earth cuts and fills and is approximately 250 feet in length. Submittal Contents: Interested (small and large) businesses should submit the following information: (1) Company name, UEI number, address, point of contact, telephone number, and email address. (2) Business type: Classification as a Large or Small Business under the above listed NAICS, Small Business Administration (SBA) certified Historically Underutilized Business Zone (HUBZone), Veteran-Owned Small Businesses (VOSB), Service-Disabled Veteran-Owned Small Businesses (SDVOSB), SBA certified Woman Owned Small Business (WOSB), Economically Disadvantaged Woman Owned Small Business (EDWOSB). The size of a small business firm includes all parents, subsidiaries, affiliates, etc.¿see 13 CFR 121.108.) Misrepresentation of size status can result in penalties. (3) Statement regarding your company¿s bonding capacity. Letters from bonding companies are not required at this time. (4) Information demonstrating experience and capability on projects of same or similar size, scope and magnitude, and constructed under similar conditions. (5) In addition businesses may submit existing marketing materials such as capability statements and brochures. (6) UEI Number Only Submittal Due Date/Time: Thursday, November 12, 2026 no later than 9:00am Mountain Time Submit To: Rachel_dyer@ios.doi.gov
67%
Market Research11/12/2026
THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE. PROJECT NAME: CO BR UCPO Blue Mesa Road(1) Blue Mesa Road Blue Mesa Road is a 1.44-mile corridor located in Gunnison County, CO and provides access to the Bureau of Reclamation (BOR) Power Plant and Pine Creek Trailhead recreational activities on the Curecanti National Recreational Area. SCOPE OF THE WORK Schedule A: Proposed rehabilitation of 0.86 miles to replace existing gravel roadway with asphalt concrete pavement. Reconstruction/Rehabilitation, as needed, for 0.24 miles of existing asphalt to incorporate raising roadway profile at US 50 intersection, drainage improvements including replacement and/or lining of damaged culverts, relocation of traffic counters, formalize parking area with ADA stalls, signing and striping, ditch reconditioning, rockfall mitigation. Option X: Proposed rehabilitation of 0.34 miles to replace existing gravel roadway with asphalt concrete pavement from BOR gate to Blue Mesa Power Plant, drainage improvements to include replacement of damaged culverts, signing and striping, ditch reconditioning, installation of 6” electrical conduit for purposes of future automatic gate installation. Option Y: Proposed 6-inch electric conduit installation and 2 ft x 2 ft max trenching for 2,215 LF miles from the electric security gate to The Blue Mesa Power Plant. Conduit will provide future access for BOR to provide electric connection to security gate. PRINCIPAL WORK ITEMS: Schedule A: 15225-0000 Slope, Reference, and Clearing and Grubbing Control: 1.051 MILE 20301-1900 Removal of Pipe Culvert: 5 EACH 20401-0000 Roadway Excavation: 1,500 CU YD 30201-2000 Roadway Aggregate, Method 2: 2,500 CU YD 30302-1000 Ditch Reconditioning: 3,280 LN FT 40301-0100 Asphalt Concrete Pavement, Type 1: 2,500 TON 60103-0140 Concrete, Headwall for 24-Inch Pipe Culvert (L-Shaped): 3 EACH 60103-0160 Concrete, Headwall for 30-Inch Pipe Culvert: 1 EACH 60103-0280 Concrete, Headwall for 66-Inch Pipe Culvert (Includes Wingwalls): 1 EACH 60201-0800 24-Inch Pipe Culvert: 255 LN FT 60201-0900 30-Inch Pipe Culvert: 45 LN FT 60707-1200 Lining 66-Inch Pipe Culvert (HDPE Slipline): 110 LN FT 60707-1300 Lining 72-Inch Pipe Culvert (HDPE Slipline): 190 LN FT 63401-0300 Pavement Markings, Type B, Solid: 46,000 LN FT Option X: 15225-0000 Slope, Reference, and Clearing and Grubbing Control: 0.38 MILE 20420-0000 Embankment Construction: 200 CU YD 30201-2000 Roadway Aggregate, Method 2: 700 CU YD 40301-0100 Asphalt Concrete Pavement, Type 1: 650 TON 56603-0000 Reinforced Shotcrete: 180 SQ YD 60704-0000 Cleaning Culvert in Place: 7 EA 63401-0300 Pavement Markings, Type B, Solid: 8,500 LN FT Option Y: 63610-3410 Conduit, 6-Inch, HDPE (Schedule 40): 2,215 LN FT 63621-1000 Utility Box, Pullbox: 6 EA 63622-0000 Utility Trench: 2,215 LN FT ANTICIPATED SCHEDULE Advertisement: November 2026 Award: January 2027 NTP: April 2027 Construction: May 2027- October 2027 ESTIMATED COST RANGE: Between $2,000,000 and $5,000,000 A NON-MANDATORY PRE-BID SITE VISIT WILL BE HELD NOVEMBER 4TH, 2026 AT 10:00AM. PLEASE SEE ATTACHEMENTS FOR ADDITIONAL INFORMATION
62%
Pre-SolicitationOpen
SOLICITATION ID: 6982AF27B000004 PROJECT NUMBER: CO FTNP ROMO 407(1) PROJECT NAME: Holzwarth Culvert PROJECT DESCRIPTION: This project will replace the deficient Holzwarth Culvert (Structure No. 1520-029S), a six-barrel corrugated metal arch pipe culvert on the Holzwarth Access Road with a steel girder bridge. Located in Rocky Mountain National Park, approximately nine miles north of Grand Lake, CO, along US HWY 34 at an elevation of 8,900 feet, the culvert conveys flow from the Colorado River and provides access to the Holzwarth Historic Site. The purpose of this project is to prevent future roadway damage and flooding while maintaining access to employee housing, the historic site, and National Park Service and Forest Service recreation opportunities. SCOPE OF THE WORK: The project will consist of removal of the existing six barrel culvert and construction of a new steel girder bridge with a cast in place concrete deck. New bridge abutments and micropiles. Temporary stream diversion and riprap. New aggregate roadway surfacing. Relocation of an existing electrical line. Relocation of existing historic head gates into a new concrete slab. The site is accessible on foot a quarter mile past the locked gate at the south end of the Holzwarth Historic Site Parking Lot and along the Holzwarth Culvert Access Road. The Holzwarth Culvert Access Road is approximately 13’ wide with tight turns. Temporary widening will be necessary to prevent truck off tracking on to sensitive environmental resources. A temporary truck turnaround will also be necessary as no construction access is allowed more than 100’ west of the bridge. PRINCIPAL WORK ITEMS: 20304-2000 Removal of Bridge: 1 EACH 30202-2000 Roadway Aggregate, Method 2: 120 TON 55504-0000 Prefabricated Steel Bridge (10’ wide x 48’ long modular steel vehicular bridge): 1 LPSM 56701-0000 Micropile (8.68” dia.): 180 LNFT 62801-0000 Temporary Stream Diversion: 1 LPSM ANTICIPATED SCHEDULE: Advertisement – September 2026 Award – December 2026 NTP – December 2026 Contract Completion – November 2027 ESTIMATED COST RANGE: Total estimated cost between $700,000 and $2,000,000.
62%
Solicitation10/27/2026
This project involves the repair and resurfacing of three parking lots on the Arapaho and Roosevelt National Forest and Pawnee National Grassland including crack sealing, pavement patching, seal coating and re-striping. NAICS code 237310 - Highway, Street, and bridge Construction as a 100% SB Set Aside. Size standard $45 Million. PSC Code Y1LB - CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, Questions Due: November 6th, 2026 at 14:00 Eastern Standard Time(EST). Quotes Due:November 23rd, 2026 at 14:00 Eastern standard Time (EST). All questions and quotes relating to this Solicitation shall be submitted to Contract Specialist, Jordan Carlsen at Jordan.Carlsen@usda.gov by the deadlines stated above. Late quotes will be rejected.
62%
Solicitation11/23/2026
Update 11/16/2026: Bid Tabulation Report posted to attachemnts. Update 11/13/2026: Bid Summary posted to attachemnts. Update 11/12/2026: Interested Vendor List Posted 11/12/2026 Update 10/30/2026: Bid opening due date has been revised from 11/04/2026 to 11/13/2026. Update 10/30/2026: Amendment_A001.pdf posted to attachments. Update 10/30/2026: QandA_10-30-2026.pdf posted to attachments. Update 10/28/2026: QandA_10-28-2026.pdf posted to attachments. Update 10/27/2026: QA_10-27-2026.pdf posted to attachments. Update 10/16/2026: QA_10-16-2026.pdf posted to attachments. Invitation for Bids (IFB) for construction project WA NP OLYM 12(8), Hurricane Ridge Rockfall Mitigation MP 9.4 The Invitation for Bids (IFB), Plans, Physical Data, and the Construction Contract Administration Document per FAR 36.211 are posted under attachments.
59%
Solicitation11/13/2026

Additional Details

Solicitation Number

140L0620R0046

Archive Date

Sep 12, 2020

Office Address

DENVER, CO, 80225